Inspection History Details
Inspection Status: Canceled
Inspection History: ENGR Grading Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/03/2025 | ENGR Grading Final | Canceled | ||
| 11/19/2025 | ENGR Grading Final | Partial Pass | 11/19/25 Subgrade Inspection. Contractor and owner opted to change plan and use 3" over 5" in all asphaltic pavement areas. They will forward Engineer's Approval of this. Bluestake and Subgrade correct to new configuration. Drainage appears correct. Submit 3rd party compaction reports to permit in the portal. Send pictures of areas not 100 % complete before placing ABC. Request same inspection when AB is complete before paving. |
|
| 12/11/2025 | ENGR Grading Final | Re-inspection required | AB not ready. | |
| 12/12/2025 | ENGR Grading Final | Passed | AB correct. Submit compaction reports to the portal. Ok to pave parking area. Landscaping elevations and basins correct. |