Permit: T19CM05544

Parcel: 109224470


Addresses:

5650 E RIVER RD

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
11/15/2021 REINFORCED MASONRY PRE-GROUT Approved Approved. All CMU Walls are topped out. Ok to place grout in progress areas.
11/12/2021 REINFORCED MASONRY PRE-GROUT Partial Approval . Partial. CMU Walls at U-X/1-5 at 40’ top out. Ok to place concrete in progress areas.
11/10/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial approval grid lines 1 from G to S, wall U from 1 to 4.5, and X from U to X.5 all up to 17.5 ready for the next lift
11/08/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: 4/E-N (top out); 2/Q-T at 4’-8’ above lintel.; U/3-5.5 at 8’-12’. Ok to place grout in progress areas
11/04/2021 REINFORCED MASONRY PRE-GROUT Partial Approval . Partial. CMU walls on GL: N/2-4 (top out); P-Q at 9’4”-13’4”; U/2-5.5 (top out); Elevator #1 (top out); X/1-4.5 at 4’-8’; 5.5/W-X at 4’-8’. Ok to place grout in progress areas.
11/01/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 2/Q-U at top out 38’8”; U/2-5.5 at 9’8”; 9.5/Q-T at top out 38’8”; N/2-4 at 9’4”- 12’8”. Southeast retaining wall at entry area to South spaces. Ok to place grout and concrete in progress areas.
10/27/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 9.5/Q-& at 8’-12’; U/2-7.5 at 4’-8’; N/2-4 at 4’-8’; 2/N-U at 4’-8’: on Level #3. Ok to place grout in progress areas.
10/25/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #3; masonry walls at 2-9.5/U-N at 2’8’-6’8’: N/3-4 at 2’8”; 6-7.5/U at 4’-8’; U/2.5 at 2’8”-6’8”; Q-T/9.5 at 4’8”. Ok to place grout in progress areas.
09/03/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU wall topped out on GL: 4/G.5 - N. Ok to place grout in progress areas.
08/31/2021 REINFORCED MASONRY PRE-GROUT Partial Approval . Partial. CMU walls on GL: A.5/21-24 (top out); 24/A.5-G (top); Q/9.5 - 13 (top out); 4/G- N at 32’ - 36’. Ok to grout progress areas.
08/27/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU Walls on GL: A.5/21-24 at 42’ top out; 24/Q-G at 42’ top out; 24/A.5 - F at 34’-38’; Q/9.5 - 14 at 34’ -38’. Ok to place grout in progress areas.
08/25/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: A/21-24 at 12’-16’; 24/A-F at 12’-16’; Q/17-24 at 16’-20’; L.5/4-5 at 8’-12’; 4/I-L.5 at 8’-12’. Ok to place grout in progress areas.
08/23/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 24/Q-B.5 at 8’-12’; Q/13.3-24 at 8’-24’; Q/9.5-13.5 at 4K’-8’; 4/G-N at 4’-8’. Ok to place grout in progress areas.
08/16/2021 REINFORCED MASONRY PRE-GROUT Partial Approval PA. Second lift: GL-Q, from 9.5 to 24, GL-From B to Q, Gl-B, from 21-24.
08/12/2021 REINFORCED MASONRY PRE-GROUT Partial Approval 01020. Partial. CMU walls at 38’ (top out) on GL: A/5-7; 5/A-C; A/18.5-21. Ok to place grout in progress areas.
08/11/2021 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled due to flooding.
08/10/2021 REINFORCED MASONRY PRE-GROUT Cancelled Canceled by contractor due to rain.
08/09/2021 REINFORCED MASONRY PRE-GROUT Cancelled 5205497635
I called this number but could not leave a voicemail because his inbox was full. He never called back all day so inspection is canceled.

