Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T05CM05115
Permit Details
Apply Date:
10/07/2005
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
ADDITION:FOUNDATION ONLY & U/G PLUMBING AND ELECTRICAL WOMANS PAV. STRUCTURAL STEEL ADDED TO THIS PERMIT AS A DEFERRED SUBMITTAL
Architects:
- BOLLARD, MARK EDWARD
Contractors:
- B F L CONSTRUCTION CO INC ,
- SUNDT CORP
Permit Reviews
Permit Number - T05CM05115
Permit Status: Final
Permit Description: ADDITION:FOUNDATION ONLY & U/G PLUMBING AND ELECTRICAL WOMANS PAV.
STRUCTURAL STEEL ADDED TO THIS PERMIT AS A DEFERRED SUBMITTAL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/17/2006 | POST 3RD PARTY REVIEW | 03/17/2006 | COMPLETED |
03/17/2006 | RESUBMITTAL | 03/29/2006 | COMPLETED |
06/28/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 08/15/2006 | COMPLETED |
08/15/2006 | POST 3RD PARTY REVIEW | 08/30/2006 | COMPLETED |
10/07/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 10/07/2005 | COMPLETED |
10/07/2005 | 3RD PARTY REVIEW-COMMERCIAL | 12/06/2005 | COMPLETED |
12/06/2005 | POST 3RD PARTY REVIEW | 03/16/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM05115
Permit Status: Final
Permit Description: ADDITION:FOUNDATION ONLY & U/G PLUMBING AND ELECTRICAL WOMANS PAV.
STRUCTURAL STEEL ADDED TO THIS PERMIT AS A DEFERRED SUBMITTAL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/07/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM05115
Permit Description: ADDITION:FOUNDATION ONLY & U/G PLUMBING AND ELECTRICAL WOMANS PAV.
STRUCTURAL STEEL ADDED TO THIS PERMIT AS A DEFERRED SUBMITTAL
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/19/2006 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* J/14 STEM OK |
11/07/2006 | FRAMING | LHANLY | Approved | BEFORE ERECTION I NEED VERIFICATION THAT STEEL COMES FROM REGISTERED FABRICATOR. C.O.T ALSO NEEDS TO APPROVE SHOP DRAWINGS. |
11/17/2006 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* SEC B COMPLETE TIE-INS TO EXISTING AND CITY APPROVAL OF REVISIONS ARE ALL THAT REMAIN. |
11/29/2006 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* SOUTH PORTION OF FOUNDATION PLAN "B"; S/.5 TO S/15 S TO X OK TO POUR -- ENSURE THAT MESH IS ELEVATED OFF GROUND. |
11/29/2006 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* SOUTH, EAST, WEST PERIMETER FOOTINGS OF FOUNDATION PLAN "B" -- OK TO POUR ENSURE THAT EXCESS DIRT AND DEBRIS IS REMOVED FROM FOOTINGS. |
11/29/2006 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* SEC B READY FOR CONCRETE |
12/11/2006 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* - OK 11 SETS OF 4" PVC BEHIND PHYSICAL - OK 4/0 TO 2 - GROUND RODS. |
12/26/2006 | BUILDING - PROGRESS | LHANLY | Approved | IVRS - Inspection :* 1. AREA "A" STRUCT STEEL PRE-INSPECTION OK H.S BOLTS AND MOMENT CONNECTIONS OK (85% COMPLETE) SPECIAL INSPECTION CERTS FOR WELDS AND HS BOLTS NOT YET REVIEWED. 2. STRUCTURAL STEEL PRE-INSPECT FOR SITE DELIVERED AREA "B" COMPONENTS OK OK TO ERECT |
10/26/2007 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* SEE T06CM01872 |
10/26/2007 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* HAVE PLAN AVAILABLE CALL IN ALL PLB INSPECTIONS TO FINAL THIS PERMIT. |
03/21/2008 | ROOF NAILING | LHANLY | Approved | |
04/02/2008 | PLUMBING - FINAL | LHANLY | Approved | REFERENCE T06CM01872 FOR BULK OF INSPECTIONS ON THIS HOSPITAL ADDITION. |
04/02/2008 | PLUMBING - FINAL | LHANLY | Approved | |
04/02/2008 | ELECTRIC - FINAL | LHANLY | Approved | REFERENCE T06CM01872 FOR BULK OF INSPECTIONS ON THIS HOSPITAL ADDITION. |
04/02/2008 | BUILDING - FINAL | LHANLY | Approved | REFERENCE T06CM01872 FOR BULK OF INSPECTIONS ON THIS HOSPITAL ADDITION. |
09/29/2008 | PERMIT FINALED | LJACKSON | Approved |