Permit: TC-COM-1224-02437

Parcel: 13809002E


Addresses:

5951 S 12TH AV

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Masonry Pregrout 

Date Description Inspector Results Comments
01/15/2026 COT - HCBU - Masonry Pregrout  Partial Pass 1-15-26:reinforcement on cmu walls for north classrooms-3 in total were verified per plans-okay to grout 4th lift at 15' 8".
01/21/2026 COT - HCBU - Masonry Pregrout  Partial Pass 1-21-26: reinforcement at cmu classrooms 6,5,4,3 verified per plans-okay to grout 5th lift at 20'.
01/28/2026 COT - HCBU - Masonry Pregrout  Partial Pass 1-28-26: verified reinforcement on classrooms 1-4 and embeds on classroom's 1&2 from the north. Okay to grout progress areas for 6th lift at 23'4".
02/03/2026 COT - HCBU - Masonry Pregrout  Partial Pass 2-3-26: Reinforcement at cmu walls for classroom's 1-4 verified per plans. Okay for grout top out-east & west walls at 28' and 27' for north & south walls.
02/06/2026 COT - HCBU - Masonry Pregrout  Partial Pass 2-6-26: reinforcement at cmu walls for classrooms 5& 6 verified per plans. Okay to grout Class room #5 @ 6th lift with a height of 26'. Okay to grout Classroom #6 @ 5th lift with a height at 20'. Wall between classroom's 5 & 6 on north side at 23'. Okay to grout boys/girls restrooms together with maintenance room.
02/11/2026 COT - HCBU - Masonry Pregrout  Partial Pass 2-11-26: reinforcement at peak for classroom's 3 & 4 verified per plans-okay to pour grout at 34'. Reinforcement at classroom 6 approved at 24'-okay to pour 6th lift. Interior walls of boys/girl 's restroom together with maintenance room at 23'.
02/13/2026 COT - HCBU - Masonry Pregrout  Partial Pass 2-13-26: reinforcement at the following locations verified per plans & are okay to grout: exterior walls of classroom 6 at 29' 4", interior walls for room's 105B & 106B at 25' 4". Reinforcement for top out at west peak of classrooms 3 & 4 at 32'. Reinforcement for 7 Columns located between the south & north stairs verified per details located on S400- okay to grout at 10' 8".
02/19/2026 COT - HCBU - Masonry Pregrout  Partial Pass 2-19-26: reinforcement for the cmu wall of south stairs verified per plans with a height at 11' 2" & the far end column at the south stair is at 12'. Reinforcement at north cmu wall at the stairs is at 12' and column at far end of north stair is at 10' 8". All progress areas are okay to grout.
02/23/2026 COT - HCBU - Masonry Pregrout  Partial Pass 2/23/2026 partial pass. Both south and north stairwells approved at top out. Okay to grout all progress areas.
03/04/2026 COT - HCBU - Masonry Pregrout  Partial Pass 3-4-26: reinforcement for all columns approved -okay to grout at 16'.
03/06/2026 COT - HCBU - Masonry Pregrout  Partial Pass 3-6-26: reinforcement at all 15 columns verified per plans. Okay to grout 5th lift at 20'.
03/10/2026 COT - HCBU - Masonry Pregrout  Partial Pass 3-10-26: top out for 15 columns approved-okay to grout at 22'.
10/16/2025 COT - HCBU - Masonry Pregrout  Partial Pass 10/16/25: First lift at 4' approved. Reinforcement per approved plans. Ok to proceed with grout at columns and walls,
10/20/2025 COT - HCBU - Masonry Pregrout  Partial Pass 10-20-25: reinforcement on columns, stairwells , and south end of cmu wall verified per plans. Okay to grout 1st lift at 4'.
11/13/2025 COT - HCBU - Masonry Pregrout  Partial Pass 11/13/25: reinforcement at columns, stairwells at 12' approved ok to proceed with grout, classrooms (203,204,205,206) approved for to grout at 12'.
11/18/2025 COT - HCBU - Masonry Pregrout  Partial Pass 11-18-25: reinforcement for cmu wall at south bathrooms verified per plans. Okay to grout 3rd lift at 11' 4".
12/10/2025 COT - HCBU - Masonry Pregrout  Partial Pass 12/10/2025 3rd lift at elevator walls approved. Okay to grout progress areas.