1020 cancel
08/05/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Grid lines G4 thru E4 to E5, to B5. Grid lines A7 Thru A19, to A21, top-out to parapet.
08/03/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. West CMU wall on GL: A/5-18 at 8’-12’; stairwell #2 at 8’-12’; elevator shaft #2 at 8’-12’ plus infill; walls at 8’-12’ on GL: G/4; A/5. Ok to place grout in progress .
07/30/2021 REINFORCED MASONRY PRE-GROUT Partial Approval . Partial. Level #2, CMU walls on GL: A/5-19 at 4’-8’; stairwell #2 topped out; elevator #2 at 4’-8’. Ok to place grout in progress areas.
07/28/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #3, CMU walls on GL: 5/B-E, E/4-5, 4/E-N, N/3-4’ all at 4’-8’. A/5-19 at 0’-4’. Ok to place grout in progress areas.
07/13/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at Elevator #1 at 16’-20’; Stairwell #1 at 17’ 4”-21’ 4”. Ok to place grout in progress areas.
07/07/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls in stairwell #1 at12’-16’; CMU walls on GL: 9.5/P-Q at 8’-12’; CMU walls on GL: 9.5-14/Q at 8’-12’. Ok to place grout in progress areas.
07/01/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 4/I-N at 8’-12’; U/2-5 at 8’-12’; 12/T-U at 4’-8’; Elevator #1 at 12’-16’. Ok to place grout in progress areas.
06/29/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU wall on GL: 2/N-U at 8’-12’. Ok to place grout in progress area.
06/24/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at Elevator #1 at 9’4”; Stairwell #1 at 9’ 4”; CMU walls on GL: U/6-8 at 8’-12’; 2/U-N at 6’-10’. Ok to place grout in progress areas.
06/22/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 19/A-C; C/19-20 at 12’-16’ (Stairwell #2); A-B/21-22 at 12’-16’; E-G/24 at 12’-16’; Q/12-16 at 12’-16’. Ok to place grout in progress areas.
06/18/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: Q/18-24 at 12’-16’; 18/F-Q at 12’-16’. Ok to grout progress areas.
06/17/2021 REINFORCED MASONRY PRE-GROUT Cancelled CANCELLED - Left voicemail for a contractor He never called back
06/16/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: Q/18-24 at 8’-12’ and 18/F-Q at 8’-12’. Ok to grout progress areas.
06/11/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: A-B/21-24 at 4’-8’; 24/A-Q at 4’-8’; Q/19-24 at 4’-8’. Ok to place grout in progress areas.
06/09/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 2/N-U at 13’4”-17’4”; Stairwell #2, on GL: A/19-21 at 8’-12’; Northwest wing wall on GL: 6/A-E at 8’-12’. Ok to grout progress areas.
06/07/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: A/4-5 at 12’-16’, A/5-19 at 8’-12’. Ok to place grout in progress areas.
06/03/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: Stairwell #2 at 4’-8’; A/7-21 at 4’-8’; A/5-7 at 8’-12’; 1/C-F at 8’-12’. Ok to place concrete in progress areas.
06/01/2021 REINFORCED MASONRY PRE-GROUT Cancelled CANCELLED CONTRACTOR NEVER CALLED BACK
05/27/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: U/2-4 at 16’-20’; U-Q/2 at 9’4”-12’; U/4-5 at 11’2”-16’ (see SK28 for beam placement and cover); G-C/4 at 4’-8’; E/4-5 at 4’-8’. Ok to place concrete in progress areas.
05/25/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. East loading dock area at 16’- 20’. CMU wall on GL: U/2-4 at 12’ - 16’. Room k to place grout in progress areas.
05/21/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 4/E,G,H at 0’-4’; Loading dock area U-X/1-5 at 12’-16’, Elevator #1 at 12’-16’. Ok to place grout in progress areas.
05/18/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. East loading dock area on GL: U-V/1-5 at 8’-12. Ok to place grout in progress areas.
05/14/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at Elevator #1 at 8’-12’; Loading dock at 4’-8’. Ok to place grout in progress areas.
05/12/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. East loading dock on GL: U-X/1-5 at 0’-4’; Stairwell #1 at 12’-16’. Ok to place concrete in progress areas.
05/10/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: Q/14-24 at 12’-16’; 9.5/Q-U at 12’-16’. Ok to place grout in progress areas.
05/06/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 24/H-Q at 12’-16’; Q/9-10 at 12’-16’; Q/14-24 at 8’-12’. Ok to place grout in progress areas.
05/04/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU wall at GL: 25/H-I at 8’-12’. Exterior stairwell steps; rebar to be epoxied per special inspection.
04/29/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 2 - 18/9-10 at 0’-4’; Elevator #1 at 6’-10; T-2/9-10. Ok to grout progress areas.
