Permit: T14CM06599

Parcel: 117062000


Addresses:

151 E BROADWAY BL

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
08/17/2017 REINFORCED MASONRY PRE-GROUT Approved
01/09/2017 REINFORCED MASONRY PRE-GROUT Partial Approval ELEVATOR #3 CMU WALLS AT 46' TO 54'8". OK TO GROUT PROGRESS AREAS.
01/08/2017 REINFORCED MASONRY PRE-GROUT Partial Approval ELEVATOR #3, CMU WALLS AT 38" - 46".OK TO GROUT.
01/05/2017 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALLS AT ELEVATOR #3; AT 32' - 36'. OK TO GROUT.
01/04/2017 REINFORCED MASONRY PRE-GROUT Partial Approval PARTIAL: ELEVATOR #3, CMU WALLS AT 24' TO 32'. OK TO GROUT.
12/30/2016 REINFORCED MASONRY PRE-GROUT Partial Approval ELEVATOR #3 AT 32' LEVEL...OK TO PLACE GROUT.
12/22/2016 REINFORCED MASONRY PRE-GROUT Partial Approval ELEVATOR #3; CMU WALL AT 16' - 24'
12/21/2016 REINFORCED MASONRY PRE-GROUT Not ready for Inspection ELEVATOR SHAFT #3, NOT READY.
AT 24'
12/20/2016 REINFORCED MASONRY PRE-GROUT Approved ELEVATOR #3 AT 8' - 16'. OK TO GROUT PROGRESS AREA. *NOTE: PARAPET WALL AT EXTERIOR ROOF LEVEL HEIGHTS ARE IN QUESTION. TO BE ADDRESSED BY LLOYD STAFF
12/19/2016 REINFORCED MASONRY PRE-GROUT Partial Approval ELEVATOR #3 -LEVEL #1 AT 8'. OK TO GROUT.
11/06/2016 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALL AT GL: G/1 - 4, TOP OUT AT 25' 4". OK TO GROUT
11/03/2016 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALL AT GL: G/1 - 4 (20' 8"); MEZZANINE WALL AT 8' 4", GL: D/2 - 3; LEVEL 2 ROOM 304, TOP OUT ABOVE DOOR JAMB AT 8'. OK TO GROUT PROGRESS AREAS.
10/26/2016 REINFORCED MASONRY PRE-GROUT Partial Approval LEVEL #5; ROOMS 504 - 505, CMU WALLS TOPPED - OUTAT 13' 4". OK TO GROUT PROGRESS AREAS.
10/24/2016 REINFORCED MASONRY PRE-GROUT Partial Approval LEVEL #2 - MEZZANINE ENTRY AT 4' 8", LEVEL #3 - ROOM #304 AT 4'; LEVEL #5: ROOMS 504 - 505 EXTERIOR WALLS AT 7' 4". OK TO GROUT PROGRESS AREAS.
10/23/2016 REINFORCED MASONRY PRE-GROUT Not ready for Inspection WILL RECALL FOR 24 OCT. MASONS NOT ON SITE
10/12/2016 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALLS AT GL: G-1/G-4, SECOND LEVEL AT 16' 8"; EAST STAIRS TOP-OUT AT 21' 9"; 5TH LEVEL ROOM #504 AT 12', ROOM #506 AT 12'. OK TO GROUT PROGRESS AREAS.
10/06/2016 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALLS IN GENERATOR ROOM #506 AT 9' 4"; POOL EQUIPMENT ROOM #504 AT 9' 4" - OK TO GROUT PROGRES AREAS.
10/04/2016 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALLS AT 5TH LEVEL GENERATOR ROOM (506) AT 4' 8". POOL EQUIPMENT ROOM (504), INTERIOR WALLS AT 4' 8" (EXCLUDING SOUTH WALL); 4TH LEVEL: HOTEL BOILER ROOM (404) AT 7' 4"; 3RD LEVEL: MECHANICAL ROOM (305 - 306) BLILER ROOM AT 8'; 2ND LEVEL: G1 TO WEST STAIRS AT 8'; LEVEL 1: G1 - WEST STAIRS AT 12' 8"; EAST STAIRS AT 16' 8" (LT2 LINTEL) ; NORTH WALL AT 18' 8" AT GL: A.5/3.7 - 4.3. OK TO GROUT PROGRESS AREAS.
10/03/2016 REINFORCED MASONRY PRE-GROUT Cancelled MASONRY CONTRACTOR CANCELLED.
09/30/2016 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALLS AT GL: A/8 WEST STAIRS - SOUTH WALL AT 4' 8" (CRASH BARS IN PLACE); EAST STAIRS AT 12' (BOTH SIDES); 3RD LEVEL: FIRE ROOM, LOBBY BOILER ROOM AT 4' 8", SOUTH WALL AT COLUMNS 2 - 5 AT 12' 8"; GL: 1 - 2/B, 4 - 5/B AT 26' 8". OK TO GROUT PROGRESS AREAS.