| 11/07/2022 |
COT - HCBU - Framing |
|
Canceled |
Inspection Canceled |
| 07/25/2022 |
COT - HCBU - Framing |
JBURGE |
Not ready for Inspection |
Entered by VVERA1 - Not ready. Contractor cancelled
|
| 07/07/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #5; Room units 517; 519; 521; 523. Ok to insulate and cover walls |
| 07/06/2022 |
COT - HCBU - Framing |
JBURGE |
Not ready for Inspection |
Entered by VVERA1 - Not ready. Contractor cancelled. Will reschedule for 7 July. |
| 07/01/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #4 East corridor
|
| 06/14/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #3; Units 301 - 324 |
| 06/07/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #4; Units 406, 407, 408, 409, 410, 418, 419, 421, 422 |
| 06/03/2022 |
COT - HCBU - Framing |
JBURGE |
Not ready for Inspection |
Entered by NGARCIA3 - Not ready. Contractor cancelled.
|
| 04/26/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #4; All units exterior walls on interior side. Ok to spray insulate. |
| 04/25/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #3, Units 301 - 307, 317. |
| 03/29/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Level #3, exterior walls. Ok to spray foam insulation. |
| 03/16/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Level #5 corridor above ceiling; studs and clips in place. |
| 03/11/2022 |
COT - HCBU - Framing |
JBURGE |
Not ready for Inspection |
Entered by NGARCIA3 - Not ready. Contractor cancelled |
| 02/24/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Pop-out at Levels 2 -4 in South courtyard area. Ok to cover exterior walls. |
| 02/23/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Pop-out at NORTHWEST corner of building at Levels 1-5. Ok to cover progress areas. |
| 02/11/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Pop-out at Southwest corner of building. Ok to cover progress areas. |
| 02/07/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Exterior pop-outs on South side of building. Ok to cover progress areas. |
| 02/03/2022 |
COT - HCBU - Framing |
JBURGE |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Contractor cancelled will reschedule for 7 February. |
| 01/28/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Pop-outs (4) on East side and South side. Ok to cover progress areas. |
| 01/26/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Two each 6” PVC vent lines for water heaters on Level #2. Extended from Level #2 to Level #3. |
| 01/07/2022 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Drain leader pop-outs on East side of building, levels #1 - #3. Ok to cover progress areas. |
| 12/27/2021 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Level #1; Units: 108, 109, Laundry Room, 110, 111, 112, 113, 114, 115, 116. |
| 12/15/2021 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. Level #1; Units #101-107. Exterior roof drains, framing for pop-outs on Level #1. |
| 12/08/2021 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial, Level #2, corridor ceiling. Ok to cover progress areas. |
| 12/07/2021 |
COT - HCBU - Framing |
JBURGE |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Contractor cancelled. Will reschedule for 8 December. |
| 12/03/2021 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. Level #1; Room Units 118, 119, 120, 121, 122, 123, 124. |
| 10/29/2021 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - . Partial. Level #1; apartment units with demising walls, screwed in place.
|
| 10/20/2021 |
COT - HCBU - Framing |
DQUINN |
Partial Approval |
Entered by VVERA1 - pa
1st floor corridor lid ok to 5/8 rock underside of floor joists. Clips and Titans ok. |