04/28/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 24/A-F at 8’-12’; Stairwell #2 at 12’-16’. Ok to place grout in progress areas.
04/26/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls on GL: 4/M/I at 12’-16’; Stairwell #2 at 8’-12’; H-J/ 24 at 4’-8’. Ok to place grout in progress areas.
04/22/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: 4/I-N at 8’-12’; Stairwell #2 interior walls at 4’-8’; 24//J-G at 0’-4’. Ok to place grout in progress areas.
04/20/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: A/11-24 at 12’-16’; 24/A-F at 12’ - 16’; columns (2) at GL: 2/N-U at 0’-4’; U/1-2. Ok to grout progress.
04/16/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Grid line A, 10-20, 4’ over 5 bay doors and storefront lintels. Next lift @ grid line 4,G-N.
04/14/2021 REINFORCED MASONRY PRE-GROUT Partial Approval PARTIAL - Part. a CMU walls at GL: 24/A-N at 8’-12’; Elevator #2 at 16’-20’; Stairwell #2 short wall at 4’; wall at GL: A/21 at 8’-12’. Ok to place concrete in progress areas.
04/12/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at Elevator #1; at Level #1 at 32”-80”; Level #1 wall between elevator and stairwell; GL; U at 0’-4’. CMU wall at 4’-8’ on GL: 24/A-N; Elevator #2 at 17’ above Level #1; Level #1 CMU wall on GL: 4/G-I at 0’-4’. Ok to place grout in progress areas.
04/08/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: A/19-21; 24/A-F at 0”-24”. Ok to grout progress areas.
03/30/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: 24/Q-N at 16' - 20'; Elevator #2 at 16'-20', stairwell #1 at Level #1 at 8'-12'. Ok to place grout in progress.
03/25/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: N-HI/24 at 12’-16’; Stairwell #1 at 16’-20’. Ok to place grout in progress areas.
03/24/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: Q/17-24 at 16’-20’; Q/12-15 at 16’-20’; 24/Q-N at 16’-20’; 24/N-HI at 8’-12’. Ok to place grout in progress areas.
03/19/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: Q/17-24 at 8’-12’; Stairwell #1 at 12’-16’. Ok to place grout in progress areas.
03/17/2021 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled
03/12/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at 4’-8’ at GL: Q/17-24; 24/Q-H.5; wall at 12’-16’ at Gl: 9.5/R-S; exterior stairwell at 13.5 top out. Ok to grout progress areas.
03/10/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: U/9.5-10 at 8’-12’; Q/17-124 at 0’-4’; 24/H-I at 0’-24’. Ok to place grout in progress areas.
03/08/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at 12’-16’: GL: E/4-5; 5/A-E; A/1-10.5; CMU wall at 0’-8’ with clean outs at GL: 9/R-S. Ok to place grout in progress areas.
03/04/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at 8’-12’: GL: A/5-11; 5/A-E; E/5-4; 4/H-I. Elevator #2 at 0’-4’. Ok to place grout in progress areas.
03/01/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU wall at GL: A/4-5 at 4’-8’. Ok to grout progress areas.
02/22/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: Q/9-10 at 12'-16'; Elevator #1 at 12'-16'; Stairwell #1 at 12'-16'. Ok to grout progress areas.
02/19/2021 REINFORCED MASONRY PRE-GROUT Not ready for Inspection NOT READY(PROJECT MANGER MR. JEROD NEGRETTE WAS UNABLE TO REACH HIS JOB SITE SUPERINTENDANT TO SET UP A VIRTUAL MEETING
02/17/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU wall on GL: 2 at 8’-12’. Elevators #2 at 0’-4’. Ok to grout progress areas.
02/16/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Elevator pit at GL: 4-7/T-U at 8’-12’; CMU walls at GL: Q/9-12 at 7’-12’; 9-10/Q-S at 8’-12’. Ok to grout progress areas.
02/11/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU wall at 8’-12’; GL: 4/H-I-N; Center Shear wall topped out at 12’; CMU wall at 10-11/17 at 0”-48”; Stairwell #1 at 4’-8’; Elevator North wall at 4’-8’. Ok to place grout in progress areas.
02/08/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Basement level, exterior stairwell first lift at 0”-48”; Center wall at 4’-8’; Elevator shaft at 4’-8’, exterior wall at 4’-8’ GL: 4/ HI-N. Ok to grout progress areas.
02/04/2021 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Basement Level; Elevator #1 at 0’- 4’; Southeast Stairwell at 0’ - 4’; Center wall at 0’ - 4’; North wall at GL: 4/H-I at 0’ - 4’. Ok to grout progress areas.
12/22/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Restraining wall at sub grade level at GL: 15.5-17. Ok to grout solid in progress area. 24"-60".