Permit: T09CM01843
Permit Details
Apply Date:
07/15/2009
Applicant:
N/A
Description:
NEW RETAIL SHELL BUILDING
Contractors:
- IN N OUT BURGER INC
Permit Reviews
Permit Number - T09CM01843
Permit Status: Final
Permit Description: NEW RETAIL SHELL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/05/2010 | RESUBMITTAL - SITE | 02/02/2010 | COMPLETED |
| 01/05/2010 | RESUBMITTAL | 02/02/2010 | COMPLETED |
| 02/10/2010 | RESUBMITTAL - SITE | 03/02/2010 | COMPLETED |
| 02/11/2010 | RESUBMITTAL | 02/25/2010 | COMPLETED |
| 02/25/2010 | RESUBMITTAL | 02/25/2010 | COMPLETED |
| 02/25/2010 | RESUBMITTAL | 03/02/2010 | COMPLETED |
| 03/08/2010 | REVISION - - 1ST | 03/17/2010 | COMPLETED |
| 03/22/2010 | REVISION - - 2ND | 04/27/2010 | COMPLETED |
| 07/15/2009 | PLANS OK TO SUBMIT - SITE | 07/17/2009 | COMPLETED |
| 07/17/2009 | SITE | 08/12/2009 | COMPLETED |
| 09/10/2009 | RESUBMITTAL - SITE ALL | 10/08/2009 | COMPLETED |
| 10/26/2009 | RESUBMITTAL - SITE ALL | 12/09/2009 | COMPLETED |
| 11/12/2009 | PLANS OK TO SUBMIT - COMM | 11/12/2009 | COMPLETED |
| 11/12/2009 | COMMERCIAL NEW | 12/09/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM01843
Permit Status: Final
Permit Description: NEW RETAIL SHELL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/15/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM01843
Permit Description: NEW RETAIL SHELL BUILDING
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2010 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 03/31/2010 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* 1) LIGHT POLE BASE AND SIGN |
| 04/12/2010 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) TOWERS AND PORCH AREAS ARE COMPLETE-OK TO DRY IN |
| 04/12/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) EXTERIOR FRAMING AND TRUSS SYSTEM COMPLETED AS PER PLANS |
| 04/20/2010 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* 1) OK TO STUCCO EXTERIOR WALLS |
| 04/20/2010 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 04/20/2010 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
| 04/27/2010 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 05/04/2010 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 1) FOOTINGS FOR TRASH ENCLOSURE |
| 05/04/2010 | ELECTRIC - TEMP POWER FOR TEST | RMORENO | Approved | IVRS - Inspection :* |
| 05/25/2010 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 05/26/2010 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 06/04/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) PROVIDE FLEX CONNECTOR PER NOTE 10 M1.0 AND DETAIL 1 M1.0 |
| 06/04/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/07/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO/RELOCATE FOR "HOUSE METER" PER R. MORENO |
| 06/08/2010 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 06/08/2010 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 06/08/2010 | PLUMBING - PRE SLAB | BBENEDON | Approved | |
| 06/08/2010 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | |
| 06/08/2010 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | |
| 06/08/2010 | ELECTRIC - PROGRESS | RMORENO | Approved | |
| 06/08/2010 | ELECTRIC - CABLE DROP | RMORENO | Approved | |
| 06/08/2010 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | |
| 06/08/2010 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | |
| 06/08/2010 | ELECTRIC - UFER | RMORENO | Approved | |
| 06/08/2010 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | |
| 06/08/2010 | FIRE - ALARM FINAL | DSIWARSKI | Approved | |
| 06/08/2010 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 06/08/2010 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 06/08/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/08/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/08/2010 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :$ |
| 06/08/2010 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 06/08/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 06/08/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 06/08/2010 | RIGHT OF WAY - FINAL | PWhiddon | Approved | |
| 06/09/2010 | FIRE - FINAL | DSIWARSKI | Approved | Letter of completion approved. CofO not ready. |
| 06/09/2010 | FIRE SPKLR - UG, PIPING, HYDRO | DSIWARSKI | Approved | |
| 06/09/2010 | SIGN - FINAL | JYBARRA | Approved |