Permit: TD-DEV-0724-00196
Permit Details
Status:
Complete
Type:
Development Package
Address:
8284 S CAMINO DE CAFE
Address NEW:
8284 S CAMINO DE CAFE
Apply Date:
07/08/2024
Applicant:
Chris Guinter
Description:
New building with parking and landscaping improvements
Permit Reviews
Permit Number - TD-DEV-0724-00196
Permit Status: Complete
Permit Description: New building with parking and landscaping improvements
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/25/2024 | DEVELOPMENT PACKAGE NEW v.3 | 02/24/2025 | APPROVED |
| 07/11/2024 | DEVELOPMENT PACKAGE NEW v.1 | 08/29/2024 | REQUIRES RESUBMIT |
| 10/03/2024 | DEVELOPMENT PACKAGE NEW v.2 | 11/07/2024 | REQUIRES RESUBMIT |
| 06/03/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/04/2026 | APPROVED |
Conditions
Permit Number - TD-DEV-0724-00196
Permit Status: Complete
Permit Description: New building with parking and landscaping improvements
| Date | Description | Comments |
|---|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0724-00196
Permite Description: New building with parking and landscaping improvements
Total Outstanding Inspections - 1
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0724-00196
Permit Description: New building with parking and landscaping improvements
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/21/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | See inspection checklist. | |
| 05/20/2025 | NPPO Pre-Construction | Passed | PIP # 1 & 2 accounted for. #1 will be replaced and #2 TOS. Nursery in place. See checklist items for details. | |
| 06/22/2026 | Passed | Rough Grading is good. Retaining wall footer will need to be cut in on South edge of parking area from the corner of the Refuse Enclosure to the East to where it will be retaining less than 3'. Wall Detail has been submitted and approved. Retaining wall will also be needed at North side of parking area around the transformer where it will be too steep for grouted rip rap. Areas west/south of building are correct. Also the Basin at the street needs to be dug deeper at the south end so that the bottom is flat as it is drawn in grading sheet. Currently it tapers up to the south, following the grade of the sidewalk. Riprap will be grouted where necessary. North of building is ready for grouted riprap as well as other areas on plan where retaining wall is not necessary. Okay to proceed with retaining walls. Schedule Grading Progress inspection when basin is correct, and Final when curbs and walls are in place, backfilled and subgrade and fill is compacted and ready for AB. Schedule wall inspections when wall footers are ready. |
||
| 09/08/2026 | Passed | |||
| 09/08/2026 | LAND Landscape Appearance & Function Final | Passed | ||
| 09/11/2026 | ENGR Paving | Passed | ||
| 09/11/2026 | For trash and recycling enclosures | Passed | ||
| 09/11/2026 | Passed | |||
| 09/11/2026 | Passed | |||
| 09/25/2026 | ENGR Engineering Final | Passed | ||
| 09/25/2026 | COT - ENGR - Signage Final | Passed | ||
| 09/25/2026 | SITE - Zoning Final | Passed |