Permit: T07CM03308
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
8233 S CAMINO DE CAFE
Address NEW:
8233 S CAMINO DE CAFE
Apply Date:
08/08/2007
Applicant:
TOM CATTANY
Description:
NEW METAL WAREHOUSE
Architects:
- CATTANY THOMAS A
Contractors:
- MAASLAND L L C
Permit Reviews
Permit Number - T07CM03308
Permit Status: C of o
Permit Description: NEW METAL WAREHOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/19/2008 | RESUBMITTAL | 03/19/2008 | COMPLETED |
| 04/23/2008 | RESUBMITTAL | 04/24/2008 | COMPLETED |
| 05/16/2008 | REVISION - - 1ST | 05/16/2008 | COMPLETED |
| 08/08/2007 | PLANS OK TO SUBMIT - COMM | 08/08/2007 | COMPLETED |
| 08/08/2007 | COMMERCIAL NEW | 09/12/2007 | COMPLETED |
| 10/30/2007 | RESUBMITTAL | 02/19/2008 | COMPLETED |
| 11/10/2008 | REVISION - - 2ND | 11/13/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03308
Permit Status: C of o
Permit Description: NEW METAL WAREHOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/08/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM03308
Permit Description: NEW METAL WAREHOUSE
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/02/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/02/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/03/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* TRASH ENCLOSURE FOOTING |
| 08/06/2008 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR SHEETROCK |
| 08/06/2008 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) CALL IN 03075 FOR CLOSET FLANGE INSPECTION PRIOR TO SETTING STOOLS. SEE 2006 UPC INSTALLATION STANDARDS FOR REQUIREMENTS |
| 08/06/2008 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/06/2008 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 08/06/2008 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* |
| 08/06/2008 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
| 08/06/2008 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 08/21/2008 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 09/09/2008 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 09/10/2008 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
| 09/10/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. JIROUDEK |
| 10/08/2008 | FIRE - FINAL | DRAMIREZ | Approved | |
| 10/16/2008 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* RECEIVED BACTERIA REPORT FOR POTABLE WATER SYSTEM |
| 10/28/2008 | NPPO - FINAL | ACONNOR | Approved | |
| 10/28/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 10/29/2008 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 10/29/2008 | ENGINEERING - FINAL | NKALAHAR | Approved | APPROVED SEE GRADING PERMIT T07U01716 |
| 11/14/2008 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | |
| 11/14/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/14/2008 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 11/14/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
| 11/14/2008 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
| 11/18/2008 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 11/18/2008 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
| 11/20/2008 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |