Permit: T08CM01986
Permit Details
Apply Date:
06/06/2008
Applicant:
N/A
Description:
SITE/FORKLIFT REPAIR & NEW OFFICE BUILDING
Architects:
- VENEZIANO, PHILIP JOHN
Contractors:
- BETTER BUILT BUILDERS INC *
Permit Reviews
Permit Number - T08CM01986
Permit Status: C of o
Permit Description: SITE/FORKLIFT REPAIR & NEW OFFICE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/06/2008 | PLANS OK TO SUBMIT - SITE | 06/06/2008 | COMPLETED |
| 06/06/2008 | SITE | 07/03/2008 | COMPLETED |
| 07/18/2008 | RESUBMITTAL - SITE ALL | 08/21/2008 | COMPLETED |
| 08/05/2008 | PLANS OK TO SUBMIT - COMM | 08/05/2008 | COMPLETED |
| 08/05/2008 | COMMERCIAL TI | 09/08/2008 | COMPLETED |
| 09/12/2008 | RESUBMITTAL - SITE ALL | 10/14/2008 | COMPLETED |
| 09/19/2008 | RESUBMITTAL | 09/24/2008 | COMPLETED |
| 09/24/2008 | RESUBMITTAL | 10/14/2008 | COMPLETED |
| 11/10/2008 | REVISION - - 1ST | 11/10/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM01986
Permit Status: C of o
Permit Description: SITE/FORKLIFT REPAIR & NEW OFFICE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/06/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM01986
Permit Description: SITE/FORKLIFT REPAIR & NEW OFFICE BUILDING
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2008 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/17/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/17/2008 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 11/18/2008 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/18/2008 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/25/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/02/2008 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* OK 3 - 2 1/2" 1 - 2" PVC CONDUIT DATA AND FEEDER TO TEP FROM BUILDING OK 3/4" PVC TO LOADING DOCK OK 3/4" PVC TO STEAM/WASH AREA |
| 12/02/2008 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* 3/4 PVC FROM BUILDING TO STEAM CLEANER UNDERGROUND TEST OK |
| 12/02/2008 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/12/2008 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* TOP OUT OF BLDG. CMU -- OK TO GROUT |
| 12/16/2008 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/09/2009 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/20/2009 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/27/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
| 01/27/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 01/27/2009 | SIGN - FINAL | JYBARRA | Approved | |
| 01/30/2009 | TEP CLEARANCE - PM | BFLORES | Approved | TEC PER D.SANTA CRUZ |
| 02/05/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* CLOSET FLANGE OK |
| 02/11/2009 | FIRE - FINAL | CSCHULTZ | Approved | |
| 02/11/2009 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* OK C OF O |
| 02/11/2009 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/11/2009 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/11/2009 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/11/2009 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 02/11/2009 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 02/12/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 02/13/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 02/13/2009 | PERMIT FINALED | MRAMBER | Approved | |
| 02/13/2009 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | |
| 02/13/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
| 02/13/2009 | MECHANICAL - FINAL | MRAMBER | Approved | |
| 02/13/2009 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | |
| 02/13/2009 | PLUMBING - PROGRESS | RLEDONNE | Approved | |
| 02/13/2009 | PLUMBING - FINAL | RLEDONNE | Approved |