Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - DP22-0122
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2025 | Partial Pass | 05/14/25, building 3 west side dock ramps and bollards are good to pour. | ||
| 06/12/2025 | Not Ready | There is a lot of sidewalk to be poured while decision is being made on the truncated domes. | ||
| 06/18/2025 | Partial Pass | 06/18/25, I see no issues on the east side of building 3 that would raise a red flag, I sure compaction test is completed prior to pour. | ||
| 06/20/2025 | Not Ready | Main sidewalk forms on the south side of building 3 are properly set. *some cross slopes are measuring right at 2% max limit, will need to be careful to ensure finished product is at or below 2% cross slope. There is a sidewalk extending from the main path up to a door with a running slope of 10%, this sidewalk is not indicated on the approved plan set. This will need to be investigated and corrected. *see attached photos. | ||
| 06/25/2025 | Partial Pass | East side of east building looks good to pour, south side accessory door needs to have a step incorporated into the ramp to get it under 10%, north side accessory door will be the same way. Building 2 looks good all the way around for walks other than the south side accessory door. | ||
| 06/26/2025 | Partial Pass | North sides of building 2 and 3 are good to pour. One door walkway on the north side of 3 needs to be stepped same building on the south side as well. | ||
| 08/28/2025 | Passed | Item on sidewalk coming from interior of site to right of way has been addressed and fixed. | ||
| 12/09/2025 | Partial Pass | sidewalk scupper was redesigned from a type two they modified it from 2’6” to 1’8’’ informed the contractor to have the engineer record to sign off on it | ||
| 12/11/2025 | Passed | Passed per conformance letter by Rick Engineering. |