Inspection Status: Passed
Inspection History: ENGR - Drainage Structures
| Date |
Description |
Inspector |
Results |
Comments |
| 01/21/2026 |
ENGR - Drainage Structures |
|
Passed |
Inlets/outlet structures, drainage structures, and WHIA/channels are all installed in accordance with approved plans. Site drainage work is complete in accordance with approved plans. |
| 01/22/2025 |
ENGR - Drainage Structures |
|
Complete (Recurring) |
Pipe is good to backfill Nov, 21st 2024. 11/25/2024, drainage structure and dbl barrel pipe has passed. Drainage pipe along west wall, 75' section good to backfill, 01/22/25 |
| 01/27/2025 |
ENGR - Drainage Structures |
|
Passed |
|
| 01/29/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Monolithic poor of base, toe and slab. Good to pour |
| 11/15/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
single barrel drainage pipe, 80’ good to backfill. 11/15/24 |
| 11/19/2024 |
ENGR - Drainage Structures |
|
Complete (Recurring) |
Start of the dbl barrel 24”, good grade continue. |
| 11/21/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
Pipe is good to backfill Nov, 21st 2024 |
| 11/25/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
Pipe is good to backfill Nov, 21st 2024. 11/25/2024, drainage structure and dbl barrel pipe has passed. |