Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T19CM05544
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/10/2022 | EXCAVATION/LAYOUT REBAR & ZON | Approved | Approved | |
| 03/31/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Footings for manager apartment/office; loading dock at Northeast corner of building. Ok to place concrete in progress areas. | |
| 12/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Exterior perimeter footings for slab at GL: 10-2/O-Q; Basement Stairwell footing; Retaining wall at GL: 17/O-Q. Ok to place concrete in progress areas. | |
| 12/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Retaining wall footing at GL: 17/O-Q; Q/15-17. Column footings at GL: Q/18; Q/21; Q/24; Q/26; GL: M-N/18; M-N/21; M-N/24; M-N/26; GL: H-I/24; H-I/26. Ok to place concrete in progress areas. | |
| 11/25/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Caissons - Q 18, 21, 24, 26. M - N 18, 21, 24, 26. H - I 24, 26 All ok to pour. |
|
| 11/23/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. 27 column pads at GL: N-T/3-9; Elevator #1 retaining walls at GL: T-U/5-7. Ok to place concrete in progress areas. | |
| 10/07/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Columns at GL: M/5; M/6; M7; P/7; P/8. Elevator #1 mat slab and walls at GL: T-U/6-8. Ok to place concrete in progress areas. | |
| 09/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Caisson footings extensions at GL: F/18; F/21; H.5/19; H.5/21. Elevator #2 pit floor at GL: C/19.5-20. Ok to place concrete in progress areas. | |
| 09/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial caisson columns extensions at GL: A/21; A-B/24; C-D/24; F/24; F/21; F/18; H-I/19; H-I/21. Ok to set forms and place concrete in progress areas. | |
| 08/28/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Caisson footings and cages at GL: A/21; F/18; F/21; H-I/19; A-B/24; C-D/24; F/24. Ok to set forms and place concrete. | |
| 07/30/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Retaining wall at GL: A/10-19. Ok to place concrete when elevation certificate has been obtained. | |
| 07/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready. Contractor cancelled. Need slab Certificate. | |
| 07/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready. Contractor cancelled. Rebar not in footings. | |
| 07/14/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Columns at GL: C-D/12; C-D/15; C-D/18; C-D/21; C/9; F/15; E/11. Ok to place concrete in progress areas. | |
| 07/08/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Columns at GL: G/4; E/4; D-E/5; F/6-7; A/6; F15; C-D/12. Ok to place concrete in progress areas. | |
| 07/02/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Column extensions at 15’6” at GL: E/4; G/4; D.75/5; F/6.25; A/6; C-D/8.5; C-D/12; F/11.5; C-D/15; F/15; C-D/18; C-D/21. Ok to place concrete in progress areas. | |
| 06/30/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Column extension to 15’6” for columns at GL: G/4; E/4; DE/5; F/6-7. Ok to set forms and place concrete. | |
| 06/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Pier caps for caisson footings at GL: N/24; Q/24; Q/18; Q/21; N/21; N/18; N/15; N/12; L/13.5; J/11.5; H/9; J/9. Ok to place concrete in progress areas. | |
| 06/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Caisson footings and cages at GL: A/6; C-D/9; CD/12; CD/15; CD/18; CD/21; F/11-12; G/13; H15; F/15. Ok to place concrete in progress areas. | |
| 06/15/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Caisson footings and cages at Gl: F/11-12 (35’); G/13 (35’); H/15 (30’); H-I/16 (35’); F/15 (30’). Ok to place concrete in progress areas. | |
| 06/12/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Caisson footings and cages at 30’-35’ at GL: A/6; CD/9; F/11-12; G/13; H/15; H-I/16; F/15. Ok to place concrete in progress areas. | |
| 06/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Caisson footings and cages at GL: J/9; J/11; MN/9-10; MN/12; L/13-14; HI/9 | |
| 06/10/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. 4 each caisson footings with 30’ cages at GL: G/4; F/6.3; H/9; J/11.5. Ok to place concrete in progress areas. | |
| 06/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Caisson footings and cages. Cages required an additional five feet to pass water area. Water removed from subject caissons. Ok to place concrete in caisson footings: J/4; HI/4; E/4; DE/5. | |
| 05/05/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready. Contractor cancelled due to water leakage in to caisson footings. Project halted until approval from soil engineers has been obtained. | |
| 05/04/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. 5 each caisson footings at GL: CC2 at 4/E; CC2 at 4/G; CC3 at 4/H.5; CC4 at 4/J; CC4 at F/6.5. Ok to place cages and place concrete. |