Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Canceled
Inspection History: COT - HCEL - Electrical Intermediate
Permit Number - T20CM07013
Inspection Description - COT - HCEL - Electrical Intermediate
Inspection Status - Canceled
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | COT - HCEL - Electrical Intermediate | Canceled | Inspection Canceled | |
05/05/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Level #2 panels and meters for units 201, 202, 203, 204, 205, 206, 207, 208, 209, 210, 211, 212, 213, 214 215, 216, 217, 218, 219, 220, 221, 222, 223, 224. Ok to energize panels and set meters. |
04/27/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Level #4; in wall electric for units 401 - 424. |
04/21/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by RSALDAT1 - Meter sets for level #1; units 101. 102, 103. 104, 105, 106, 107, 108. 109, 110, 111. 112, 113, 114 115, 116, 117, 118, 119, 120, 121, 122, 123. 124. ECO. OK to energize meters and panels. |
04/13/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Level #1, Unit meters and panels at 101, 102, 103, 104, 105, 106, 107, 108, 109, 110, 111, 112,113, 114, 115, 116, 117, 118, 119, 120, 121, 122, 123, 124. Ok to energize meters and panels. |
04/12/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Not ready for Inspection | Entered by NGARCIA3 - Not ready. Contractor cancelled. |
04/01/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Floor sink areas on Levels 2 - 5. NOTE: Please add inspection 01045 (Sheet rock nailing) to permit. |
03/18/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Elevator panel: Ok to set meter and energize panel. |
03/17/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Panels #1’ 2, 3, 4, 5. In place. To be energized when SES is completed. |
03/10/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Level #3; Units 301, 302, 317, 318, 319, 320, 321, 322, 323, 324. |
02/14/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Level #2; Units 208 through 214. Electric in walls; Ok to cover wall |
02/08/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Level #2; Units #201 - 207. In wall electrical. |
02/03/2022 | COT - HCEL - Electrical Intermediate | JBURGE | Not ready for Inspection | Entered by RSALDAT1 - Not ready. Contractor cancelled will reschedule for 7 February. |
12/27/2021 | COT - HCEL - Electrical Intermediate | JBURGE | Not ready for Inspection | Entered by VVERA1 - Not ready. Contractor cancelled. |
12/15/2021 | COT - HCEL - Electrical Intermediate | JBURGE | Not ready for Inspection | Entered by RSALDAT1 - Not ready. Contractor cancelled. |
12/03/2021 | COT - HCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by RSALDAT1 - Partial. Level #1; Room Units 118, 119, 120, 121, 122, 123, 124. |