Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
151 E BROADWAY BL
Apply Date:
10/06/2014
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
HOTEL
Contractors:
  • LLOYD CONSTRUCTION COMPANY INC ,

Permit Reviews

Permit Number - T14CM06599
Permit Status: C of o
Permit Description: HOTEL
Start Date Submittal Complete Date Status  
01/12/2017 REVISION - - 2ND 01/13/2017 COMPLETED Review Details
01/31/2017 REVISION - - 2ND 03/13/2017 COMPLETED Review Details
03/02/2016 COMMERCIAL - NEW 05/05/2016 COMPLETED Review Details
03/13/2017 REVISION - - 2ND 03/29/2017 COMPLETED Review Details
03/29/2017 RESUBMITTAL 05/03/2017 COMPLETED Review Details
05/05/2016 RESUBMITTAL - TI ALL 06/13/2016 COMPLETED Review Details
06/13/2016 RESUBMITTAL - TI ALL 07/21/2016 COMPLETED Review Details
06/13/2017 REVISION - - 3RD 07/06/2017 ACTIVE Review Details
07/21/2016 REVISION - - 1ST 07/22/2016 COMPLETED Review Details
07/22/2016 REVISION - - 1ST 08/08/2016 COMPLETED Review Details
10/06/2014 COMMERCIAL - NEW 03/02/2016 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T14CM06599
Permit Status: C of o
Permit Description: HOTEL
Total Outstanding Activity Conditions - 1
Date Name
10/06/2014 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T14CM06599
Permit Description: HOTEL
Total Completed Inspections - 46
Date Description Inspector Results Comments
10/17/2016 ELECTRIC - INTERMEDIATE JBURGE Approved CONDUITS IN SLAB AT LEVEL #8 - OK TO COVER.
10/17/2016 BUILDING PRE-SLAB JBURGE Approved LEVEL #8: METAL DECKING AND REBAR; REBAR AROUND SHAFTS IS TOO HIGH; BARS IN QUESTION NEED TO BE LOWERED FOR CLEARANCE TO TOP OF SLAB. OK TO POUR WHEN CORRECTIONS HAVE BEEN COMPLETED.
10/23/2016 STEM WALL/RETAINING WALL JBURGE Approved LEVEL 2.5 EAST CRASH WALL: 40 EACH MECHANICAL COUPLERS INSTALLED.
10/30/2016 PLUMBING - ABOVE CEILING JBURGE Approved LEVEL #5 - rOOM #565 (COPPER LINES 2" - 3", HOT, COLD, RETURN), LEVEL 5.5 (1/2" COPPER WATER LINES); LEVEL 6 COPPER LINES IN ALL ROOMS AND CORRIDORS EXCEPT FOR BAR AREA; LINES FROM LEVEL 6 TO LEVEL 4 ARE TESTED AND STUBBED OUT.
12/08/2016 FIREWALL/FIREBARRIER/FIRESTOP JBURGE Approved LEVEL #6 (INTERIOR COMMON WALLS) 601, 603, 607, 609, 613, 615, 617, 619, 621, 623, 626, 627, 628, 629, 632, 633, 634, 635, 636, 637, 641, 643, 645, 651, 653, 655, 657, 659, 661.
12/15/2016 PLUMBING - ROOF DRAINS JBURGE Approved ROOF DRAIN #1 SW CORNER OF BUILDING: LEVELS 8 - 5 UNDER TEST.
12/21/2016 PLUMBING - GAS PRESSURE TEST JBURGE Approved 2" GAS LINE AT LEVEL #5 AT 75 psi.
12/21/2016 PLUMBING - INTERMEDIATE JBURGE Approved LEVEL #7, GUEST ROOM #736, WASTE AND VENT LINES.
12/28/2016 FRAMING JBURGE Approved ROOM #903; PARAPET POP-OUT(NW) AREA "A"
12/30/2016 SHEET ROCK NAILING JBURGE Approved EXTERIOR WALLS (ELECTRIC ROOM - ELEVATOR #3, ROOMS 901 AND 902; SUB-FLOORING IN ROOM 903.
