Permit: TC-COM-1124-02257
Permit Details
Apply Date:
11/25/2024
Applicant:
Dennis Caldwell
Description:
ELVIRA BUILDING 2731 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-1549 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 5 OVERHEAD DOORS FOR NEW TRUCK DOCKS, FOUR POSITIONED AT EXISTING OPENING. 1 POSITIONED AT A NEW OPENING. 2 ADDITIONAL OVERHEAD DOORS IN EXISTING OPENINGS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
Permit Reviews
Permit Number - TC-COM-1124-02257
Permit Status: Complete
Permit Description: ELVIRA BUILDING 2731 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-1549 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 5 OVERHEAD DOORS FOR NEW TRUCK DOCKS, FOUR POSITIONED AT EXISTING OPENING. 1 POSITIONED AT A NEW OPENING. 2 ADDITIONAL OVERHEAD DOORS IN EXISTING OPENINGS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/08/2025 | REQUIRES RESUBMIT |
| 01/13/2025 | COMMERCIAL REVIEW - FULL v.2 | 02/04/2025 | REQUIRES RESUBMIT |
| 02/27/2025 | COMMERCIAL REVIEW - FULL v.3 | 03/27/2025 | APPROVED |
| 08/13/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/14/2025 | APPROVED |
| 03/28/2025 | RESTAMP - COMMERCIAL v.1 | 03/28/2025 | APPROVED |
| 08/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/25/2025 | APPROVED |
| 12/04/2024 | COMMERCIAL REVIEW - FULL v.1 | 12/26/2024 | REQUIRES RESUBMIT |
| 09/12/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 09/15/2025 | APPROVED |
Conditions
Permit Number - TC-COM-1124-02257
Permit Status: Complete
Permit Description: ELVIRA BUILDING 2731 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-1549 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 5 OVERHEAD DOORS FOR NEW TRUCK DOCKS, FOUR POSITIONED AT EXISTING OPENING. 1 POSITIONED AT A NEW OPENING. 2 ADDITIONAL OVERHEAD DOORS IN EXISTING OPENINGS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
| Date | Description | Comments |
|---|---|---|
| 12/04/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 12/10/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 12/10/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 01/13/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 08/14/2025 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 12/10/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 12/10/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1124-02257
Permite Description: ELVIRA BUILDING 2731 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-1549 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 5 OVERHEAD DOORS FOR NEW TRUCK DOCKS, FOUR POSITIONED AT EXISTING OPENING. 1 POSITIONED AT A NEW OPENING. 2 ADDITIONAL OVERHEAD DOORS IN EXISTING OPENINGS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/15/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | 7-15-25: not applicable |
| 05/14/2025 | COT - HCBU - Building Progress | N/A | Re-inspection required | 5-14-25, plumbing progress inspection called in with no additional notes. Arrived on site at approximately 1135 hours. Called contractor at 1139 hours and received no answer. I waited until 1151 hours and left. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1124-02257
Permit Description: ELVIRA BUILDING 2731 TENANT IMPROVEMENT. NO CHANGE OF USE OR ADDITIONAL SF TO EXISTING BUILDING. +/-1549 SF OF OFFICE SPACE, RESTROOMS AND THE REST AS OPEN WAREHOUSE SPACE. 5 OVERHEAD DOORS FOR NEW TRUCK DOCKS, FOUR POSITIONED AT EXISTING OPENING. 1 POSITIONED AT A NEW OPENING. 2 ADDITIONAL OVERHEAD DOORS IN EXISTING OPENINGS. MECHANICAL AND PLUMBING TO BE REWORKED TO FIT NEW PARTITION LAYOUT. NEW ELECTRICAL WORK TO INCLUDE POWER AND LIGHTING THROUGHOUT BUILDING.
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/04/2025 | COT - HCPL - Rough Soil | Passed | 4/4/25: plumbing underground passed. | |
| 05/05/2025 | COT - HCEL - Electrical Intermediate | Passed | 5-5-25, in wall electrical intermediate inspection verified per plans. Okay to continue with construction at progress areas. | |
| 05/05/2025 | COT - HCBU - Framing | Passed | 5-5-25, framing inspection approved. Okay to continue with at progress areas. | |
| 05/14/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 07/17/2025 | BULD - Electrical Clearance | Passed | 7-17-25: okay to energize panel. ECO clearance sent to TEP. | |
| 08/27/2025 | COT - FCON - Alarm - Final | Passed | ||
| 09/10/2025 | COT - FCON - Fire - Final | Passed | Need knox box installed and fire extinguishers mounted. 9/10/25 Completed per Will Motto | |
| 08/27/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 8-27-25: previously inspected and approved. | |
| 08/27/2025 | ENGR Engineering Final | Passed | ||
| 08/27/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 08/27/2025 | COT - HCBU - Building Progress | Passed | 8-27-25: approved | |
| 08/27/2025 | COT - HCEL - Electrical Above Ceiling | Passed | 8-27-25: approved | |
| 08/27/2025 | COT - HCEL - Electrical Progress | Passed | 8-27-25: approved. | |
| 08/27/2025 | COT - HCME - Mechanical Progress | Passed | 8-27-25: approved | |
| 09/02/2025 | COT - HCBU - Building Above Ceiling | Passed | 9-2-25: approved. | |
| 09/02/2025 | COT - HCEL - Electrical Final | Passed | 9-2-25: electrical final approved. | |
| 09/02/2025 | COT - HCME - Mechanical Above Ceiling | Passed | 9-2-25: approved. | |
| 09/02/2025 | COT - HCME - Mechanical Final | Passed | 9-2-25: mechanical final approved. | |
| 09/02/2025 | COT - HCME - Mechanical Intermediate | Passed | 9-2-25: approved. | |
| 09/09/2025 | COT - HCBU - Building Final | Passed | 9-9-25: building final approved. All conditions have been met. |