Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 05/16/2025 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
5-16-25, above ceiling and in wall domestic verified per plans- insulation of hot water copper line will be verified on final. Okay to continue with construction at progress areas. |
| 07/15/2025 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
7-15-25: mechanical nearly complete at new construction areas. Pending architect submittal with regard to which mechanical equipment will be utilized in existing warehouse areas. |
| 08/27/2025 |
COT - HCME - Mechanical Progress |
|
Passed |
8-27-25: approved |