| 04/23/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 4-23-26: okay for concrete placement at B-Decking/2nd level from classroom 202- 209. Note: Submit all related special inspection reports for mentioned above areas to the city for review. |
|
| 08/25/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 8/22/25: Reinforcement and Footer depth and width per approved plans at building footers. | |
| 08/26/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 8-26-25: verified reinforcement per S400 detail 412 for elevator shaft retaining wall at 4'. Okay to pour. | |
| 08/28/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 8-28-25: reinforcement/depth/width on column & stair footings verified per plans. Okay for concrete placement at progress areas. | |
| 09/08/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9/8/25: reinforcement per approved plans at Stem wall ok to proceed with concrete placement. | |
| 09/19/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9-19-25: vapor barrier/reinforcement for slab on grade verified per plans. Okay for concrete placement at progress areas. | |
| 10/16/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 10/16/25: First lift at 4' approved. Reinforcement per approved plans. Ok to proceed with grout at columns and walls, | |
| 10/23/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 10-23-25: reinforcement on cmu wall verified per,plans. Only to grout 2nd lift at 8'. |