Permit Details

Status:
Inspections Complete
Type:
Development Package
Address NEW:
4150 E LOS REALES RD
Apply Date:
05/09/2022
Applicant:
Adam Jones
Description:
Revision 2 - Site/Grading/Swppp/Floodplain: I-10 International. New commercial storage.

Permit Reviews

Permit Number - DP22-0122
Permit Status: Inspections complete
Permit Description: Revision 2 - Site/Grading/Swppp/Floodplain: I-10 International. New commercial storage.
Start Date Submittal Complete Date Status  
05/09/2022 DEV PKG - OK TO SUBMIT 05/20/2022 COMPLETED Review Details
05/20/2022 DEV PKG 08/09/2022 COMPLETED Review Details
09/21/2022 DEV PKG - RESUBMITTAL 10/18/2022 ACTIVE Review Details
09/18/2025 DEVELOPMENT PACKAGE NEW REVISION v.3 10/17/2025 APPROVED Review Details
06/20/2025 DEVELOPMENT PACKAGE NEW REVISION v.2 07/28/2025 REQUIRES RESUBMIT Review Details
12/29/2022 DEVELOPMENT PACKAGE REVIEW v.2 01/05/2023 APPROVED Review Details
01/29/2025 DEVELOPMENT PACKAGE NEW REVISION v.1 05/05/2025 REQUIRES RESUBMIT Review Details
10/28/2022 DEVELOPMENT PACKAGE REVIEW v.1 11/09/2022 REQUIRES RESUBMIT Review Details
09/16/2024 DEVELOPMENT PACKAGE REVIEW v.1 09/17/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: DP22-0122
Permite Description: Revision 2 - Site/Grading/Swppp/Floodplain: I-10 International. New commercial storage.
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
02/05/2025 NPPO Monitoring N/A Complete (Recurring) Nursery’s are in good condition and all plants look extremely healthy. Tree and cactus are separated due to irrigation being used for trees.
05/07/2025 N/A Complete (Recurring) starting grade cut and compaction on the west and north of building 2 for walk and asphalt.
06/26/2025 Grading Progress ENGR N/A Partial Pass 06/26/25, Grading in progress on east side, south side of building 3 north side completed and blue topped. In between buildings 2 and 3 ready for blue top.
07/08/2025 ENGR Paving N/A Partial Pass 07/08/25, Paving on the east side of building 3 is completed with minor adjustments possibly needed. Curb damage on the south corner, super knows about this. Next inspection should be middle and north side paving.
04/21/2025 SITE - Stormwater Follow-up N/A Complete (Recurring) Nursery is also in good shape
12/09/2025 N/A Partial Pass sidewalk scupper was redesigned from a type two they modified it from 2’6” to 1’8’’ informed the contractor to have the engineer record to sign off on it
10/28/2025 ENGR Engineering Final N/A Partial Pass Contractor has not completed the sidewalk scupper type two over by building two. Will call in for another inspection when completed.
12/11/2025 COT - BASN - Drainage/Basin - Condition Inspection N/A Deferred

Completed Inspections

Permit Status: Inspections Complete
Permit Number: DP22-0122
Permit Description: Revision 2 - Site/Grading/Swppp/Floodplain: I-10 International. New commercial storage.
Total Completed Inspections - 19
Date Description Inspector Results Comments
08/19/2024 PDSD Engineering Division Pre-Construction SITE Passed
11/07/2024 NPPO Pre-Construction Passed
11/08/2024 SITE - Stormwater Setup and Controls Passed
06/04/2025 Passed 06/04/25, All bollards between building 2 and 3 passed.
07/10/2025 SITE - Sign Footer/Setback/Excavation Layout/Rebar Passed Okay to pour light pole foundations along Los Reales frontage.
07/15/2025 ENGR Paving Passed 07/15/25, Paving has passed all specs, proper drainage appears to be consistent with the approved plans.
07/16/2025 Passed This drainage system could possibly be in the right of way but it does have positive pitch at 1.5% and is a triple barrel RCP pipe. Pipe was shaded but could still see the bedding.
08/12/2025 LAND Landscape Appearance & Function Final Passed Finish of the landscaping is per plan and looks good. All plants required by plan have been installed. Equipment is in the proper locations. Pressure test have not been completed. NPPO is covered under its own inspection.
08/12/2025 SITE - Stormwater Follow-up Passed 08/12/25, noted there is a swale missing on the southeast corner of the site between the 2 buildings that diverts the water to the east basin.

All trash will need to be cleaned up on the far southeast corner of the project and this area needs to be raked/ripped to create a pervious surfaces so water does not stand here for longer than the allowed 24 hr time period.

The lot itself has several areas of standing water that needs to be addressed prior to the engineering final.

The rip rap berm on the southeast corner middle side is being impacted by pour drainage and a missing swale
08/12/2025 NPPO Final Passed NPPO is in good shape and has all been transplanted. The continued maintenance of the nursery shows here. All trees and cactus on the NPPO have survived and have been reestablished.
09/09/2025 Passed Cane stakes are coming out now. All at other elements are correct. with the planting.
09/09/2025 Passed Backflow preventer and meter, are correct to plan. Controller is correct. plants and materials are correct. and Plants look good.
09/19/2025 Passed Parking areas are now complete and striped according to approved plans.
09/24/2025 ENGR - Drainage Structures Passed Drainage pipe outlets and retention basins are complete and in accordance with approved plans. All drainage structures on site for buildings 2 & 3 (building 1 is no longer part of this project).
09/25/2025 ENGR Grading Final Passed Previous issues have been resolved. Site grading is complete and acceptable. Drainage works as intended.
11/18/2025 Consultation SITE Passed 11/18/25
Consultation with contractor and super retrofit the non compliant existing scupper NW of bldg 3 to PAG 205 type 2. Plan is good and will meet the intent and dimensions required.
Request sidewalk/Flatwork inspection or send pictures showing reinforcing as discussed, before pouring plate supports and plate angle iron embeds.
12/09/2025 COT - ENGR - Signage Final Passed
12/11/2025 Passed Passed per conformance letter by Rick Engineering.
12/11/2025 ENGR Engineering Final Passed Passed per conformance letter by Rick Engineering.

Documents

File Name Document Type  
4329 - SITE SUBST CONFORM COMMERCIAL LTR.PDF DOCUMENTS VIEW
DP22-0122 CONFORMED SET REVISION 2.PDF DOCUMENTS VIEW
4329A - REV 2 - DP RESPONSE LETTER - 1ST__V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
I-10 INTERNATIONAL_DP REVISIONS NARRATIVE COT_2025.01.17_V1.PDF DOCUMENTS VIEW
REVISION 2 - APPROVED - UPDATED PAGES ONLY - 4329A - DEVELOPMENT PACKAGE - 2025_09_16_REV2_V1 -STAMPED 10.17.2025.PDF DOCUMENTS VIEW
4329A - DEVELOPMENT PACKAGE - 2024_08_24_REV1_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW