Permit Details

Status:
In Review
Type:
Commercial Building
Address:
5951 S 12TH AV
Address NEW:
5951 S 12TH AV
Apply Date:
12/30/2024
Applicant:
Bruce Call
Description:
Phase 2 West Wing Building - two story classroom building REV3: 5/28/26 REV3: Corrections to the outdoor lighting calculations and color temperature.

Permit Reviews

Permit Number - TC-COM-1224-02437
Permit Status: In review
Permit Description: Phase 2 West Wing Building - two story classroom building REV3: 5/28/26 REV3: Corrections to the outdoor lighting calculations and color temperature.
Start Date Submittal Complete Date Status  
08/14/2026 SPECIAL INSPECTION REVIEW v.2 N/A IN REVIEW Review Details
04/07/2025 COMMERCIAL REVIEW - FULL v.2 04/28/2025 REQUIRES RESUBMIT Review Details
05/28/2025 RESTAMP - COMMERCIAL v.1 06/02/2025 APPROVED Review Details
05/28/2026 COMMERCIAL REVIEW - FULL REVISION v.1 06/09/2026 APPROVED Review Details
12/31/2024 COMMERCIAL REVIEW - FULL v.1 02/07/2025 REQUIRES RESUBMIT Review Details
06/26/2025 COMMERCIAL REVIEW - FULL REVISION v.1 06/26/2025 REQUIRES RESUBMIT Review Details
08/14/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 N/A IN REVIEW Review Details
04/30/2025 COMMERCIAL REVIEW - FULL v.3 05/28/2025 APPROVED Review Details
06/27/2025 COMMERCIAL REVIEW - FULL REVISION v.2 07/07/2025 APPROVED Review Details
08/05/2026 SPECIAL INSPECTION REVIEW v.1 08/06/2026 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-1224-02437
Permit Status: In review
Permit Description: Phase 2 West Wing Building - two story classroom building REV3: 5/28/26 REV3: Corrections to the outdoor lighting calculations and color temperature.
Date Description Comments
05/07/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
05/07/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
05/07/2025 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
05/07/2025 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
05/07/2025 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
05/07/2025 Masonry Inspection Report submittal review is required.
05/07/2025 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
12/31/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
05/07/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
05/07/2025 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
05/07/2025 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: In Review
Permit Number: TC-COM-1224-02437
Permite Description: Phase 2 West Wing Building - two story classroom building REV3: 5/28/26 REV3: Corrections to the outdoor lighting calculations and color temperature.
Total Outstanding Inspections - 23
Last Inspection Date Description Inspector Results Comments
09/12/2025 COT - HCPL - Plumbing Progress N/A Partial Pass 9/12/25: Plumbing underground per approved plans at rooms #101,102,107,108,109A. Ok to backfill progress areas. Shading required
02/06/2026 COT - HCBU - Masonry Pregrout N/A Partial Pass 2-6-26: reinforcement at cmu walls for classrooms 5& 6 verified per plans. Okay to grout Class room #5 @ 6th lift with a height of 26'. Okay to grout Classroom #6 @ 5th lift with a height at 20'. Wall between classroom's 5 & 6 on north side at 23'. Okay to grout boys/girls restrooms together with maintenance room.
10/23/2025 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 10-23-25: reinforcement on cmu wall verified per,plans. Only to grout 2nd lift at 8'.
05/05/2026 COT - HCEL - Electrical Intermediate N/A Partial Pass 5-5-26: in wall electrical at classrooms 101-106 approved. Okay to continue with construction at progress areas.
05/18/2026 COT - HCBU - Framing N/A Partial Pass 5/18/2026 all corrections were made from previous inspection. Okay to proceed progress areas.
05/11/2026 COT - HCPL - Plumbing Intermediate N/A Partial Pass 5/11/26: Plumbing intermediate in-wall approved in rooms 101,102,107,108 and 109
06/05/2026 COT - HCBU - Roof Nailing N/A Partial Pass 6-5-26: screw inspection for roof crickets approved-Okay to dry-in progress areas.
06/12/2026 COT - HCPL - Rough Soil N/A Partial Pass 6-12-26: verified 6-2" & 2-2" schedule 40 electrical conduits stub -ups for future use located on southeast side of site. Okay to backfill approximately 50' of trench using shading materials.
06/18/2026 COT - HCPL - Sewer N/A Re-inspection required 6-18-26: place sewer under test using a 10' stack.
06/25/2026 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass 6-25-26: second floor purple xp drywall screw inspection approved-Okay to tape & mud.
09/15/2025 COT - HCEL - Electrical Underground N/A Partial Pass 9/15/25: Partial pass for electrical underground from SES to Panel A ok to proceed with backfill.
07/09/2026 COT - HCME - Mechanical Above Ceiling N/A Re-inspection required Provide saddle straps at multiple locations. Missing returns in bathrooms. 7/9/2026
06/16/2026 COT - HCEL - Electrical Above Ceiling N/A Partial Pass 6-16-26: electrical above ceiling along 2nd floor hallway approved. Okay to continue with construction at progress areas.
07/10/2026 COT - HCBU - Building Above Ceiling N/A Partial Pass 7/10/2026 partial pass. 1st and 2nd floors classrooms approved. Pending bathrooms and mechanical rooms.
07/15/2026 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass 7-15-26: plumbing, mechanical & electrical above ceiling at the restrooms (room's 107/108 & 207/208) approved. Okay to cover progress areas.
07/17/2026 BULD - Electrical Clearance N/A Re-inspection required 7-17-26: duct seal is required at Subpanel A.
08/05/2026 COT - HCBU - CofO N/A Partial Pass 8/5/26: OKAY TO APPLY FOR LEVEL 4 TCO
08/05/2026 ENGR Engineering Final N/A Partial Pass Okay to apply for a Level 4 TCO
08/05/2026 COT - HCBU - Building Final N/A Partial Pass 8/5/26: OKAY TO APPLY FOR LEVEL 4 TCO
08/05/2026 COT - HCEL - Electrical Final N/A Partial Pass 8/5/26: OKAY TO APPLY FOR LEVEL 4 TCO
08/05/2026 COT - HCPL - Plumbing Final N/A Partial Pass 8/5/26: OKAY TO APPLY FOR LEVEL 4 TCO
COT - FCON - Alarm - Final N/A Not Ready
COT - FCON - Fire - Final N/A Not Ready Flushed out underground. Waiting for Underground permit to be approved and issued.

