Permit: T07CM02315
Permit Details
Apply Date:
06/06/2007
Applicant:
GIROUD, CHARLES ALFRED
Description:
TI:MANUFACTURING FACILITY
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T07CM02315
Permit Status: C of o
Permit Description: TI:MANUFACTURING FACILITY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/03/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 05/28/2008 | COMPLETED |
| 06/06/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 06/06/2007 | COMPLETED |
| 06/06/2007 | 3RD PARTY REVIEW-COMMERCIAL TI | 07/06/2007 | COMPLETED |
| 07/06/2007 | POST 3RD PARTY REVIEW | 07/18/2007 | COMPLETED |
| 07/18/2007 | RESUBMITTAL | 07/19/2007 | COMPLETED |
| 07/18/2007 | PLANS OK TO SUBMIT - SITE | 07/18/2007 | COMPLETED |
| 07/18/2007 | SITE | 07/19/2007 | COMPLETED |
| 08/16/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 08/16/2007 | COMPLETED |
| 10/22/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 11/06/2007 | COMPLETED |
| 12/18/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 01/07/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM02315
Permit Status: C of o
Permit Description: TI:MANUFACTURING FACILITY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/06/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM02315
Permit Description: TI:MANUFACTURING FACILITY
Total Completed Inspections - 45
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/08/2007 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* (G, G.5 AREA) DOWELS TO REPLACE SLAB AT PLUMBING TRENCHES OK |
| 08/27/2007 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 09/21/2007 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* CONTINUATION OF 4" BUILDING DRAIN UP TO 10' AFF COLUMN LINE D-5 |
| 09/21/2007 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/18/2007 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
| 10/31/2007 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* FROM METER THRU MEDIUM PRESSURE SYSTEM TO FUTURES AS SHOWN, THRU JUMPER FOR PRESSURE REDUCER TO (2) BOILERS PRESSURE TEST OK NOTE: DO NOT COVER WITHOUT INSPECTION |
| 11/07/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK TO SHEETROCK RESTROOMS |
| 11/07/2007 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* ROOMS #127, 127A & 128 FOR TEMPORARY OCCUPANCY FOR TESTING AND SET UP PURPOSES ONLY W/LIMITED ACCESS |
| 11/07/2007 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* NO PROBLEMS FOR TEMPORARY USE OF R.O + D.I WASTEWATER, CDS, CHEMICAL MIX ROOMS CONTRACTOR INFORMED NO CLEAN BACTERIA REPORT FOR POTABLE WATER SUPPLY TO BUILDING, NON-CONSTRUCTION PERSONNEL WILL BE DRINKING BOTTLE WATER SUPPLY, NO IN HOUSE RESTROOM FACILITIES AT THIS TIME |
| 11/07/2007 | NPPO - FINAL | ACONNOR | Approved | |
| 11/07/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | On-site questions |
| 11/09/2007 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 11/19/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) 100 PSI TEST ON HOT WATER HEATING PIPE NORTH UP TO COLUMN LINE D |
| 12/06/2007 | BUILDING ABOVE CEILING | GDABBS | Approved | ROOM #126 & NORTH/WEST ENTRY CORRIDOR |
| 12/06/2007 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 12/06/2007 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 12/07/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | OK TO SHEETROCK RESTROOMS SOUTH END OF BLDG. |
| 12/10/2007 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* CONTRACTOR CANCELLED |
| 12/17/2007 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* ELEVATOR SHAFT FROM 14' TO 18' -- OK TO GROUT |
| 12/20/2007 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* WELDED WIRE @ MEZZANINE - OK TO POUR |
| 12/21/2007 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 12/26/2007 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 12/28/2007 | FRAMING | GDABBS | Approved | IVRS - Inspection :* CONTRACTOR CANCELLED |
| 12/28/2007 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* CANCELLED BY CONTRACTOR |
| 03/04/2008 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
| 03/04/2008 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* |
| 04/18/2008 | ENGINEERING - FINAL | NKALAHAR | Approved | APPROVED FROM OFFICE ON DAY OFF |
| 05/14/2008 | MECHANICAL - HOOD SYSTEMS | JMILITEL | Approved | |
| 05/14/2008 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :* |
| 05/14/2008 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
| 05/14/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 05/14/2008 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 05/14/2008 | FIRE - FINAL | LTHOMAS | Approved | |
| 05/20/2008 | ELECTRIC - PROGRESS | RJIROUDE | Approved | IVRS - Inspection :* |
| 05/21/2008 | RIGHT OF WAY - FINAL | MCASTRO | Approved | PER EMAIL |
| 05/21/2008 | U VALUE FOR WINDOW | GDABBS | Approved | IVRS - Inspection :* |
| 05/21/2008 | SIGN - FINAL | JYBARRA | Approved | |
| 05/22/2008 | ELECTRIC - SERVICE UPGRADE | RJIROUDE | Approved | |
| 05/22/2008 | ELECTRIC - RECONNECT | RJIROUDE | Approved | |
| 05/22/2008 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | |
| 05/22/2008 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | |
| 05/22/2008 | ELECTRIC - SERVICE RELOCATION | RJIROUDE | Approved | |
| 05/30/2008 | MODULAR - ELECTRIC INSPECTION | RJIROUDE | Approved | IVRS - Inspection :* |
| 05/30/2008 | MODULAR - BUILDING INSPECTION | GDABBS | Approved | IVRS - Inspection :* |
| 06/02/2008 | PERMIT FINALED | BFLORES | Approved |