Permit: T05CM03547
Permit Details
Apply Date:
07/07/2005
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW OFFICE BLDG
Contractors:
- TRIUMPH BUILDERS SOUTHWEST LLC *C*
Permit Reviews
Permit Number - T05CM03547
Permit Status: C of o
Permit Description: NEW OFFICE BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/07/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 07/08/2005 | COMPLETED |
07/08/2005 | 3RD PARTY REVIEW-COMMERCIAL | 08/30/2005 | COMPLETED |
08/29/2005 | SITE | 09/12/2005 | COMPLETED |
08/30/2005 | POST 3RD PARTY REVIEW | 09/12/2005 | COMPLETED |
09/12/2005 | RESUBMITTAL | 09/12/2005 | COMPLETED |
11/21/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 11/30/2005 | COMPLETED |
12/30/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 01/10/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM03547
Permit Status: C of o
Permit Description: NEW OFFICE BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/07/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM03547
Permit Description: NEW OFFICE BLDG
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/19/2005 | TEP CLEARANCE - AM | RMAJUTA | Approved | OK TEMP POWER POLE PER SUBA |
10/03/2005 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* PLACE COPPER UFER AT BOTTOM OF FOOTING & CLAMP TO REBAR PER 250 NEC OK |
10/11/2005 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :*PER CONVERSTION WITH ENGINEER SCOTT DUECKER REBAR L?? SPLICE IN MASONRY IS TO BE PER ACI 530 ( 48 BAR DIAMETER FOR GRADE 60) GSN'S DO NOT NOTE THIS INFORMATION |
11/04/2005 | EXCAVATION/LAYOUT REBAR & ZON | JCAGLE | Approved | IVRS - Inspection :*COLUMN FOOTING @ LINES Z/1.5 |
11/04/2005 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :*EITHER WAY I WILL BE BACK IN THE MORNING 10:50AM PRIVATE MH #1 SUBJECT TO TEST SDR 35 BETWEEN MH# 1 & MH #2 OK TO COVER SUBJECT TO TEST AND VERIFICATION OF GRADE |
11/09/2005 | ENGINEERING - FINAL | MCARREON | Approved | CONTRACTOR MISTAKENLY REQUESTED A DSD ENGINEERING INSPECTION WHEN WHAT HE REQUIRED WAS A RIGHT OF WAY INSPECTION. |
11/28/2005 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection :*TOP OUT SOUTH TOWER |
12/06/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :*N/H UNDERGROUND COMPLETE OK TO COMPLETE ALL AREAS |
12/07/2005 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :*3" TYPE K UNDER STAIRWAY # 8 WI? RISER OK NEED TO SEE CONNECTION TO PVC YARD WATER. |
12/08/2005 | ELECTRIC - UNDERGROUND | RSUBA | Approved | IVRS - Inspection :*2ND FLOOR SOUTH 1/2 FLOOR FLOOR BOXES |
12/19/2005 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :*4-4'' N/H ROOF DRAINS UP TO TEN FEET OK SITE SEWER FROM M.H # 2 TO UPPER CLEAN-OUT AND 4" CONNECTION TO BLDG DRAIN OK SUBJECT TO VERIFICATION OF GRADE AND TESTING OK TO COVER |
12/19/2005 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* |
12/21/2005 | FRAMING | LHANLY | Approved | IVRS - Inspection :*1) PLEASE PROVIDE MILL CERTIFICATION FOR STEEL FABRICATOR. 2) PROVIDE APPROVED SHOP DRAWINGS FOR STRUCTURED STEEL. 3) 1ST FLOOR STRUCTURAL STEEL CONFORMS TO PLAN/SPEC. INSP REVIEWED/ACCEPTED. |
12/21/2005 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
12/27/2005 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :*3RD FLOOR SUPER STRUCTURE OK. I STILLNEED SPECIAL INSP REPORTS P. FOR H.S BOLTS AND WELDS. CONTRANCTOR HAS SUBSTITUTED A 12" ON STUGGER ( 6" O.C ON LINE) STUD PATTERN ON BY BEANS RATHER THAN TANDEM PATERN REQUIRED BY DETAIL. T24. CONTRACTOR TO PROVIDE RFI FROM ENGINEER FOR THIS STANDARD FIX. OK TO PLACE 3RD FLOOR SLAB |
02/22/2006 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
02/23/2006 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
03/17/2006 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection :* |
04/04/2006 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* WALK THROUGH FOURTH FLOOR OVERHEAD INSPECTED PARTITION INSTALLATION OK TO COVER ALL AREAS, ALL FLOORS |
05/30/2006 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* OK TO COVER ALL AREAS ALL FLOORS. |
05/31/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* FINISH INSULATING SHEETMETAL DUCTS 4TH FLOOR. DO NOT USE PLASTIC DRAIN HOSE IN THE R.A. PLENUM. WILL CHECK ON FINAL |
06/01/2006 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
06/01/2006 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
06/01/2006 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
06/05/2006 | RIGHT OF WAY - FINAL | NBRIGGS | Approved | PER EMAIL |
06/07/2006 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
06/22/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
06/22/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
06/22/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
06/23/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
06/26/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
06/26/2006 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
06/28/2006 | FIRE - FINAL | LTHOMAS | Approved | PER PHONE CALL |
06/28/2006 | OUTDOOR LIGHTING FINAL | RSUBA | Approved | IVRS - Inspection :* |
06/28/2006 | ELECTRIC - OUTDOOR LIGHTING | RSUBA | Approved | IVRS - Inspection :* |
06/28/2006 | ELECTRIC - CABLE DROP | RSUBA | Approved | IVRS - Inspection :* |
06/28/2006 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
06/28/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
06/29/2006 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
06/29/2006 | ELECTRIC - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection :* |
07/13/2006 | LANDSCAPE - FINAL | ACONNOR | Approved |