Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
In Review
Type:
Commercial Building
Address NEW:
10041 E OLD VAIL RD
Apply Date:
11/03/2022
Applicant:
Jake Hughes
Description:
New Commercial Storage Building

Permit Reviews

Permit Number - TC-COM-1122-00044
Permit Status: In review
Permit Description: New Commercial Storage Building
Start Date Submittal Complete Date Status  
06/20/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/23/2025 APPROVED Review Details
03/18/2024 COMMERCIAL REVIEW - FULL v.2 04/18/2024 APPROVED Review Details
11/14/2022 COMMERCIAL REVIEW - FULL v.1 10/18/2023 REQUIRES RESUBMIT Review Details
05/14/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 05/15/2025 APPROVED Review Details
04/18/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/22/2025 REQUIRES RESUBMIT Review Details
07/16/2024 COMMERCIAL REVIEW - FULL v.1 08/16/2024 REQUIRES RESUBMIT Review Details
08/16/2024 COMMERCIAL REVIEW - FULL v.2 09/05/2024 REQUIRES RESUBMIT Review Details
10/04/2024 COMMERCIAL REVIEW - FULL v.3 10/16/2024 APPROVED Review Details
06/27/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/01/2025 APPROVED Review Details
11/14/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/18/2025 REQUIRES RESUBMIT Review Details
12/01/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 12/01/2025 REQUIRES RESUBMIT Review Details
12/08/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.3 N/A IN REVIEW Review Details
03/05/2025 COMMERCIAL REVIEW - FULL REVISION v.1 04/02/2025 APPROVED Review Details
10/16/2024 RESTAMP - COMMERCIAL v.1 10/22/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-1122-00044
Permit Status: In review
Permit Description: New Commercial Storage Building
Total Outstanding Activity Conditions - 15
Date Name
06/15/2025 Elevator Designs must be submitted and approved prior to ...
06/15/2025 Fire Stopping Designs (penetration and joints) must be submitted and approved prior to installation.
06/15/2025 Prefabricated Canopy Designs must be submitted and approved prior to fabrication.
10/22/2024 COMMISSIONING REPORT IS REQUIRED.
10/22/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/22/2024 ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
10/22/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/22/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
10/22/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
10/22/2024 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
10/22/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
10/22/2024 Masonry Inspection Report submittal review is required.
10/22/2024 Post-Installed Anchor Inspection Report is required.
10/22/2024 SPECIAL INSPECTION FOR EFIS IS REQUIRED
10/22/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.

Conditions

Permit Number - TC-COM-1122-00044
Permit Status: In review
Permit Description: New Commercial Storage Building
Date Description Comments
09/26/2023 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
10/22/2024 AIR BALANCING REPORT IS REQUIRED.
10/22/2024 Metal stud designs must be submitted and approved prior to final
10/22/2024 Store front and window system designs must be submitted and approved prior to final
07/01/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
08/20/2024 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
10/22/2024 Stair Designs must be submitted and approved prior to...
10/22/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: In Review
Permit Number: TC-COM-1122-00044
Permite Description: New Commercial Storage Building
Total Outstanding Inspections - 14
Last Inspection Date Description Inspector Results Comments
11/13/2024 COT - HCBU - Interior Shear Bracing N/A Partial Pass 11-13-24, reinforcement per approved plans on elevator shaft walls (4), okay to grout.
11/06/2024 COT - HCBU - Masonry Pregrout N/A Partial Pass 11-6-24: reinforcement per plan 2nd lift at 96" A. F. F. at NE stairwell. NE stairwell being grouted.
12/30/2024 COT - HCBU - Framing N/A Partial Pass 12/30/24: PARTIAL PASS--2nd floor wall framing completed, worker's are screwing off the 3rd floor decking off.
02/05/2025 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass 2-5-25, intermediate on 1st floor office area, restrooms at office area, and restroom on 2nd floor on southeast quad. Partial pass on progress areas-okay for wall covering.
02/05/2025 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Partial Pass 2-5-25, exterior sheathing/nailing on exterior west wall verified as per approved plans. Okay to continue construction on progress areas.
10/22/2024 COT - HCEL - Electrical Underground N/A Partial Pass 2/0 Ufer for SES. 2 Ground rods with # 6 ground to SES. 4” conduit for telephone (utilities) schedule 40. Remainder of x9 1” stubbing up into wall in I.T room. Okay to backfill progress areas. 10/22/2024
02/06/2025 COT - HCPL - Plumbing Intermediate N/A Partial Pass 2-6-25, plumbing intermediate inspection for office and bathrooms at office on 1st floor together with bathroom on 2nd floor verified as per approved plans. Okay to continue construction at progress areas.
06/17/2025 COT - HCEL - Electrical Above Ceiling N/A Not Ready Missing deadfront at panel 3rd floor. Add labeling to all panels along with printed panel schedules. Add cover plates to blanks. Label all j boxes. Open j boxes throughout need to be made up and labeled. Mc cable hanging for outdoor signage. Stopped inspection other items may apply. 6/17/2025
02/28/2025 COT - HCEL - Electrical Intermediate N/A Partial Pass 2-6-25, office and bathrooms at office on 1st floor together with bathroom on 2nd floor verified as per approved plans. Okay to continue construction at progress areas.
2/28/25:electrical wall cover up in both elevator machine rooms partial pass.
07/10/2025 ENGR Engineering Final N/A Partial Pass Okay fot Level 4 TCO
07/09/2025 COT - FCON - Fire - Final N/A Partial Pass ok level 4 tco just need the elevator to pass state inspection.
07/10/2025 COT - HCBU - Building Final N/A Partial Pass 7/10/25: OK FOR LEVEL 4 TCO
06/17/2025 COT - HCEL - Outdoor Lighting N/A Not Ready Missing deadfront at panel 3rd floor. Add labeling to all panels along with printed panel schedules. Add cover plates to blanks. Label all j boxes. Open j boxes throughout need to be made up and labeled. Mc cable hanging for outdoor signage. Stopped inspection other items may apply. 6/17/2025
06/18/2025 COT - HCPL - Yard Water Line N/A Re-inspection required There is no history on water line inspection. Need to verify size, depth and tracer wire. 6/18/2025

