Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T05CM05115
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2007 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
04/17/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* REINFORCING FOR CURB ON LEVEL 1 PART B-2 GRIDLINE 15.0/R.0-X/14.0-15 |
|
03/29/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOURTH FLOOR AREA GRIDLINE P-X/1-15 SQ. HIGH STR. BOLT REPORT PROVIDED WELDING REPORT PROVIDED PRE-POUR OBSERVATION REINFORCING FOR FOURTH FLOOR AREA GRID LINE P-X/1-15 SQ |
|
03/14/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
02/20/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* NOTE: EQUIPMENT PAD ON SECOND FLOOR OK TO POUR 1. GRIDLINE FOR THIRD FLOOR K-P/1.2-15 SHEET S2.EP 2. SUPER STRUCTURE OK AREA B.1 REGARDING TO AREA K-P/1.2-15 WELD, HIGH 5-BOLTS REPORTS PROVIDED. |
|
02/09/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
01/24/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* PROVIDE ACCESS TO APPROVED PLAN AND IRC IN ACCORDANCE WITH THE SECTION 106.3.1 NO SUPERINTENDENT ON JOB SITE TO PROVIDE INFORMATION ABOUT INSPECTION REQUESTED. |
|
11/29/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SOUTH, EAST, WEST PERIMETER FOOTINGS OF FOUNDATION PLAN "B" -- OK TO POUR ENSURE THAT EXCESS DIRT AND DEBRIS IS REMOVED FROM FOOTINGS. |
|
11/27/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PEDESTAL #W-15 -- OK TO POUR |
|
11/22/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTING #W-15 OK TO POUR |
|
11/08/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PEDESTAL W-15, X-15, FOOTING P.8-1 OK TO POUR |
|
11/07/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTINGS W-15, X-15 PEDESTAL S-15 OK TO POUR |
|
11/06/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 10:52 AM EXCAVATION AREN'T READY NO STEEL IN PLACE NOTHING TO INDICATE YOU WILL BE READY WITHIN 2 HOURS. |
|
11/03/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PIERS X-14, X-13, FOOTINGS V-10, V8, (U-15 ?) OK TO POUR |
|
11/01/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTINGS @ X-13, X,14 PIERS @ V-2, V-4, V-10, X-9 OK TO POUR |
|
10/31/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PIER FOOTINGS V-2, V-4 COLUMN FOOTINGS X-9, X-12 OK TO POUR |
|
10/30/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
10/26/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMN X-1, PIERS X-2, X-5 OK TO POUR |
|
10/25/2006 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* PROVIDE INF. FOR INSP. REQUESTED. |
|
10/23/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PIERS -- FOOTINGS U-1, W-1 (POURED) |
|
10/20/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* CANCELLED BY CONTRACTOR |
|
10/19/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1.7/E.9, D.8, C & 1.5/K WHEN SP. INSP. CONFIRMS |
|
10/18/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
10/16/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMN FOOTING U-14 OK TO POUR |
|
10/13/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMN #V-13 (U-14 NOT READY) |
|
10/12/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTINGS V-13, T-7; COLUMNS T-3, N-14, N-15 |
|
10/11/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMNS T-10, T-13, M-13; FOOTINGS N-14, N-15, T-3 |
|
10/10/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LINE T/13, 10; LINE U/13 |
|
10/09/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. PIER CAPS LINE A/5.8, 9.5, 12.5 OK 2. COL. FOOTINGS AT K-11 AND M-11 OK |
|
10/06/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. CAISSONS LINE A OK 2. LINE B, C, D, E, F COL FOOTINGS COMPLETE |
|
10/05/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PIERS #P2, P14, COLUMNS D9.5, B19.5, E9.5 F7.8, F5.8 -- OK TO POUR |
|
10/03/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LINE B @ 13.8; LINE K @ 7, 14, 15; L @ 15; P @ 7, 13, 15; Q @ 13, 14; R @ 7, 10, 15; SC1 |
|
10/02/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PIERS: 12.8, F13.8, K13, D5.8 FOOTINGS: B 13.8, D 5.8, K14, K8, J 9.7, P7, R7, R10 |
|
09/29/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LINE F @ 12.8, 13.8; LINE K @ 13, 8 |
|
09/28/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LINE 3 @ 12.5; LINE D @ 5.8, 12.5, 13.8; LINE C 14.3 OK TO PLACE |
|
09/27/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LINE B - F7 @ 9.5 - F7 @ 12.8; F6.5 @ 14.3 LINE E - F7 @ 13.8 OK TO PLACE FOOTING |
|
09/26/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* F6.5 @ 5.8/B OK TO PLACE |
|
09/12/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ||
08/30/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SOUTH ELEVATOR PIT NAILS OK TO FINISHED GRADE |
|
08/29/2006 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - RI canceled | |
08/25/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SUMP PIT FLOOR OK |
|
08/22/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SOUTH TUNNEL WALL, LINES R.4/.5 TO R.4/3.8 |
|
08/18/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/16/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* FLOODED SITE |
|
08/14/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/10/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* N.3 THROUGH G9 -- FORM SAVERS ADDED |
|
08/07/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 4 COLUMN FOOTINGS AT COOLING PLANT OK PER RFI #93 |
|
07/28/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* ALL TUNNEL FOOTING OK OK TO PLACE WHEN SP. INSP. CONFIRMS REMAINING VERTICALS @ SOUTH END. |
|
07/27/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
07/25/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* STEM WALLS TO 0' AFF TUNNEL LINES 2/A-D |
|
07/21/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SOUTH PORTION OF TUNNEL, LINES B.6/F SOUTH |
|
07/14/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMNS TO GRADE @ B/1.7 AND N 1.5 OK TO CLOSE & POUR |
|
07/12/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* F4 @ 1.7/B AND F14 @ 1.5/N |
|
07/11/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
07/07/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
06/27/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* EAST WALL OF ELEV. SHAFT @ P/1.8 TO 12' OK |
|
06/22/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BASEMENT WALL FOOTING C-F/LINE 3 |
|
06/16/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BASEMENT @ ELEVATION 17'0" LINES 1.5-3.9/A.9 CORRIDOR STEP DOWN A.9-C.0 WEST FOOTING INCREASED FROM 18"-24" |
|
06/15/2006 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - RI canceled | |
06/09/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BOTTOM OF ELEVATOR @ P/1.7 EAST WALL REQUIRES #6 VERTICALS NOT #5 REFERENCE DETAIL 13/S3.1 OK TO PLACE WHEN SPECIAL INSP. CONFIRMS REPLACEMENT PLEASE HAVE SPEC. BOOK SUBMITTAL FOR WATER STOP @ NEXT INSPECTION. |
|
06/08/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BASEMENT PAD ELEV. 19.6 @ A/1.7 *PLEASE PROVIDE SHOP DRAWINGS AND SPECIAL INSP. REPORT FOR GUNITE FOUNDATION SYSTEM. |