Permit: TD-DEV-0924-00273
Permit Details
Apply Date:
09/29/2024
Applicant:
Ryan Laber
Description:
Rev 3 - Update to EV spaces started 06.08.2026 ** Rev 2 RESTRICED ACCESS 84-Unit Multifamily Development
Permit Reviews
Permit Number - TD-DEV-0924-00273
Permit Status: Complete
Permit Description: Rev 3 - Update to EV spaces started 06.08.2026 ** Rev 2 RESTRICED ACCESS 84-Unit Multifamily Development
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/30/2024 | DEVELOPMENT PACKAGE NEW v.1 | 10/30/2024 | REQUIRES RESUBMIT |
| 12/12/2024 | DEVELOPMENT PACKAGE NEW v.3 | 12/19/2024 | APPROVED |
| 04/14/2026 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 04/16/2026 | APPROVED |
| 06/08/2026 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 06/15/2026 | APPROVED |
| 04/13/2026 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 04/13/2026 | REQUIRES RESUBMIT |
| 05/13/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 05/19/2025 | APPROVED |
| 06/15/2026 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 06/15/2026 | APPROVED |
| 11/19/2024 | DEVELOPMENT PACKAGE NEW v.2 | 12/03/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TD-DEV-0924-00273
Permit Status: Complete
Permit Description: Rev 3 - Update to EV spaces started 06.08.2026 ** Rev 2 RESTRICED ACCESS 84-Unit Multifamily Development
| Date | Description | Comments |
|---|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0924-00273
Permite Description: Rev 3 - Update to EV spaces started 06.08.2026 ** Rev 2 RESTRICED ACCESS 84-Unit Multifamily Development
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | There is no concerns at this time |
| 11/06/2025 | For trash and recycling enclosures | N/A | Partial Pass | 11/6/26 Ok to grout second lift of refuse enclosures. Request inspections for refuge enclosure when rebar for floor and bollard footers are ready. Protect all storm drain inlets on site with waddle or other bmp. Use correct concrete cleanout, as well....And as part of the renewed 2025 GCP, the site plan needs to show the entire area including the leased lot for material lay down parking etc. |
| 04/03/2026 | N/A | Partial Pass | Okay to pour vertical curb on north end of building, and Curb & gutter on north end of parking lot. Okay to pour landing and sidewalk at northwest corner. Ensure that all slopes are per plan |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0924-00273
Permit Description: Rev 3 - Update to EV spaces started 06.08.2026 ** Rev 2 RESTRICED ACCESS 84-Unit Multifamily Development
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/16/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
| 05/30/2025 | SITE - Stormwater Setup and Controls | Passed | On our first by-weekly we will need to see the rain gauge, report book and full set of SWPPP plans. Start your schedule from this date for your by-weekly inspections. | |
| 07/10/2025 | Passed | contractor installed 30 inch HDP 70 feet two barrels good to backfill | ||
| 06/26/2026 | Passed | contractor is good to pave the parking lot area the main line and the entrances | ||
| 07/22/2026 | Consultation SITE | Passed | Discussed status of project in relation to close out requirements. Advised contractor to begin calling in flatwork inspections so that we have time to complete inspections. | |
| 08/18/2026 | ENGR Paving | Passed | ||
| 08/18/2026 | Grading Progress ENGR | Passed | ||
| 09/18/2026 | SITE - Zoning Final | Passed | ||
| 09/18/2026 | Passed | |||
| 09/18/2026 | SITE - Stormwater Final Inspection | Passed | ||
| 09/18/2026 | Passed | |||
| 09/18/2026 | COT - ENGR - Signage Final | Passed | ||
| 09/18/2026 | ENGR - Drainage Structures | Passed | Structures complete | |
| 09/23/2026 | COT - BASN - Drainage/Basin - Condition Inspection | Passed | ||
| 09/23/2026 | For trash and recycling enclosures | Passed | ||
| 09/25/2026 | Passed | |||
| 10/01/2026 | LAND Landscape Appearance & Function Final | Passed | ||
| 10/01/2026 | ENGR Engineering Final | Passed |