Completed Inspections

Permit Status: In Review
Permit Number: TC-COM-1224-02437
Permit Description: Phase 2 West Wing Building - two story classroom building REV3: 5/28/26 REV3: Corrections to the outdoor lighting calculations and color temperature.
Total Completed Inspections - 5
Date Description Inspector Results Comments
07/08/2026 PDSD Building Division SIte Consultation Passed
07/24/2026 BULD - Electrical Clearance Passed 7/24/26: TEP ECO FOR 5951 S 12TH AV SES 2M
08/03/2026 TRSP - ROW - Final/Close-Out Passed
08/04/2026 COT - FCON - Alarm - Final Passed
08/04/2026 COT - FCON - Sprinkler - Final Passed

Documents

File Name Document Type  
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
2025-6-25 PRCA PHASE 2 WEST WING - SF CORRECTION_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
63225131 PRCA SOUTH GEO REPORTSIGNED_V1.PDF DOCUMENTS VIEW
CONS-2025-4-28 PRCA PHASE 2 WEST WING ASPME_V3.PDF DOCUMENTS VIEW
PRCA CALC_V1.PDF DOCUMENTS VIEW
PRCA HVAC CALC_V1.PDF DOCUMENTS VIEW
SPECIAL_INSPECTION_CERTIFICATE SIGNED-2025-04-03_V1.PDF DOCUMENTS VIEW