Inspection Status: Partial Pass
Inspection History: ENGR - Drainage Structures
| Date |
Description |
Inspector |
Results |
Comments |
| 05/27/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
05/27/05, Drainage structure in the middle section of the 3 barrel drain pipe on the southwest corner of building 2. |
| 05/30/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
05/30/25, Nyoplast drainage structures are good to backfill on the last section of the southwest 3 barrel section of pipe. |
| 06/02/2025 |
ENGR - Drainage Structures |
|
Canceled |
|
| 06/03/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
06/03/25, Drainage structure Middle and East of building 2 good to backfill. |
| 06/04/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
06/04/25, Drainage Nyoplast structure on the east side run passed. |
| 06/25/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
06/25/25, as an as built drainage will be added to the two parking areas on the south side of building 2 for drainage into the large basin. |
| 08/12/2025 |
ENGR - Drainage Structures |
|
Passed |
08/12/25, Mag Wells are now open and certified. |
| 09/24/2025 |
ENGR - Drainage Structures |
|
Passed |
Drainage pipe outlets and retention basins are complete and in accordance with approved plans. All drainage structures on site for buildings 2 & 3 (building 1 is no longer part of this project). |