Permit: TC-COM-0724-01311
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
9537 E OLD VAIL RD
Address NEW:
9537 E OLD VAIL RD
Apply Date:
07/03/2024
Applicant:
Description:
6,000 SF Office Building with 4,000 SF covered yard and 10,000 SF Premanufactured Metal building with 5,000 SF of covered yard. REV1: The Revision shows the SES moving from the southwest corner of Building 1 to the north side of the same building to avoid a conflict. REV2: TEMPORARY POWER PANEL
Permit Reviews
Permit Number - TC-COM-0724-01311
Permit Status: Complete
Permit Description: 6,000 SF Office Building with 4,000 SF covered yard and 10,000 SF Premanufactured Metal building with 5,000 SF of covered yard.
REV1: The Revision shows the SES moving from the southwest corner of Building 1 to the north side of the same building to avoid a conflict.
REV2: TEMPORARY POWER PANEL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/01/2024 | RESTAMP - COMMERCIAL v.1 | 10/15/2024 | APPROVED |
| 08/21/2024 | COMMERCIAL REVIEW - FULL v.2 | 09/23/2024 | REQUIRES RESUBMIT |
| 05/27/2025 | COMMERCIAL REVIEW - FULL REVISION v.4 | 05/29/2025 | APPROVED |
| 09/25/2024 | COMMERCIAL REVIEW - FULL v.3 | 10/01/2024 | APPROVED |
| 05/27/2025 | COMMERCIAL REVIEW - FULL REVISION v.3 | 05/27/2025 | REQUIRES RESUBMIT |
| 05/09/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 05/09/2025 | REQUIRES RESUBMIT |
| 07/08/2024 | COMMERCIAL REVIEW - FULL v.1 | 08/09/2024 | REQUIRES RESUBMIT |
| 03/04/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/06/2026 | APPROVED |
| 04/22/2025 | RESTAMP - COMMERCIAL v.1 | 04/23/2025 | APPROVED |
| 03/28/2025 | COMMERCIAL REVIEW - FULL v.1 | 03/28/2025 | REQUIRES RESUBMIT |
| 04/01/2025 | COMMERCIAL REVIEW - FULL v.2 | 04/22/2025 | APPROVED |
| 05/14/2025 | COMMERCIAL REVIEW - FULL REVISION v.2 | 05/21/2025 | REQUIRES RESUBMIT |
| 03/25/2026 | SPECIAL INSPECTION REVIEW v.2 | 03/26/2026 | APPROVED |
| 03/16/2026 | SPECIAL INSPECTION REVIEW v.1 | 03/23/2026 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0724-01311
Permit Status: Complete
Permit Description: 6,000 SF Office Building with 4,000 SF covered yard and 10,000 SF Premanufactured Metal building with 5,000 SF of covered yard.
REV1: The Revision shows the SES moving from the southwest corner of Building 1 to the north side of the same building to avoid a conflict.
REV2: TEMPORARY POWER PANEL
| Date | Description | Comments |
|---|---|---|
| 07/08/2024 | Please contact Pima County Addressing to verify official address. Addressing@pima.gov or 520-724-9512 | |
| 10/01/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 07/08/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 10/01/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 10/01/2024 | Masonry Inspection Report submittal review is required. | |
| 07/08/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 03/05/2026 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0724-01311
Permite Description: 6,000 SF Office Building with 4,000 SF covered yard and 10,000 SF Premanufactured Metal building with 5,000 SF of covered yard.
REV1: The Revision shows the SES moving from the southwest corner of Building 1 to the north side of the same building to avoid a conflict.
REV2: TEMPORARY POWER PANEL
Total Outstanding Inspections - 16
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 7-14-25: excavation/reinforcement on 9 warehouse footings/columns verified per plans. Okay |
| 11/03/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 11/3/25 partial pass for dumpster pan and exterior wall |
| 11/17/2025 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | 11/14/25: ABOVE CEILING ELECTRICAL,MECHANICAL,PLUMBING,BUILDING PASSED IN OFFICE BUILDING |
| 11/17/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 11/14/25: ABOVE CEILING ELECTRICAL,MECHANICAL,PLUMBING,BUILDING PASSED IN OFFICE BUILDING |
| 11/17/2025 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | 11/14/25: ABOVE CEILING ELECTRICAL,MECHANICAL,PLUMBING,BUILDING PASSED IN OFFICE BUILDING |
| 11/17/2025 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 11/14/25: ABOVE CEILING ELECTRICAL,MECHANICAL,PLUMBING,BUILDING PASSED IN OFFICE BUILDING |
| 06/04/2025 | COT - HCBU - Preslab | N/A | Partial Pass | 6-4-25: reinforcement layout together with excavation for warehouse verified per plan. Okay to pour concrete. |
| 02/12/2025 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 2-12-25, west wall at 1st lift-okay to grout. Northeast section of north wall(1st lift) verified as per approved plans and is okay to grout. Drainage area of northeast section of cmu wall also okay to pour grout (1st lift). |
| 06/18/2025 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | Partial pass. Hardware approved at exterior parapet all around. Okay to proceed with sheathing. 6/18/202 |
| 11/07/2025 | COT - HCBU - Framing | N/A | Partial Pass | 11-7-25: Interior metal framing for Building 2, room's 202-206 approved. A 3party inspector verified interior steel framing and exterior framing was installed by a metal framing. Verify that there are no additional framing requirements for Building 1. Okay to continue with construction at Building 2 progress areas. |
| 12/08/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 12.8.25 Partial pass for 15'6" deep foundation beams at parking structure |
| 06/04/2025 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | 6-4-25: partial pass for copper ground/bonding at warehouse. |
| 11/17/2025 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 11/14/25: ABOVE CEILING ELECTRICAL,MECHANICAL,PLUMBING,BUILDING PASSED IN OFFICE BUILDING |
| 11/12/2024 | COT - HCPL - Sewer | N/A | Partial Pass | 11-12-24, sewer pressure test approved. Okay to proceed with construction. |
| 11/25/2025 | COT - HCEL - Outdoor Lighting | N/A | Partial Pass | Total of 2 light pole bases per detail 30 page S1.5. 1 Flag pole foundation per detail 31 page S1.5 okay for concrete placement. 11/25/2025 |
| 03/03/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0724-01311
Permit Description: 6,000 SF Office Building with 4,000 SF covered yard and 10,000 SF Premanufactured Metal building with 5,000 SF of covered yard.
