Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/07/2026 | For trash and recycling enclosures | Partial Pass | Footer for double refuse enclosure dimensions and reinforcing correct. OK to pour footer. Schedule pre grout inspection at first lift. Other option is to put a bond beam at the top of wall and schedule pre grout inspection at top of wall with weep holes at bottom of reinforced cells. |
|
| 07/28/2026 | For trash and recycling enclosures | Partial Pass | OK to grout first lift of refuse enclosure. Schedule inspection for Floor, Bollards and pre grout inspection for second lift of wall. | |
| 07/31/2026 | For trash and recycling enclosures | Partial Pass | Okay to pour floor and bollards correct. Okay to finish building enclosure walls. Schedule pregrout for 2nd lift. | |
| 08/10/2026 | For trash and recycling enclosures | Partial Pass | Okay for 2nd lift grout. | |
| 09/11/2026 | For trash and recycling enclosures | Passed |