Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
5650 E RIVER RD
Address NEW:
5650 E RIVER RD
Apply Date:
08/02/2019
Applicant:
N/A
Description:
SELF STORGAE
Contractors:
  • CANYON BUILDING AND DESIGN L L C

Permit Reviews

Permit Number - T19CM05544
Permit Status: C of o
Permit Description: SELF STORGAE
Start Date Submittal Complete Date Status  
01/23/2020 RESUB - SITE/GRADING ALL 03/25/2020 COMPLETED Review Details
03/25/2020 RESUBMITTAL 04/03/2020 COMPLETED Review Details
04/03/2020 RESUBMITTAL 08/25/2021 COMPLETED Review Details
08/07/2019 PLANS OK TO SUBMIT - COMM 08/15/2019 COMPLETED Review Details
08/15/2019 COMMERCIAL - NEW 11/20/2019 COMPLETED Review Details
08/25/2021 REVISION - - 1ST 09/16/2021 COMPLETED Review Details
11/20/2019 RESUB - SITE/GRADING ALL 01/23/2020 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T19CM05544
Permit Description: SELF STORGAE
Total Completed Inspections - 38
Date Description Inspector Results Comments
04/08/2020 ROOF NAILING ENEWCOMB Approved
10/30/2020 STEM WALL/RETAINING WALL JBURGE Approved Partial. Retaining wall at GL: U/4.5-7: approximately 25 ‘x14-18’. Changes as per RFI #39 and SK #14 and SK 18. Ok to place concrete in progress area.
12/16/2020 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved Partial. Exterior perimeter footings for slab at GL: 10-2/O-Q; Basement Stairwell footing; Retaining wall at GL: 17/O-Q. Ok to place concrete in progress areas.
12/22/2020 REINFORCED MASONRY PRE-GROUT JBURGE Approved Partial. Restraining wall at sub grade level at GL: 15.5-17. Ok to grout solid in progress area. 24"-60".
04/22/2021 SEWER - PRE CONSTRUCTION MTG JBURGE Approved
04/22/2021 PLUMBING - BACK WATER VALVE JBURGE Approved Partial. Water lines in place, hydro tested. Valves to be placed at a later date.
05/12/2021 PLUMBING - ABOVE CEILING JBURGE Approved Partial. West side roof drains from level #1 to basement area (3 primary drains and 3 secondary drains)
09/13/2021 PLUMBING - FINAL RSHERRY Approved WATER DISINFECTION REPORT REQUIRED
11/15/2021 PLUMBING - ROUGH, SOIL JBURGE Approved Partial. 1 1/2” domestic water line at South/Southeast side of structure. Ok to cover progress areas.
11/22/2021 FRAMING JBURGE Approved Not ready. Contractor cancelled.
12/09/2021 PLUMBING - ROOF DRAINS JBURGE Approved Partial. East portion, middle section primary and secondary roof drains.
12/17/2021 ELECTRIC - UFER JBURGE Approved Approved. Ok to cover.
12/22/2021 ELECTRIC - UNDERGROUND JBURGE Approved Partial. Conduits for light poles (2). Caisson footings for light poles. Ok to place concrete in progress areas.
12/22/2021 BUILDING PRE-SLAB JBURGE Approved . Partial. Loading dock apron at East area. Ok to place concrete in progress areas.
12/30/2021 TEP CLEARANCE - PM JBURGE Approved CODE ECO
12/30/2021 ELECTRIC - INTERMEDIATE JBURGE Approved Partial. Switch gear and panels in place. Ok to energize service and set meter.

CLEARANCE: Code: ECO
03/10/2022 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved Approved
03/10/2022 STUCCO MESH JBURGE Approved Approved
03/10/2022 U VALUE FOR WINDOW JBURGE Approved Approved
03/10/2022 FIREWALL/FIREBARRIER/FIRESTOP JBURGE Approved Approved
03/10/2022 ELECTRIC - ABOVE CEILING JBURGE Approved Approved
03/10/2022 ELECTRIC - TEMPORARY SERVICE JBURGE Approved Approved
03/10/2022 ELECTRIC - CONSTRUCTION POWER JBURGE Approved Approved
03/10/2022 ELECTRIC - OUTDOOR LIGHTING JBURGE Approved Approved
03/10/2022 PLUMBING - INTERMEDIATE JBURGE Approved Approved
03/10/2022 MECHANICAL - INTERMEDIATE JBURGE Approved Approved
03/25/2022 PLUMBING - YARD WTR LINE/TEST JBURGE Approved Approved
03/25/2022 OUTDOOR LIGHTING FINAL JBURGE Approved Approved
03/25/2022 BUILDING ABOVE CEILING JBURGE Approved Approved
04/18/2022 ELECTRIC - FINAL JBURGE Approved Approved
06/02/2022 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
06/03/2022 BUILDING - PROGRESS JBURGE Approved Approved
06/08/2022 FIRE - FINAL wmotto1 Approved
06/08/2022 FIRE - ALARM FINAL wmotto1 Approved
06/08/2022 FIRE SPKLR - FINAL wmotto1 Approved
06/17/2022 ENGINEERING - FINAL DROBERTS Approved APPROVED FOR A FULL C OF O PENDING ALL OTHER INSPECTIONS. DP IS PENDING WAITING FOR THE APPROVED PLANS FOR ALL REMAINING WORK FOR THIS SITE THAT DOES NOT AFFECT THE PEDESTRIAN INGRESS AND EGRESS FOR THE BUILDING AT ALL LOCATIONS.
06/17/2022 CERTIFICATE OF OCCUPANCY JBURGE Approved Approved. Ok to make application for Certificate of Occupancy.
06/17/2022 BUILDING - FINAL JBURGE Approved Approved

Documents

File Name Document Type  
C OF O 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
C OF O.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PERMIT.PDF CONSTRPLANS VIEW
PLAN SET REV1.PDF CONSTRPLANS VIEW
REVISION NARRATIVE.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
PERMIT DOCUMENTS VIEW
APPLICATION DOCUMENTS VIEW
TRUSS DESIGN DOCUMENTS VIEW
CODE REVIEW CHECKLIST DOCUMENTS VIEW
SOILS REPORT DOCUMENTS VIEW
SPECIAL INSPECTION CERT DOCUMENTS VIEW
STRUCTURAL CALCS DOCUMENTS VIEW
ZONING EMAIL DOCUMENTS VIEW
PLAN SET CONSTRPLANS VIEW
1_PETITION OF APPEAL TO THE BUIDING OFFICIAL.PDF DOCUMENTS VIEW
1_PLUMBING FIXTURE CALC.PDF DOCUMENTS VIEW
T19CM05544 APPEAL RESPONSE LETTER.PDF DOCUMENTS VIEW