| 11/07/2022 |
COT - HCBU - Masonry Pregrout |
|
Canceled |
Inspection Canceled |
| 02/24/2022 |
COT - HCBU - Masonry Pregrout |
IVR USER |
Cancelled |
Entered by IVR USER - IVRS - RI canceled |
| 11/16/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. Trash enclosure at top out of masonry walls. Ok to place grout in progress areas. |
| 08/16/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - Pa Elevator ok to top out at 57’ |
| 08/13/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
South stairs ok to grout to top-out at 57’.
Elevator ok to grout 40 to 44 and 44 to 48’ with cleanouts |
| 08/12/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by VVERA1 - pa
Elevator 36 to 40’ and stairs 48 to 52’ ok to grout |
| 08/11/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Cancelled |
Entered by RSALDAT1 - ca
Per Mark
|
| 08/10/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by VVERA1 - pa
Elevator ok from 32 to 36’
Stairs ok from 44 to 48’
|
| 08/09/2021 |
COT - HCBU - Masonry Pregrout |
DQUNN |
Cancelled |
Entered by RSALDAT1 - ca
Per Mark |
| 08/06/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - pa
Ok to grout:
Elevator 28 to 32’
Stair 40 to 44’
|
| 08/06/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - pa
Ok to grout:
Elevator 28 to 32’
Stair 40 to 44’ |
| 08/05/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
Elevator - 24 - 28’
Stairs - 36 - 40’
Ok to grout
|
| 08/04/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - pa
Ok to grout elevator from 32 to 36’
Ok to grout stairs from 20 to 24 ‘ |
| 08/03/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - pa
Elevator shaft ok 28’ to 32 ‘
South stair shaft ok 16’ to 20’ |
| 08/02/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - pa
Stairs 24’ to 28’ and elevator 12’ to 16’ |
| 07/30/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. South stairwell walls at 22’-26’; elevator shaft walls at 16’- 20’. Ok to place grout in progress areas. |
| 07/29/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. North stairwell at 57’ topped out. South stairwell CMU walls at 18’-22’. Ok to place grout in progress areas. |
| 07/27/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. West stairwell CMU walls at 48’-52’. Elevator shaft at12’-16’; Ok to grout progress areas.
|
| 07/26/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. CMU walls in North stairwell at 44’-48’; elevator shaft at 8’-12’. Ok to grout progress areas. |
| 07/23/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Contractor canceled. Unable to get grout, batch plant closed |
| 07/22/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Contractor canceled. Inclement weather. |
| 07/21/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. North Stairwell at 40’-44’. Elevator walls at 4’-8’. Ok to grout progress areas |
| 07/20/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. CMU walls for West stairwell at 36’ - 40’. Ok to place grout in progress areas.
|
| 07/19/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. West stairwell at 51’-57’ (topped out). Ok to place grout in progress areas.
|
| 07/18/2021 |
COT - HCBU - Masonry Pregrout |
DMUNIZ |
Partial Approval |
Entered by DMUNIZ1 - PROGRESS FOR WEST STAIRWELL CMU UP TO 50'8", NORTH STAIRWELL CMU UP TO 36'. BOTH OK TO GROUT AND PROCEED. |
| 07/16/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. West stairwell walls at 42’-46’. Ok to grout progress areas. |
| 07/15/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Contractor cancelled due to inclement weather. |
| 07/14/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Contractor cancelled due to flooding and inclement weather. |
| 07/13/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. CMU walls in West Stairwell at 36’-40’; Elevator walls at 4’-8’
Ok to place grout in progress areas. |
| 07/12/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. CMU walls in North Stairwell at 28’-32’; West Stairwell at 32’-36’: ok to grout progress areas.
|
| 07/12/2021 |
COT - HCBU - Masonry Pregrout |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - PARTIAL, North stairwell CMU 28'-32' ok to grout progress.
|
| 07/09/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by VLEON1 - Partial. CMU walls in West Stairwell at 28’-32’; South Stairwell at 24”-48”. Ok to grout progress areas.
|
| 07/08/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. CMU walls in North Stairwell at 20’-24’; West Stairwell at 20’-24’. Ok to place grout in progress areas. |
| 07/07/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. CMU walls in North Stairwell at 16’-20’; CMU walls in West Stairwell at 20’-24’. Ok to grout progress areas.
|
| 07/06/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. Elevator CMU Walsall’s at -5’-2’; South Stairwell at 0’-4’; West Stairwell at16’-20’. Ok to place grout in progress areas. |
| 07/02/2021 |
COT - HCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by VLEON1 - Partial. Stairwell North and stairwell West at 12’-16’. Ok to place grout in progress areas. |
| 07/01/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Cancelled |
Entered by VLEON1 - CANCELLED PER MARK |
| 06/30/2021 |
COT - HCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by VLEON1 - pa
3rd lift ok to grout on ne and nw stairwells. |
| 06/29/2021 |
COT - HCBU - Masonry Pregrout |
ESTEVENS |
Partial Approval |
Entered by VLEON1 - Partial. Northeast and Northwest elevator shafts, second lift, 4 to 8 feet. |
| 06/28/2021 |
COT - HCBU - Masonry Pregrout |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - partial, first 4’ lift CMU North and South Stairwells ok for grout. |