| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/08/2007 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | Impact Fee's Do Apply; South East District; Factory 5,000 Square Feet; $5,147.50 |
| 08/09/2007 | MARTIN BROWN | FIRE | REVIEW | Denied | 1) Please provide location(s) of existing fire hydrants, with dimensions to property lines. Refer to C.O.T. amendments to the 2006 IFC (section 508) for required hydrant locations. 2) Add note to site plan indicating security gate will allow 20' unobstructed access, and will be equiped with a fire department approved lock box. |
| 08/13/2007 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL. PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov IF YOU CARE TO DISCUSS. 1. Demonstrate compliance with the 2006 IECC. 2. Plumbing Sheet P1.0 specifies a 3KW Water Heater. Electrical provides for 2.5KW. Coordinate with Plumbing and clarify. 3. Provide a disconnecting means for the Water Heater. Reference NEC 422 Part III. 4. Provide load information on panel schedule for Refrigerator Ckt 26. 5. Provide load information on panel schedule for Microwave Ckt 28. 6. Provide load information on panel schedule for Receptacles Ckt 29. 7. Provide load information on panel schedule for Receptacles Ckt 31. 8. Panel schedule provides power for duct-mounted strip heater on Ckt 18,20. This was not found on the Mechanical sheets or the electrical plan. 9. Please provide more detail on the purpose of this new metal building. General Note 2 on Sheet A1.0 indicates "general manufacturing," which does not eliminate such considerations as classified locations. 10. The suspended unit heater branch circuits are to be considered as continuous loads. Reference NEC 424.3 (B). 11. Phase A and B appear to have 43,150 VA and 42,045 VA respectively, not 33770 and 33813. Panel would be overloaded with a 300A main. 12. Panel schedule indicated 300A main on panel. Line diagram indicates 400A main on panel. Please clarify. 13. Panel P disconnecting means is 3-pole. Electrical service is single-phase. Please clarify. 14. It appears that the distance between the utility transformer terminals and the service entrance is 109', not 340'. 15. The equation used to calculate fault current lacks the two as a multiplier, used in the case of a single phase system. 16. The "c" value for 500 kcmil is 26706 for non-magnetic conduit, not 25000. 17. I1 as calculated in "Short Circuit Calc", and as noted on the line diagram, have different values. 18. Panel schedule indicates "FULL RATED" and "SERIES RATED." Clarify intent. 19. For any series rating, specify the line side and load side ratings. 20. General Note A Short Circuit Calc, does not address the branch circuit circuit breakers. Please note that a three-tiered series-rated system is not available commercially. |
| 08/27/2007 | BUREAU VERITAS | BUILDING-COMMERCIAL | REVIEW | Denied | August 23, 2007 CITY OF TUCSON - FIRST CHECK Tucson Appl. No. T07CM03308 Bureau Veritas Job No. 01007-161001.070 Mr. Tom Gattanty 1202 E. Broadway Blvd. Tucson, Arizona Re: Plan Review: Metal Building Address: 8233 S. Camino De Cafe Dear Mr. Gattany Bureau Veritas North America has completed a FIRST review of the following documents on behalf of the City of Tucson: Plans: One (1) set of building plans (26 sheets, C1 through E4) Sealed by Mardonio Talavera. Dated May 14, 2007. Structural Calculations: Two (2) sets. These documents were reviewed only for their conformance to the provisions of the 2006 International Building Codes (i.e., State of Arizona and Tucson amended 2006 IRC, 2006 IMC, 2005 NEC and 2006 IPC). Please submit an itemized response letter and required number of complete and revised documents with all revisions clouded. Sincerely, Bureau Veritas North America Shelley Knuffke ICC Plans Examiner SKK;skk Re: Stories: One Occupancy: F-1/IIIB Building Area (sq. ft.): 5000 A. The following plan review comments are based on the City of Tucson Building Regulations and referred to the 2006 International Building Code. B. Please respond in writing to each comment by marking the attached comment list or creating a response letter. Indicate which detail, specification, or calculation shows the requested information. Your complete and clear responses will expedite the re-check and hopefully, approval of this project. Thank you for your assistance. C. These plan review comments are based on building code items only. If site-related comments are applicable to this project, they will be generated by others (e.g., County Engineering, Public Works, Health, etc.). GENERAL REQUIREMENTS: All plans, engineering, letters, notes and references must reflect the 2006 IBC If you have any questions regarding the above comments, please contact Shelley Knuffke at (520) 576-8400 between 8:00 A.M. to 5:00 P.M., M-F. |
| 08/29/2007 | TERRY STEVENS | ZONING | REVIEW | Denied | 08/29/07 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped development, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming. 4. A site card with DSD approvals by Fire, Zoning, Handi-cap, Engineering, and Landscape/NPPO including the approved development plan stamped for site plan approval and signatures is required before the building plan can be approved by Zoning. Two copies of the approved development plan, landscape and NPPO plans are to be submitted with the building plans packet for processing and approval as a site plan. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan. The development plan may be walked through for stamps and site card sign off. Submit the following: two copies of the stamped development plan, landscape and NPPO plans must be included with the building plans packet processed together for site approval |
| 08/30/2007 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 08/31/2007 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide updated energy code compliance calculations. Reference Section 101.4, International Energy Conservation Code 2006. 2. Provide information to show that the termination of the restroom exhaust complies with the requirements of Section 401.4.2, IMC 2006. 3. Coordinate the control of the restroom exhaust fans between the electrical drawings and the mechanical drawings to prevent the recirculation of the air from the restrooms. |
| 08/31/2007 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide waste and vent isometrics. Reference Section 103.2.3, UPC 2006. 2. Provide underground facility tracer wires per ARS 40-360.22. 3. Provide the minimum plumbing facilities required by Table 2902.1, IBC 2006, for storage occupancy. Note that the break room sink shown on the drawing is not a service sink. 4. Provide fixture descriptions for all plumbing fixtures. Reference Section 401.1, UPC 2006. 5. The maximum flow rates for plumbing fixtures shall be consistent with ARS Title 45, Chapter 1, Article 12. See text at: (http://www.azleg.state.az.us/ArizonaRevisedStatutes.asp). Reference Section 402.1, UPC 2006, as amended by the City of Tucson. 6. Show how the temperature of the hot water supply to the public lavatories is controlled. Reference Section 413.1, UPC 2006 and Section 504.3, IECC 2006. 7. Revise the water pressure calculations to include the pressure drop due to the reduced pressure backflow preventer and the correct developed pipe length from the meter to the furthest plumbing outlet (see the site plan). Reference Section 610.2, UPC 2006. 8. The 2-way cleanout shown is in violation of Section 707.6, UPC 2006. 9. Provide an end of run cleanout at the break room sink. Reference Section 707.4, UPC 2006. 10. Provide vent piping of sufficient size to comply with Section 904.1, UPC 2006. |
| 08/31/2007 | ROBERT SHERRY | WATER | REVIEW | Denied | Reduced pressure backflow prevention assemblies are required at the water meter for multi-use commercial buildings. Reference COT Ordinance 9976, http://www.tucsonaz.gov/water/docs/backflow-ord.pdf |
| 09/05/2007 | PATRICIA GILBERT | ENGINEERING | REVIEW | Denied | This building plan will be approved once the development plan has been approved and has been stamped by reviewing sections for site plan approval. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/12/2007 | VFLORES1 | OUT TO CUSTOMER | Completed |
| 09/12/2007 | VFLORES1 | REJECT SHELF | Completed |