REV1: The Revision shows the SES moving from the southwest corner of Building 1 to the north side of the same building to avoid a conflict.
REV2: TEMPORARY POWER PANEL
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/18/2024 | COT - HCPL - Plumbing Intermediate | Passed | 11-18-24, verified pressure for all sections of water line. Okay to backfill-provide shading. | |
| 03/13/2025 | COT - HCPL - Rough Soil | Passed | 3-13-25, underground plumbing on Building 1 verified per approved plans. Okay to backfill with shading materials. | |
| 06/18/2025 | COT - HCBU - Roof Nailing | Passed | ||
| 09/26/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 9-26-25: reinforcement for Building 1 cover slab on grade verified per plans-okay for concrete placement at progress areas. | |
| 11/03/2025 | BULD - Electrical Clearance | Passed | Ready for temp power CLEARANCE ECO | |
| 12/08/2025 | COT - HCBU - Building Progress | Passed | 12.8.25 Partial pass for 15'6" deep foundation beams at parking structure |
|
| 12/12/2025 | COT - HCBU - Building Above Ceiling | Passed | ||
| 12/12/2025 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 12/12/2025 | COT - HCME - Mechanical Above Ceiling | Passed | 12.12.25 Approved |
|
| 12/12/2025 | COT - HCPL - Plumbing Above Ceiling | Passed | 12.12.25 Approved |
|
| 12/31/2025 | COT - HCBU - Preslab | Passed | ||
| 02/10/2026 | COT - LCBU - Building Progress | Passed | 2-10-26: approved. | |
| 02/10/2026 | COT - HCBU - Exterior Clips/Sheathing | Passed | 2-10-26: exterior/interior clips/sheathing approved. | |
| 02/10/2026 | COT - HCBU - Framing | Passed | 2-10-26: framing/exterior/interior clips/sheathing approved. | |
| 02/10/2026 | COT - HCEL - Electrical Intermediate | Passed | 2-10-26: approved. | |
| 02/10/2026 | COT - HCEL - Electrical Progress | Passed | 2-10-26: electrical progress approved. | |
| 02/10/2026 | COT - HCEL - Electrical Underground | Passed | 2-10-26: electrical underground approved. | |
| 02/10/2026 | COT - HCEL - Grounding/Bonding | Passed | 2-10-26: approved. | |
| 02/10/2026 | COT - HCPL - Plumbing Progress | Passed | 2-10-26: approved. | |
| 02/10/2026 | COT - HCPL - Sewer | Passed | 2-10-26: approved. | |
| 02/24/2026 | COT - HCEL - Outdoor Lighting | Passed | 2-24-26: exterior lighting specifications on site. Contractor to submit to the city for record purposes/review. | |
| 03/03/2026 | COT - FCON - Alarm - Final | Passed | Approved on 2/9/26 on permit TF-FCP-0725-00602 | |
| 03/03/2026 | COT - FCON - Fire - Final | Passed | ||
| 03/03/2026 | ENGR Engineering Final | Passed | ||
| 03/03/2026 | TRSP - ROW - Final/Close-Out | Passed | Work was completed outside of the right of way | |
| 03/03/2026 | COT - FCON - Sprinkler - Final | Passed | Approved on 2/9/26 on permit TF-FCP-0425-00301 | |
| 03/03/2026 | COT - HCBU - Building Final | Passed | ||
| 03/03/2026 | COT - HCBU - CofO | Passed | ||
| 03/03/2026 | COT - HCEL - Electrical Final | Passed | ||
| 03/03/2026 | COT - HCME - Mechanical Final | Passed | ||
| 03/03/2026 | COT - HCPL - Plumbing Final | Passed | ||
| 03/03/2026 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 03/03/2026 | COT - HCME - Mechanical Progress | Passed | ||
| 03/03/2026 | COT - HCME - Mechanical Intermediate | Passed |