Permit: TD-DEV-0424-00137
Permit Details
Status:
Complete
Type:
Development Package
Address:
9537 E OLD VAIL RD
Address NEW:
9537 E OLD VAIL RD
Apply Date:
04/24/2024
Applicant:
Description:
16,000 SF Office / Commercial Storage on a 1.7 AC Site
Permit Reviews
Permit Number - TD-DEV-0424-00137
Permit Status: Complete
Permit Description: 16,000 SF Office / Commercial Storage on a 1.7 AC Site
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/12/2024 | DEVELOPMENT PACKAGE NEW v.2 | 08/14/2024 | REQUIRES RESUBMIT |
| 04/25/2024 | DEVELOPMENT PACKAGE NEW v.1 | 06/02/2024 | REQUIRES RESUBMIT |
| 09/09/2024 | DEVELOPMENT PACKAGE NEW v.3 | 09/11/2024 | APPROVED |
| 04/02/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/03/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TD-DEV-0424-00137
Permit Status: Complete
Permit Description: 16,000 SF Office / Commercial Storage on a 1.7 AC Site
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/01/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0424-00137
Permite Description: 16,000 SF Office / Commercial Storage on a 1.7 AC Site
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2024 | PDSD Engineering Division Pre-Construction SITE | N/A | Partial Pass | I met on the site this morning with members of KE&G construction company to discuss the project they will be starting.We looked over the site no work has been started at this time but, will begin within the next week. I met with Kurt Rice and Eddie Norris, Eddie Norris will be the site supervisor for this site. He advised me of what they will be doing in the near future starting with the removal of all the plants and have them placed in a nursery during the construction . They will start on minor grading and grubbing of the site once they have the NPPO approved for the nursery. they will be posting the site with their sign as required this coming week and will provide us with the NOI (Notice of Intent) for the site at that same time. Ron will remind them on his first meeting to pick up the notice of intent information that they are to call their site every two weeks for an inspection for the SWPPP. |
| 10/07/2024 | NPPO Pre-Construction | N/A | Partial Pass | I met on the site this morning with members of KE&G construction company to discuss the project they will be starting.We looked over the site no work has been started at this time but, will begin within the next week. I met with Kurt Rice and Eddie Norris, Eddie Norris will be the site supervisor for this site. He advised me of what they will be doing in the near future starting with the removal of all the plants and have them placed in a nursery during the construction . They will start on minor grading and grubbing of the site once they have the NPPO approved for the nursery. they will be posting the site with their sign as required this coming week and will provide us with the NOI (Notice of Intent) for the site at that same time. Ron will remind them on his first meeting to pick up the notice of intent information that they are to call their site every two weeks for an inspection for the SWPPP. |
| 03/10/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No concerns at this time |
| 12/11/2025 | ENGR Grading Final | N/A | Re-inspection required | AB not ready. |
| 11/15/2024 | ENGR - Drainage Structures | N/A | Partial Pass | single barrel drainage pipe, 80’ good to backfill. 11/15/24 |
| 12/31/2025 | N/A | Partial Pass | Okay to pour sidewalk along front of building. | |
| 01/23/2026 | ENGR Engineering Final | N/A | Re-inspection required | Site is not complete, not ready for engineering final. Items that need finished are listed below: 1. Landscaping - plants, irrigation, ground cover 2. Refuse Enclosure - mount doors, grout wall, fill bollards 3. Site striping - parking lines, cross-walk 4. ADA parking - access isle, signs 5. Site wall - finish walls 6. Address numbers - visible from Old Vail Road |
| 12/31/2025 | For trash and recycling enclosures | N/A | Partial Pass | Okay to pour refuse enclosure slab and approach. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0424-00137
Permit Description: 16,000 SF Office / Commercial Storage on a 1.7 AC Site
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2024 | NPPO Pre-Construction | Passed | NPPO is completed | |
| 12/12/2025 | ENGR Grading Final | Passed | AB correct. Submit compaction reports to the portal. Ok to pave parking area. Landscaping elevations and basins correct. | |
| 01/21/2026 | ENGR - Drainage Structures | Passed | Inlets/outlet structures, drainage structures, and WHIA/channels are all installed in accordance with approved plans. Site drainage work is complete in accordance with approved plans. | |
| 01/23/2026 | Passed | Concrete sidewalks are complete and acceptable. | ||
| 02/27/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 02/27/2026 | For trash and recycling enclosures | Passed | Trash enclosure is complete in accordance with approved plans. | |
| 02/27/2026 | Final inspection to ensure all landscape and water harvesting SITE | Passed | All water harvesting areas are complete in accordance with approved plans. |