Permit: TC-COM-0724-01311

Parcel: 141185450


Addresses:

9537 E OLD VAIL RD

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Masonry Pregrout 

Date Description Inspector Results Comments
01/23/2025 COT - HCBU - Masonry Pregrout  Partial Pass 1-23-25, rebar/spacing verified as per approved plans. Okay to grout 1st lift for north and east retaining/wall
01/23/2026 COT - HCBU - Masonry Pregrout  Passed 1-23-26: cmu walls at top out verified and approved by Brian with engineering. Okay to grout at your convenience.
01/23/2026 COT - HCBU - Masonry Pregrout  Re-inspection required 1-23-26: vertical reinforcement at cmu walls not per plans. Spacing calls for #5's at 48" o.c...Check cmu walls and reschedule when ready.
02/12/2025 COT - HCBU - Masonry Pregrout  Partial Pass 2-12-25, west wall at 1st lift-okay to grout. Northeast section of north wall(1st lift) verified as per approved plans and is okay to grout. Drainage area of northeast section of cmu wall also okay to pour grout (1st lift).
02/27/2025 COT - HCBU - Masonry Pregrout  Partial Pass 12-10-24, rebar spacing/sizes and spacing verified as per approved plans. Okay to grout.
12/18/24: reinforcement per plan at at East retaining wall top out ok to proceed.
1-23-25, rebar/spacing verified as per approved plans. Okay to grout 1st lift for north and east retaining/wall.

2-12-25, west wall at 1st lift-okay to grout. Northeast section of north wall(1st lift) verified as per approved plans and is okay to grout. Drainage area of northeast section of cmu wall also okay to pour grout (1st lift).
2/27/25: second lift at north east corner to north west corner complete ok to grout, south west top out complete midway.
03/25/2025 COT - HCBU - Masonry Pregrout  Partial Pass 3-25-25, reinforcement for stem wall at south end of Building 1 per plans-okay to grout. Vertical reinforcement for east wall at approximately 160'- okay for grout 1st lift
04/22/2025 COT - HCBU - Masonry Pregrout  Partial Pass 4-22-25, approximately 35' of reinforcement verified per plans on northwest wall together with another 60' of reinforcement along southeastern section of wall-each okay to grout. South end of cmu's reinforcement for Building 1 also verified and is okay to grout 1st lift at 4'.
04/29/2025 COT - HCBU - Masonry Pregrout  Partial Pass 12-10-24, rebar spacing/sizes and spacing verified as per approved plans. Okay to grout.
12/18/24: reinforcement per plan at at East retaining wall top out ok to proceed.
1-23-25, rebar/spacing verified as per approved plans. Okay to grout 1st lift for north and east retaining/wall.

2-12-25, west wall at 1st lift-okay to grout. Northeast section of north wall(1st lift) verified as per approved plans and is okay to grout. Drainage area of northeast section of cmu wall also okay to pour grout (1st lift).
2/27/25: second lift at north east corner to north west corner complete ok to grout, south west top out complete midway.
3-25-25, reinforcement for stem wall at south end of Building 1 per plans-okay to grout. Vertical reinforcement for east wall at approximately 160'- okay for grout 1st lift.
4-22-25, approximately 35' of reinforcement verified per plans on northwest wall together with another 60' of reinforcement along southeastern section of wall-each okay to grout. South end of cmu's reinforcement for Building 1 also verified and is okay to grout 1st lift at 4'.
4/29/25: south end of CMU wall for building 1 reinforced per plans ok to proceed with grout. 2nd lift 4'-8'.
05/05/2025 COT - HCBU - Masonry Pregrout  Partial Pass 5-5-25, reinforcement on Building 1 verified per plans. Okay to grout 4th lift at 14' 8".
05/09/2025 COT - HCBU - Masonry Pregrout  Partial Pass 5/9/2025. Top out at building 1 approved. Reinforcement per plan. Okay to grout progress areas.
10/14/2025 COT - HCBU - Masonry Pregrout  Partial Pass 10-14-25: top out of perimiter wall at rear and retention basin-Okay to grout.
11/25/2025 COT - HCBU - Masonry Pregrout  Not Ready
12/10/2024 COT - HCBU - Masonry Pregrout  Partial Pass 12-10-24, rebar spacing/sizes and spacing verified as per approved plans. 1st lift Okay to grout.
12/18/2024 COT - HCBU - Masonry Pregrout  Partial Pass 12-10-24, rebar spacing/sizes and spacing verified as per approved plans. Okay to grout.
12/18/24: reinforcement per plan at at East retaining wall top out ok to proceed.