Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 06/17/2022 |
BUILDING - FINAL |
|
Approved |
Approved |
| 04/18/2022 |
BUILDING - FINAL |
|
Partial Approval |
Partial. Ok to make application for Temporary Certificate of Occupancy for basement level and office kiosk. |
| 03/31/2022 |
BUILDING - FINAL |
|
Partial Approval |
Partial. Ok to make application for Temporary Certificate of Occupancy for Basement Level only. No pedestrian traffic on any of the remaining floors. Fire and Engineering in compliance for TCO. |
| 02/24/2021 |
BUILDING - FINAL |
|
Partial Approval |
PARTIAL (FIRST LIFT GRID LINE 11 -5 A NORTH & GRID LINE E 4- H .5, GRID LINE 4 H.I TO N. 4-3) |