Completed Inspections

Permit Status: In Review
Permit Number: TC-COM-1122-00044
Permit Description: New Commercial Storage Building
Total Completed Inspections - 27
Date Description Inspector Results Comments
10/11/2024 COT - HCBU - Excavation/Rebar/Zoning Passed Forms are set for 2 elevator pits and 2 stairwell footings, rebar is properly installed per plan and supported off of soil. Okay to proceed with pouring concrete for footings.
10/11/2024 COT - HCPL - Rough Soil Passed Underground plumbing is complete and under water test with no leaks. Okay to shade pipes and backfill trenches.
10/22/2024 COT - BULD - SWG Clearance Passed
11/25/2024 COT - HCBU - Interior Shear Bracing Passed 11-25-24: CMU block and rebar reinforcement are properly installed per plan on both stairways to 26'. Okay to grout.
12/13/2024 COT - HCBU - Masonry Pregrout Passed 12-13-24: elevator shaft 1 and 2 are okay to grout.
01/06/2025 COT - HCBU - Preslab Passed 1/6/23: #5 rebar mat for 3rd floor decking is properly tied and supported off of metal decking as per plans. Okay to pour concrete for 3rd floor decking.
01/24/2025 COT - HCBU - Framing Passed 1/24/25: Roof decking is properly secured to roof framing. Okay to proceed with roofing application.
02/21/2025 COT - HCPL - Sewer Passed Building underground plumbing is connected to main sewer line with green tracer wire installed. Okay to shade pipe and backfill trench.
05/15/2025 COT - HCBU - Exterior Clips/Sheathing Passed
05/15/2025 COT - HCBU - Roof Nailing Passed
05/15/2025 COT - HCBU - Firewall/Fire Barrier/Firestop Passed
05/15/2025 COT - HCEL - Electrical Underground Passed
05/28/2025 COT - HCEL - Grounding/Bonding Passed 5-28-25, verified grounding/bonding as per plans for main distribution -Type 3R Enclosure.
05/28/2025 BULD - Electrical Clearance Passed 5-28-25, main distribution -Type 3R Enclosure approved and is okay to be energized. ECO clearance issued to TEP.
06/18/2025 COT - HCPL - Plumbing Intermediate Passed
06/18/2025 COT - HCPL - Plumbing Above Ceiling Passed
06/26/2025 COT - HCEL - Electrical Above Ceiling Passed 6/26/2025 all corrections have been made.
06/26/2025 COT - HCEL - Electrical Intermediate Passed
06/26/2025 COT - HCEL - Electrical Final Passed 6/26/2025 all corrections have been made. Approved.
06/30/2025 COT - HCME - Mechanical Above Ceiling Passed
06/30/2025 COT - HCME - Mechanical Intermediate Passed
06/30/2025 COT - HCME - Mechanical Final Passed
06/30/2025 COT - HCPL - Plumbing Final Passed
07/08/2025 COT - LCBU - Building Final Passed 7-8-25: building final approved.
Note: see pending conditions.
07/10/2025 COT - HCBU - Building Above Ceiling Passed
07/10/2025 COT - HCEL - Outdoor Lighting Passed
07/10/2025 COT - HCPL - Yard Water Line Passed

Documents

File Name Document Type  
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
CAP OLD VAIL TAB REPORT_V1.PDF DOCUMENTS VIEW
CHLORINATION AND FIELD REPORT-2025-06-19_V1.PDF DOCUMENTS VIEW
S122_STOREFRONT SHOP DRAWINGS - PRODUCT DATA (S)_142ARCH REVIEW (1)_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-REV PLAN SET_V1.PDF DOCUMENTS VIEW
CONS-PLAN SET_V3.PDF DOCUMENTS VIEW
REV1_2_CAP OLD VAIL GEOTECHNICAL REPORT_2021.5.24_V2.PDF DOCUMENTS VIEW
REV1_2_CAP OLD VAIL GEOTECHNICAL REPORT_2021.5.24_V2ORIGIN_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-4_CONS-STANTEC_APPROVED_PLANS_V1-4_V2.PDF DOCUMENTS VIEW