Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/08/2010 | BUILDING - PROGRESS | Approved | IVRS - Inspection :* | |
| 05/06/2010 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) TRASH ENCLOSURE TOPPED OUT; BOND BEAM IN PLACE-OK TO GROUT, CAP AND STUCCO |
|
| 05/05/2010 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 04/29/2010 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 04/27/2010 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) TRASH ENCLOSURE CMU WALLS AT 64" OK TO GROUT 2) SCREEN WALL-S.W. PORTION APPROX 150' L.F. |
|
| 04/05/2010 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
| 03/29/2010 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* PARTIA: TRASH ENCLOSURE TOPPED OUT AT 8' - OK TO GROUT |