Permit Details

Status:
Complete
Type:
Commercial Building
Address:
1410 N ORACLE RD
Apply Date:
10/13/2020
Applicant:
Vance Goodman
Description:
Temporary Certificate of Occupancy for LevelS #1, 2, 3,4 AND 5

Permit Reviews

Permit Number - T20CM07013
Permit Status: Complete
Permit Description: Temporary Certificate of Occupancy for LevelS #1, 2, 3,4 AND 5
Start Date Submittal Complete Date Status  
03/01/2021 RESUBMITTAL 03/23/2021 COMPLETED Review Details
05/05/2021 REVISION - - 1ST 05/18/2021 COMPLETED Review Details
06/02/2021 REVISION - - 2ND 06/10/2021 COMPLETED Review Details
07/06/2021 REVISION - - 3RD 07/15/2021 COMPLETED Review Details
07/15/2021 RESUBMITTAL 08/03/2021 COMPLETED Review Details
10/01/2020 COMMERCIAL - NEW 12/10/2020 COMPLETED Review Details
12/14/2020 RESUBMITTAL 02/02/2021 COMPLETED Review Details

Conditions

Permit Number - T20CM07013
Permit Status: Complete
Permit Description: Temporary Certificate of Occupancy for LevelS #1, 2, 3,4 AND 5
Date Description Comments
11/12/2020 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
11/12/2020 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
11/12/2020 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
11/12/2020 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
11/12/2020 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
11/12/2020 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
11/12/2020 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
11/12/2020 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
11/12/2020 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
10/26/2020 SPECIAL INSPECTION REQUIRED FOR OUTDOOR LIGHTING

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM07013
Permite Description: Temporary Certificate of Occupancy for LevelS #1, 2, 3,4 AND 5
Total Outstanding Inspections - 21
Last Inspection Date Description Inspector Results Comments
11/07/2022 COT - HCBU - Building Above Ceiling N/A Canceled Inspection Canceled
11/07/2022 COT - HCME - Mechanical Final N/A Canceled Inspection Canceled
11/07/2022 COT - HCEL - Electrical Intermediate N/A Canceled Inspection Canceled
11/07/2022 COT - HCBU - Masonry Pregrout N/A Canceled Inspection Canceled
11/07/2022 COT - HCEL - Electrical Above Ceiling N/A Canceled Inspection Canceled
11/07/2022 COT - FCON - Alarm - Final N/A Canceled Inspection Canceled
11/07/2022 ENGR Engineering Final N/A Canceled Inspection Canceled
11/07/2022 COT - HCBU - Exterior Clips/Sheathing N/A Canceled Inspection Canceled
11/07/2022 COT - HCBU - Building Final N/A Canceled Inspection Canceled
11/07/2022 COT - HCME - Mechanical Intermediate N/A Canceled Inspection Canceled
11/07/2022 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Canceled Inspection Canceled
11/07/2022 COT - HCBU - Excavation/Rebar/Zoning N/A Canceled Inspection Canceled
11/07/2022 COT - HCBU - Framing N/A Canceled Inspection Canceled
11/07/2022 COT - HCEL - Electrical Progress N/A Canceled Inspection Canceled
11/07/2022 COT - HCEL - Electrical Underground N/A Canceled Inspection Canceled
11/07/2022 COT - HCEL - Outdoor Lighting N/A Canceled Inspection Canceled
11/07/2022 COT - HCPL - Plumbing Final N/A Canceled Inspection Canceled
11/07/2022 COT - HCPL - Plumbing Intermediate N/A Canceled Inspection Canceled
11/07/2022 COT - HCEL - Electrical Final N/A Canceled Inspection Canceled
11/07/2022 COT - HCBU - Interior Shear Bracing N/A Canceled Inspection Canceled
11/07/2022 COT - HCBU - CofO N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Complete
Permit Number: T20CM07013
Permit Description: Temporary Certificate of Occupancy for LevelS #1, 2, 3,4 AND 5
Total Completed Inspections - 17
Date Description Inspector Results Comments
07/13/2021 COT - HCEL - Construction Power Passed {Activity date: 07/13/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved. Ok to energize construction power.

CLEARANCE: Code: TMPP}
08/30/2021 COT - HCEL - Grounding/Bonding Passed {Activity date: 08/30/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap. ufer for MB3OC ok} ; {Activity date: 08/13/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa
2 ufers on GL 3-4 on line B ok} ; {Activity date: 08/09/2021; Status: Cancelled; Inspector: DQUNN; Comment: Entered by RSALDAT1 - ca
Per Mark} ; {Activity date: 08/04/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa
Ufers ok at MB30D and SES}
09/09/2021 COT - HCPL - Rough Soil Passed {Activity date: 09/09/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to cover progress areas.} ; {Activity date: 08/13/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - ) pa
All pvc under slab at GL D-A and 5-10 ok to backfill.
} ; {Activity date: 08/04/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa
Rough ok at E - B, along GL 2.5} ; {Activity date: 07/30/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Partial. Waste line at 6” on GL: F.5-G.5; waste line (6”) on GL: 8-9/B-H. Ok to cover progress areas.

