Permit: T06CM04197
Permit Details
Apply Date:
07/17/2006
Applicant:
N/A
Description:
TI:ARCHIVES & MUSEUM
Contractors:
- COPELAND CONSTRUCTION
Permit Reviews
Permit Number - T06CM04197
Permit Status: C of o
Permit Description: TI:ARCHIVES & MUSEUM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/15/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 08/01/2008 | COMPLETED |
07/17/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 08/31/2006 | COMPLETED |
08/26/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 08/26/2008 | COMPLETED |
08/31/2006 | PLANS OK TO SUBMIT - SITE | 08/31/2006 | COMPLETED |
08/31/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 11/15/2006 | COMPLETED |
08/31/2006 | SITE | 10/02/2006 | COMPLETED |
10/23/2006 | RESUBMITTAL - SITE ALL | 12/01/2006 | COMPLETED |
11/15/2006 | POST 3RD PARTY REVIEW | 12/01/2006 | COMPLETED |
12/11/2006 | RESUBMITTAL | 02/02/2007 | COMPLETED |
12/11/2006 | RESUBMITTAL - SITE | 02/02/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM04197
Permit Status: C of o
Permit Description: TI:ARCHIVES & MUSEUM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/17/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM04197
Permit Description: TI:ARCHIVES & MUSEUM
Total Completed Inspections - 32
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/02/2007 | EXCAVATION/LAYOUT REBAR & ZON | AALEGRIA | Approved | IVRS - Inspection :* THIS INSPECTION COVERS PERIMETER FOUNDATION IN ACCORDANCE WITH APPROVED PLANS AND SPEC. DETAIL S1 & S2 SHEETS SPECIAL INSPECTION FOR EPOXY CONNECTIONS PROVIDED |
05/14/2007 | STEM WALL/RETAINING WALL | AALEGRIA | Approved | IVRS - Inspection :* IN ACCORDANCE WITH SPECIFIC DETAIL 1 ON SHEET S2 STEM WALL PERIMETER |
05/18/2007 | BUILDING PRE-SLAB | AALEGRIA | Approved | IVRS - Inspection :* |
06/26/2007 | REINFORCED MASONRY PRE-GROUT | AALEGRIA | Approved | IVRS - Inspection :* APPROVED @ TOPOUT |
07/30/2007 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
07/31/2007 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
08/22/2007 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
08/22/2007 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
12/03/2007 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* NO MECHANICAL IN WALLS |
12/03/2007 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* NO MECHANICAL IN WALLS |
12/03/2007 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* OK WALLS, CHECK P-RINGS FOR DEPTH |
12/03/2007 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* NOT READY - BACKING FOR VENTS ELEC. AND MECHANICAL |
12/03/2007 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
12/03/2007 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
12/03/2007 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
12/07/2007 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* CALL BACK FOR CLOSET FLANGE INSPECTIONS |
12/07/2007 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
12/18/2007 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* 1. PROVIDE TEST PER PLUMBING SPECIFICATIONS #3-C 2. COMPLETE PIPING FOR WATER HEATER 3. PROVIDE LADDER FOR OVERHEAD INSPECTION |
12/21/2007 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
12/21/2007 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
05/22/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
05/22/2008 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
05/22/2008 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
05/22/2008 | NPPO - FINAL | ACONNOR | Approved | N/A |
05/29/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
05/30/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
08/08/2008 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
08/28/2008 | FIRE - FINAL | LTHOMAS | Approved | |
08/28/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
08/28/2008 | ELECTRIC - TEMPORARY POLE | DSANTACR | Approved | IVRS - Inspection :* |
09/05/2008 | BUILDING - FINAL | LHANLY | Approved | |
09/05/2008 | ENGINEERING - FINAL | LHANLY | Approved | TRUNCATED DOMES TAKEN OFF PLAN REQUIREMENT |