12/30/2016 REINFORCED MASONRY PRE-GROUT JBURGE Approved ELEVATOR #3 AT 32' LEVEL...OK TO PLACE GROUT.
12/30/2016 BUILDING - PROGRESS JBURGE Approved AREA "C", JOISTS HEAR PANELS, LEDGERS (WELDED) AND SHEAR BRIDGING. AREA "C" ROOF NAILING - METAL ROOF PANELS FOR DECKIG (SCREWS AND WELDS) OK TO PLACE INSULATION.
08/17/2017 MECHANICAL - ABOVE CEILING JBURGE Approved
08/17/2017 MECHANICAL - INTERMEDIATE JBURGE Approved
08/17/2017 PLUMBING - PROGRESS JBURGE Approved
08/17/2017 PLUMBING - YARD WTR LINE/TEST JBURGE Approved
08/17/2017 PLUMBING - ROUGH, SOIL JBURGE Approved
08/17/2017 ELECTRIC - PROGRESS JBURGE Approved
08/17/2017 ELECTRIC - TEMP POWER FOR TEST JBURGE Approved
08/17/2017 ELECTRIC - CONSTRUCTION POWER JBURGE Approved
08/17/2017 ELECTRIC - TEMPORARY SERVICE JBURGE Approved
08/17/2017 ELECTRIC - ABOVE CEILING JBURGE Approved
08/17/2017 ELECTRIC - UNDERGROUND JBURGE Approved
08/17/2017 ELECTRIC - UFER JBURGE Approved
08/17/2017 U VALUE FOR WINDOW JBURGE Approved
08/17/2017 BUILDING ABOVE CEILING JBURGE Approved
08/17/2017 FIRE SPKLR - FINAL JPEELDAVIS Approved Fire Sprinkler Approved
Kitchen Fire System Approved
Fire Alarm Approved per the submitted drawings minus the smoke control 3rd party approval. All controls and activation of the smoke control system operated properly. On field verification it was found that they needed to add four horn smoke detectors and sounders. Asked that they add the fire sprinkler panel in the FCC. Emergency and Exit lights will be completed by September. Signs for everything must be installed. System was left "Active" as of today. Ok for certifcate or Letter of TCO
08/17/2017 FIRE SPKLR - OH PIPING & HYDRO JPEELDAVIS Approved
08/17/2017 FIRE SPKLR - UG PIPING FLUSH JPEELDAVIS Approved
08/17/2017 FIRE SPKLR - UG, PIPING, HYDRO JPEELDAVIS Approved
08/23/2017 MECHANICAL - HOODS JBURGE Approved
08/25/2017 MECHANICAL - FINAL JBURGE Approved
08/25/2017 PLUMBING - FINAL JBURGE Approved
08/25/2017 OUTDOOR LIGHTING FINAL JBURGE Approved
08/25/2017 ELECTRIC - FINAL JBURGE Approved
08/25/2017 ELECTRIC - OUTDOOR LIGHTING JBURGE Approved
08/29/2017 FIRE - ALARM FINAL JPEELDAVIS Approved CLosing out on this permit but permit T17FC00050 will remian open for Simplex. OK FOR C OF O
08/29/2017 FIRE - FINAL JPEELDAVIS Approved
08/31/2017 NPPO - FINAL DROBERTS Approved
08/31/2017 SIGN - FINAL DROBERTS Approved
09/01/2017 HEALTH DEPT - FINAL 724-7908 JKINCAID Approved
09/01/2017 RIGHT OF WAY - FINAL CTREV Approved Final inspections attached to DP14-0147
09/01/2017 BUILDING - FINAL CTREVI Approved
09/01/2017 ZONING - FINAL CTREVI Approved
09/01/2017 LANDSCAPE - FINAL CTREVI Approved Final inspections attached to DP14-0147
09/01/2017 ENGINEERING - FINAL CTREVI Approved Final inspections attached to DP14-0147