Permit: T07CM03125
Permit Details
Apply Date:
07/25/2007
Applicant:
RELIABLE PERMIT MANAGEMENT
Description:
NEW:OFFICE BUILDING-
Contractors:
- B F L CONSTRUCTION CO INC ,
Permit Reviews
Permit Number - T07CM03125
Permit Status: C of o
Permit Description: NEW:OFFICE BUILDING-
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/31/2008 | RESUBMITTAL | 02/14/2008 | COMPLETED |
| 01/31/2008 | RESUBMITTAL - SITE | 02/14/2008 | COMPLETED |
| 02/28/2008 | RESUBMITTAL | 03/20/2008 | COMPLETED |
| 02/28/2008 | RESUBMITTAL - SITE | 03/20/2008 | COMPLETED |
| 06/26/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 06/27/2008 | COMPLETED |
| 07/25/2007 | PLANS OK TO SUBMIT - SITE | 07/26/2007 | COMPLETED |
| 07/27/2007 | SITE | 09/21/2007 | COMPLETED |
| 08/08/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 08/13/2008 | COMPLETED |
| 09/11/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 09/11/2008 | COMPLETED |
| 09/26/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 09/26/2007 | COMPLETED |
| 09/26/2007 | 3RD PARTY REVIEW-COMMERCIAL | 12/07/2007 | COMPLETED |
| 11/27/2007 | RESUBMITTAL - SITE ALL | 01/02/2008 | COMPLETED |
| 12/07/2007 | POST 3RD PARTY REVIEW | 01/02/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03125
Permit Status: C of o
Permit Description: NEW:OFFICE BUILDING-
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/25/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM03125
Permit Description: NEW:OFFICE BUILDING-
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/21/2008 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 06/05/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/09/2008 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* FIBER REINFORCED CONCRETE APPROVED SPECIAL INSPECTION |
| 06/17/2008 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 06/17/2008 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 07/08/2008 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 07/15/2008 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 08/07/2008 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 08/15/2008 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 08/18/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* OK FOR ROCK IN HARD LID AREAS |
| 08/18/2008 | FRAMING | MHENSON | Approved | IVRS - Inspection :* NEED SCREW EACH SIDE OF STUD |
| 08/25/2008 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 09/12/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 09/23/2008 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 4 COLUMN FOOTINGS E.SIDE OF BLDG. #3 SPECIAL INSPECTED PATTERSON EVANOFF |
| 10/03/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* OK FOR TILES MECHANICAL ONLY |
| 10/03/2008 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
| 10/03/2008 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 10/07/2008 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 10/24/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 10/24/2008 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 10/29/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
| 10/30/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 11/04/2008 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/04/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/06/2008 | SIGN - FINAL | JYBARRA | Approved | |
| 11/07/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/07/2008 | NPPO - FINAL | ACONNOR | Approved | |
| 11/07/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 11/07/2008 | FIRE - FINAL | LTHOMAS | Approved | |
| 11/07/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 11/10/2008 | ENGINEERING - FINAL | MAVERY | Approved | Ok for TEMP C of O Contractor needs to: 1. All remaining site work to be completed under permit T08CM00426. 2. Keep all construction debris activity and materials separated from public access. |
| 11/13/2008 | RIGHT OF WAY - FINAL | MOTERO | Approved | TEMP ONLY |
| 11/13/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | |
| 11/13/2008 | ELECTRIC - CABLE DROP | DSANTACR | Approved | |
| 11/13/2008 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | |
| 11/13/2008 | ELECTRIC - PROGRESS | DSANTACR | Approved | |
| 11/13/2008 | STEM WALL/RETAINING WALL | MHENSON | Approved | |
| 11/13/2008 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
| 11/13/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 11/13/2008 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 11/13/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 11/13/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 01/13/2009 | PERMIT FINALED | MAVERY | Approved |