Permit Details

Status:
Inspections
Type:
Commercial Building
Address NEW:
5211 E VALENCIA RD
Apply Date:
12/08/2025
Applicant:
Blake Sickler
Description:
New ground up drive thru restaurant building.

Permit Reviews

Permit Number - TC-COM-1225-02209
Permit Status: Inspections
Permit Description: New ground up drive thru restaurant building.
Start Date Submittal Complete Date Status  
01/26/2026 COMMERCIAL REVIEW - FULL v.2 03/03/2026 APPROVED Review Details
04/09/2026 SPECIAL INSPECTION REVIEW v.1 04/09/2026 REQUIRES RESUBMIT Review Details
12/10/2025 COMMERCIAL REVIEW - FULL v.1 01/07/2026 REQUIRES RESUBMIT Review Details
04/09/2026 SPECIAL INSPECTION REVIEW v.2 04/13/2026 APPROVED Review Details
03/31/2026 ADMINISTRATIVE v.2 03/31/2026 REQUIRES RESUBMIT Review Details
03/10/2026 ADMINISTRATIVE v.1 03/10/2026 REQUIRES RESUBMIT Review Details
04/09/2026 ADMINISTRATIVE v.3 04/09/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-1225-02209
Permit Status: Inspections
Permit Description: New ground up drive thru restaurant building.
Total Outstanding Activity Conditions - 7
Date Name
02/11/2026 AIR BALANCING REPORT, INCLUDING HOOD CAPTURE & CONTAINMENT TESTING, IS REQUIRED.
02/11/2026 WATER STERILIZATION REPORT IS REQUIRED.
02/12/2026 Prior to Final Inspection, Exterior insulation and finish systems (EIFS) Special inspection Field Report shall be submitted. A water-resistive barrier coating complying with ASTM E2570 requires special inspection of the water-resistive barrier coating where installed over a sheathing substrate. IBC 1705.16.1
04/10/2026 SPECIAL INSPECTION OF EIFS
12/29/2025 SPECIAL INSPECTION OF CONCRETE CONSTRUCTION IS REQUIRED.
12/29/2025 SPECIAL INSPECTION OF SOILS AND FOUNDATIONS IS REQUIRED.
12/29/2025 SPECIAL INSPECTION OF WOOD CONSTRUCTION IS REQUIRED.

Conditions

Permit Number - TC-COM-1225-02209
Permit Status: Inspections
Permit Description: New ground up drive thru restaurant building.
Date Description Comments
12/10/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
12/10/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
12/29/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-COM-1225-02209
Permite Description: New ground up drive thru restaurant building.
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
05/29/2026 COT - LCPL - Plumbing Final N/A Re-inspection required 5-29-26: schedule this inspection under site.
06/12/2026 COT - LCBU - Masonry Pregrout N/A Partial Pass 6-12-26: reinforcement for cmu trash enclosure walls verified per plans. Okay to grout using a vibrator at 8'.
06/23/2026 COT - LCPL - Rough Soil N/A Partial Pass 6-23-26: underground DWV and domestic lines previously inspected and approved. Okay to backfill using shading materials.
06/26/2026 COT - LCEL - Electrical Underground N/A Not Ready 6: 26-26: not ready. Contractor to reschedule.
07/07/2026 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass 7.7.26
Partial pass, column footers 2 interior and 2 exterior.
07/13/2026 COT - LCBU - Preslab N/A Partial Pass 7/13/26: REINFORCEMENT/HOLD-DOWNS/FOOTINGS/ PER APPROVED PLANS OK TO PROCEED AT SLAB.
08/17/2026 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass
08/17/2026 COT - LCBU - Roof Nailing N/A Partial Pass 8.17.26
Various sheathing are soft and lost rigidity due to rain.
08/31/2026 COT - LCEL - Electrical Intermediate N/A Re-inspection required 8-31-26: in wall rough electrical-missing low in wall electrical receptacles at west wall, add pigtails to ground screws to in wall receptacles throughout, provide vertical supports for rmc at 10' intervals and within 12" of a receptacle box. We will look at the above required corrections at intermediates.
09/01/2026 COT - LCME - Mechanical Intermediate N/A Partial Pass 9/1/26: pookie at ducts verified. Okay to insulate trunks and continue with tie-ins at registers.
09/01/2026 COT - LCPL - Gas Pressure Test N/A Partial Pass 9/1/26: partial pass pending Ansul system. Gas lines verified at 15 psi.
09/10/2026 COT - LCBU - Framing N/A Partial Pass 9/10/26: pending backing at restrooms. Schedule plumbing intermediates prior to covering walls.
09/11/2026 COT - LCPL - Plumbing Roof Drains N/A Partial Pass 9/11/26: verified blocking at restrooms-okay to insulate in wall approved areas. Pending insulation at above ceiling plumbing and to verify supports.