} ; {Activity date: 07/26/2021; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Not ready. Contractor cancelled. Areas flooded.} ; {Activity date: 07/19/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Partial. Waste lines at 6” on GL: 6.7-8.5/G-H; 8.5/G-E.5. Ok to cover progress areas

}
09/09/2021 COT - HCBU - Preslab Passed {Activity date: 09/09/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to place concrete in progress areas.} ; {Activity date: 09/02/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa
GL D - 5 to 10
Ok to pour} ; {Activity date: 08/25/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Partial. Slab at GL: B-H/1-5. Ok to place concrete in progress areas}
10/21/2021 COT - HCPL - Sewer Passed {Activity date: 10/21/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap
6” pvc from manhole to building connection ok to backfill.
} ; {Activity date: 10/20/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa
Next 40’ of 6” pvc main drain line, ok to backfill.} ; {Activity date: 10/19/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Sewer line (6”) on East side of project at 6’ below elevation. Approximately 35’ of trenching. Ok to cover progress.} ; {Activity date: 10/13/2021; Status: Cancelled; Inspector: DQUINN; Comment: Entered by NGARCIA3 - ca
Per Willy} ; {Activity date: 10/12/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. HCS connection has not been tapped to main sewer line at this point; 6” sewer line in place, approximately 50’ south of proposed HCS tap. Ok to cover progress areas.

} ; {Activity date: 10/13/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled}
11/05/2021 COT - FCON - Underground Pressure Passed {Activity date: 11/05/2021; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - }
11/18/2021 COT - FCON - Underground Flush Passed {Activity date: 11/18/2021; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - }
06/16/2022 COT - LCBU - Sustainability Passed {Activity date: 06/16/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved}
07/28/2022 COT - HCPL - Gas Pressure Test Passed {Activity date: 07/28/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved

CLEARANCE: Called in to SW. Gas at 1040 hours} ; {Activity date: 03/22/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Gas line for water heaters: under pressure test at 12 psi.}
07/28/2022 COT - BULD - SWG Clearance Passed {Activity date: 07/28/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - CODE}
08/22/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 08/22/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - CODE ECO/UNITS 501, 502, 503, 504, 505, 506, 507, 508, 509, 510, 511, 512, 513, 514, 515, 516, 517, 518 , 519, 520, 521, 522, 523, 524} ; {Activity date: 07/15/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Code; ECO. Ok to Set meters and energize room panels.
Level #4; Room Units: 401, 402. 403, 404, 405, 406, 407, 409, 410, 411, 412, 413, 414, 415, 416, 417, 418, 419, 420, 421, 422, 423, 424} ; {Activity date: 06/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - CODE ECO Level #3 meter sets and unit panels: 301, 302, 303, 304, 305, 306, 307, 308, 309, 310, 311, 312, 313, 314, 315, 316, 317, 318, 319, 320, 321, 322, 323, 324.} ; {Activity date: 05/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - CODE ECO/ Level #2 panels and meters for units 201, 202, 203, 204, 205, 206, 207, 208, 209, 210, 211, 212, 213, 214 215, 216, 217, 218, 219, 220, 221, 222, 223, 224. Ok to energize panels and set meters.

} ; {Activity date: 04/21/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - CODE ECO/ 101. 102, 103. 104, 105, 106, 107, 108. 109, 110, 111. 112, 113, 114 115, 116, 117, 118, 119, 120, 121, 122, 123. 124.} ; {Activity date: 07/13/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - CODE TMPP}
08/22/2022 COT - FCON - Sprinkler - Final Passed {Activity date: 08/22/2022; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - }
08/22/2022 FCON – OH Piping & Hydro Passed {Activity date: 08/22/2022; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - }
03/17/2023 COT - HCBU - Building Progress Passed
03/16/2023 COT - FCON - Fire - Final Passed
03/17/2023 COT - LCBU - Building Final Passed
03/21/2023 SITE - Zoning Final Passed

Documents

File Name Document Type  
APPLICATION REV3.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
COMPLIANCE REPORT.PDF DOCUMENTS VIEW
FINAL SIC.PDF DOCUMENTS VIEW
FLOOR TRUSS SUBMITTAL REV3.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET REV1.PDF DOCUMENTS VIEW
REV3_PLAN SET.PDF DOCUMENTS VIEW
ROOF TRUSS SUBMITTAL REV3.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
STRUC CALCS REV1.PDF DOCUMENTS VIEW
TCO 1-2-3-4.DOC DOCUMENTS VIEW
TCO FLR 1-2-3.PDF DOCUMENTS VIEW
TCO FLR1-2.PDF DOCUMENTS VIEW
TCO TEMPLATE.PDF DOCUMENTS VIEW
TCO.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COMLIANCE CERT.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
MECH SYSTEMS REPORT.PDF DOCUMENTS VIEW
MECH COMCHECK.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
SIGNED APPLICATION.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW