Inspection History Details
Inspection Status: Cancelled
Inspection History: BUILDING ABOVE CEILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2008 | BUILDING ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 02/19/2008 | BUILDING ABOVE CEILING | Partial Approval | BALANCE OF FIRST FLOOR | |
| 02/12/2008 | BUILDING ABOVE CEILING | Partial Approval | BALANCE OF MEZZ. SECOND FLOOR EXCEPT CONFERENCE ROOM #228 | |
| 02/06/2008 | BUILDING ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 01/17/2008 | BUILDING ABOVE CEILING | Partial Approval | CEILING GRID @ 201F EXCEPT CLOSURE AREA ALONG EAST EXT. WALL | |
| 01/16/2008 | BUILDING ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 01/15/2008 | BUILDING ABOVE CEILING | Partial Approval | ROOMS 220, 219, 218, 217, 216, 215, 214, 213, 212 AND 211 | |
| 01/14/2008 | BUILDING ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 01/11/2008 | BUILDING ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 01/10/2008 | BUILDING ABOVE CEILING | Partial Approval | ROOMS #227, 222, 222A, 222B, 222C, 222D, 221, 201G, 221, 221A AND CORRIDOR 229A | |
| 01/09/2008 | BUILDING ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 12/06/2007 | BUILDING ABOVE CEILING | Partial Approval | ROOM #126 & NORTH/WEST ENTRY CORRIDOR | |
| 12/05/2007 | BUILDING ABOVE CEILING | Approved | IVRS - Inspection :* ROOMS #125, 222A & 222B |
|
| 12/04/2007 | BUILDING ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 11/30/2007 | BUILDING ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 11/15/2007 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* ROOM #120 |
|
| 10/31/2007 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* ABOVE CEILING @ GRID 5 TO 6/A TO D |
|
| 10/25/2007 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* CEILING GRID @ A.7/C & 3/4.2 |