Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
6105 E BROADWAY BL
Apply Date:
06/03/2024
Applicant:
John Morgan
Description:
Revision 1 - New McDonald's site and building

Permit Reviews

Permit Number - TD-DEV-0624-00169
Permit Status: Complete
Permit Description: Revision 1 - New McDonald's site and building
Start Date Submittal Complete Date Status  
07/15/2025 AS-BUILT v.1 07/24/2025 APPROVED Review Details
06/14/2024 DEVELOPMENT PACKAGE NEW v.2 08/05/2024 REQUIRES RESUBMIT Review Details
12/26/2024 DEVELOPMENT PACKAGE NEW REVISION v.1 01/21/2025 REQUIRES RESUBMIT Review Details
10/18/2024 DEVELOPMENT PACKAGE NEW v.4 12/24/2024 APPROVED Review Details
02/19/2025 DEVELOPMENT PACKAGE NEW REVISION v.3 02/26/2025 APPROVED Review Details
08/29/2024 DEVELOPMENT PACKAGE NEW v.3 10/03/2024 REQUIRES RESUBMIT Review Details
02/03/2025 DEVELOPMENT PACKAGE NEW REVISION v.2 02/19/2025 REQUIRES RESUBMIT Review Details
06/06/2024 DEVELOPMENT PACKAGE NEW v.1 06/13/2024 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TD-DEV-0624-00169
Permite Description: Revision 1 - New McDonald's site and building
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
06/10/2025 For trash and recycling enclosures N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TD-DEV-0624-00169
Permit Description: Revision 1 - New McDonald's site and building
Total Completed Inspections - 7
Date Description Inspector Results Comments
03/11/2025 PDSD Engineering Division Pre-Construction SITE Passed Informed the contractor he needed to have all the third-party testing on site to install wattles all along the fence line and track out rock at the entrance of the project
06/27/2025 For trash and recycling enclosures Passed 6/27/25 Both Refuse Enclosures built not to TSM Section 8 standards but are built per COT Approved Plans- Except wall height and gate height are over 6’. They stand at 7.5’ This discrepancy will need to be submitted in as built. Gates are primed but need to be painted “Iron Ore”. Painting scheduled for June 30.
07/01/2025 LAND Landscape Appearance & Function Final Passed Contractor will replace 3 missing or dead lantanas and 2 yuccas in East Parking Area Landscape as discussed. Irrigation function and Landscape appearance is met as intended. Details are correct.

South of the building is an area outside of the landscape scope that had preexisting plants that will be mitigated with new plants. Irrigation in this area functions. Matching Dg will be placed in this area. Another Area NW of the building also needs to have Dg. This DG will be depressed as discussed with Contractor. Both of these areas will be checked at engineering final.
07/01/2025 Passed 7/1/25
Okay for level 4 TCO.
Contractor widened NW curb cut to match plans. The rest of the curb cuts were accepted by the engineer of record as sufficient to function as intended.
The Sidewalk scupper noted earlier was unintended and also accepted by the engineer. These changes will be noted in the as builts.
The long term and short term bike parking will be fastened down correctly by the Engineering Final.
The Parking area on top of Alamo Wash has been sealed with a surface restoration coating. It is setting up and the area is roped off from the public. There is sufficient access while this area is roped off. This area will be Striped Wednesday night 7/2/25. I will check details in this Area at Engineering Final.
All construction debris and Material will be off site by end of day. Unfinished areas will be cordoned or fenced off and public safety will be maintained. Access will not be limited except in Alamo Wash area.
Schedule Engineering Final when Alamo Wash and Landscaping issues completed.
07/01/2025 Passed 7/1/25 All Bollards have been filled. The remaining unpainted bollards on retaining wall are being painted per PAG 106 now.
07/08/2025 SITE - Zoning Final Passed
08/01/2025 ENGR Engineering Final Passed Alamo Wash area complete.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
MCDONALD'S 6105 E. BROADWAY BLVD ASBUILTS WITH NARRATIVE_V2.PDF DOCUMENTS VIEW
TD-DEV-0624-00169_CONFORMED SET REVISION 1 DP.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
REV 1_3RD SUB_TD-DEV-0624-00169_DEV PACKAGE_V2.PDF DOCUMENTS VIEW