Permit: T22CM02217
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
3235 E 30TH ST
Address NEW:
3235 E 30TH ST
Apply Date:
03/29/2022
Applicant:
Description:
ADU revised to Sleeping Quarters
Permit Reviews
Permit Number - T22CM02217
Permit Status: Issued
Permit Description: ADU revised to Sleeping Quarters
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/29/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 04/19/2022 | COMPLETED |
| 10/07/2022 | RESUBMITTAL | 10/14/2022 | COMPLETED |
| 10/25/2023 | RESIDENTIAL NEW DWELLING v.2 | 11/02/2023 | IN REVIEW |
| 01/29/2024 | RESIDENTIAL NEW DWELLING v.6 | 01/29/2024 | APPROVED |
| 07/09/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/09/2025 | APPROVED |
| 12/13/2023 | RESIDENTIAL NEW DWELLING v.3 | 12/28/2023 | REQUIRES RESUBMIT |
| 01/09/2024 | RESIDENTIAL NEW DWELLING v.4 | 01/09/2024 | REQUIRES RESUBMIT |
| 11/24/2023 | RESIDENTIAL NEW DWELLING v.2 | 12/06/2023 | REQUIRES RESUBMIT |
| 01/29/2024 | RESTAMP - RESIDENTIAL v.1 | 01/29/2024 | APPROVED |
| 01/11/2024 | RESIDENTIAL NEW DWELLING v.5 | 01/23/2024 | REQUIRES RESUBMIT |
| 09/25/2023 | RESIDENTIAL NEW DWELLING v.1 | 10/12/2023 | REQUIRES RESUBMIT |
| 11/02/2023 | RESIDENTIAL NEW DWELLING v.1 | 11/03/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM02217
Permit Status: Issued
Permit Description: ADU revised to Sleeping Quarters
| Date | Description | Comments |
|---|---|---|
| 10/12/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM02217
Permite Description: ADU revised to Sleeping Quarters
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/19/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | {Activity date: 04/19/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 04/19/2022 | RSME - Mechanical Progress | N/A | Canceled | {Activity date: 04/19/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 11/02/2023 | RSBU - Building Progress | N/A | Re-inspection required | 11/2/23: no approved plans on site |
| 11/02/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 11/2/23: no approved plans on site |
| 11/02/2023 | COT - RSEL - Grounding/Bonding | N/A | Re-inspection required | 11/2/23: no approved plans on site |
| 07/17/2024 | COT - RSPL - Gas Final | N/A | Not Applicable | |
| 07/17/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Ready | |
| 07/17/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 07/17/2024 | ENGR Engineering Final | N/A | Partial Pass | 2 items, TCO4 ready but these need to be addressed for full CO release. 1) parking area on right side of property in front. 2) ramp from front door of ADU to not exceed 1 in 20 on pitch. If these items have been deleted from project then a resubmitted set of plans needs to be done and submitted to the city for review. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM02217
Permit Description: ADU revised to Sleeping Quarters
Total Completed Inspections - 18