Permit: T08CM02020
Permit Details
Apply Date:
06/10/2008
Applicant:
N/A
Description:
RETAIL
Contractors:
- FLAGSHIP FACILITY SERVICES INC
Permit Reviews
Permit Number - T08CM02020
Permit Status: C of o
Permit Description: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/23/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 04/02/2009 | COMPLETED |
| 05/17/2010 | REVISION - - 1ST | 05/17/2010 | COMPLETED |
| 05/17/2010 | REVISION - - 1ST | 05/26/2011 | COMPLETED |
| 06/10/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 06/10/2008 | COMPLETED |
| 06/10/2008 | 3RD PARTY REVIEW-COMMERCIAL | 09/09/2008 | COMPLETED |
| 06/19/2012 | REVISION - - 1ST | 06/19/2012 | COMPLETED |
| 09/09/2008 | POST 3RD PARTY REVIEW | 11/19/2008 | COMPLETED |
| 11/19/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 11/21/2008 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02020
Permit Description: RETAIL
Total Completed Inspections - 52
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/2008 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* 20' COPPER #4 BASE |
| 10/10/2008 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* OK TO CLOSE SOUTH LIP WALL @ LOADING DOCK |
| 10/14/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* OK REMAINDER OF INTERIOR BLD. U.G |
| 10/21/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* 1. YARDWATER STUB IN AND UP 5' AND STUB OUT 2' TEST OK 2. PRE-SLAB OK FOR ROUGH SOIL |
| 10/30/2008 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* OK 13 POLE BASES NORTH & EAST LOTS |
| 11/04/2008 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* 1. TOP OUT OF MAIN BLDG. OK 2. NEED RFI FOR EPOXY OF MISSED LEDGER BOLTS |
| 11/12/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* ADD TEMP CONST. POWER TO PERMIT |
| 11/18/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* COMPLETE WORK PROVIDE TEST |
| 11/19/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* OK FOR TEMP. CONST. POWER USING EXISTING BLD. SERVICE NORTHEAST OF NEW BLD. TO FEED TEMP GFI PROTECTED OUTLETS FOR CONST. |
| 11/21/2008 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* DOCK POUR BACK OK @ LEVELERS |
| 11/24/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* CONDENSATE OK TO INSULATE |
| 12/05/2008 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* PROVIDE WET STAMPED RFI REPORT #3 AND ADDRESS BENT LEDGER BOLTS |
| 12/05/2008 | STUCCO MESH | MHENSON | Approved | IVRS - Inspection :* OK TO PROCEED ON CANOPIES E & W GRIDS NOT FINISHED |
| 12/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* OK TO POUR WEST SITE WALL 5' HIGH PER C.O.T STANDARD DETAIL 109 |
| 12/22/2008 | FRAMING | MHENSON | Approved | IVRS - Inspection :* WORKING ON UPPER EXTERIOR CANOPY OK TO PROCEED |
| 01/27/2009 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* 1. FROM BUILDING THRU CLEANOUTS AND BACK WATER TEST OK (ONLY) 2. HCS STUB INTO LOT |
| 01/27/2009 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/27/2009 | PLUMBING - BACK WATER VALVE | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/26/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 04/13/2009 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 06/03/2010 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 07/13/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER |
| 08/08/2012 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | |
| 08/27/2012 | FIRE - ALARM FINAL | CSCHULTZ | Approved | |
| 09/06/2012 | FIRE - FINAL | WMOTTO | Approved | |
| 09/10/2012 | FIRE SPKLR - FINAL | FIRE | Approved | |
| 09/10/2012 | MECHANICAL - PROGRESS | LHANLY | Approved | |
| 09/10/2012 | PLUMBING - PROGRESS | LHANLY | Approved | |
| 09/10/2012 | ELECTRIC - PROGRESS | LHANLY | Approved | |
| 09/10/2012 | BUILDING - PROGRESS | LHANLY | Approved | |
| 09/10/2012 | MECHANICAL - FINAL | LHANLY | Approved | |
| 09/10/2012 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
| 09/10/2012 | PLUMBING - FINAL | LHANLY | Approved | |
| 09/10/2012 | PLUMBING - MD GAS/PRECONST MTG | LHANLY | Approved | |
| 09/10/2012 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
| 09/10/2012 | PLUMBING - ROOF DRAINS | LHANLY | Approved | |
| 09/10/2012 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
| 09/10/2012 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
| 09/10/2012 | OUTDOOR LIGHTING FINAL | LHANLY | Approved | |
| 09/10/2012 | ELECTRIC - FINAL | LHANLY | Approved | |
| 09/10/2012 | ELECTRIC - CABLE DROP | LHANLY | Approved | |
| 09/10/2012 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
| 09/10/2012 | SHEET ROCK NAILING | LHANLY | Approved | |
| 09/10/2012 | U VALUE FOR WINDOW | LHANLY | Approved | |
| 09/10/2012 | BUILDING ABOVE CEILING | LHANLY | Approved | |
| 09/10/2012 | ZONING - FINAL | LHANLY | Approved | |
| 09/14/2012 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/01/2012 | CERTIFICATE OF OCCUPANCY | LHANLY | Approved | |
| 11/02/2012 | NPPO - FINAL | DROBERTS | Approved | |
| 11/02/2012 | SIGN - FINAL | DROBERTS | Approved | |
| 11/02/2012 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 11/02/2012 | ENGINEERING - FINAL | DROBERTS | Approved |