| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/08/2008 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 07/07/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CENTER SECTION S.WALL OK TO GROUT 8' TO 12' |
|
| 07/01/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* ALL BUT 20' IN SOUTH WALL OK TO TOPOUT DUMPSTER OK TO TOPOUT |
|
| 06/30/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1ST LIFT FOR DUMPSTER, TOP BOND BEAM WEST 1/2 OF BLDG. |
|
| 06/27/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* OK TO GROUT W, N, EAST WALLS SW 1/2 OK TO POUR SE WALL WITH SPECIAL INSPECTION APPROVAL POUR NE CORNER SOLID |
|
| 06/26/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* OK TO GROUT 1ST LIFT OVER STEEL LINTEL/E.SIDE |
|
| 06/25/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 3RD LIFT EAST 1/2 OF BLDG. 8' TO 12' |
|
| 06/24/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 3RD LIFT WEST 1/2 EXCEPT AT WINDOW LINTEL OF BLDG. SPECIAL INSPECTED |
|
| 06/20/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 2ND LIFT A TO F 1 TO 4 EXTERIOR WALLS SPECIAL INSPECTED |
|
| 06/19/2008 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
| 06/18/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1ST LIFT EAST WALL OK TO GROUT SPECIAL INSPECTED |
|
| 06/17/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* OK TO GROUT 1ST LIFT S,W,N WALL |