Inspection Status: Canceled
Inspection History: COT - HCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 11/07/2022 |
COT - HCEL - Electrical Underground |
|
Canceled |
Inspection Canceled |
| 10/06/2021 |
COT - HCEL - Electrical Underground |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
Conduits to 2 light poles, ok to backfill. |
| 08/31/2021 |
COT - HCEL - Electrical Underground |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
3 - 3” secondary conduits each, from MB30A and MB30B, to 20’ from new transformer area, ok to backfill |
| 08/23/2021 |
COT - HCEL - Electrical Underground |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Two each 4” conduits for meter base 30B and meter base 30C, each approximately 30’ out from building. Ok to cover progress areas. |
| 08/20/2021 |
COT - HCEL - Electrical Underground |
JBURGE |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. Contractor cancelled, will reschedule for 23 August.
|
| 08/18/2021 |
COT - HCEL - Electrical Underground |
JBURGE |
Not ready for Inspection |
Entered by VVERA1 - Not ready. Contractor cancelled.
|
| 08/17/2021 |
COT - HCEL - Electrical Underground |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - pa
2 sets of 3 - 3” conduits - one from the SES, and one from MB30D. Both sets terminate within 20’ of the TEP transformer. |
| 07/13/2021 |
COT - HCEL - Electrical Underground |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial. Electric Room conduit stub ups: 2 conduits at 4”; 2 conduits at 2 1/2”; 2 conduits at 3”. Ok to cover progress areas. |
| 06/30/2021 |
COT - HCEL - Electrical Underground |
DQUINN |
Partial Approval |
Entered by VLEON1 - pa
4 - 4” conduits from SES to building electric room, ok to backfill. |