Permit: TC-COM-0424-00685
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
2705 E MEDINA RD UNIT 111
Address NEW:
2705 E MEDINA RD UNIT 111
Apply Date:
04/16/2024
Applicant:
Laura Moreno
Description:
Open Office area's height for multi-purpose option. Includes ceiling & associated mech, elec REV1: expanding area of work and installing equipment, self-contained chemical storage in the private yard REV2: The additional scope that includes expanding the area of work to house new equipment and adding a new unisex shower, janitor’s closet with a mop sink, and a new storage closet. This revision includes the architectural, mechanical, and electrical improvements required for the updated scope.
Permit Reviews
Permit Number - TC-COM-0424-00685
Permit Status: Issued
Permit Description: Open Office area's height for multi-purpose option. Includes ceiling & associated mech, elec REV1: expanding area of work and installing equipment, self-contained chemical storage in the private yard
REV2: The additional scope that includes expanding the area of work to house new equipment and adding a new unisex shower, janitor’s closet with a mop sink, and a new storage closet. This revision includes the architectural, mechanical, and electrical improvements required for the updated scope.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/03/2025 | RESTAMP - COMMERCIAL v.1 | 09/04/2025 | APPROVED |
| 03/17/2025 | RESTAMP - COMMERCIAL v.1 | 03/20/2025 | APPROVED |
| 05/14/2024 | COMMERCIAL REVIEW - FULL v.1 | 05/14/2024 | REQUIRES RESUBMIT |
| 02/11/2025 | COMMERCIAL REVIEW - FULL v.1 | 03/13/2025 | REQUIRES RESUBMIT |
| 08/28/2025 | COMMERCIAL REVIEW - FULL REVISION v.2 | 09/03/2025 | APPROVED |
| 05/14/2024 | COMMERCIAL REVIEW - LIMITED v.2 | 05/29/2024 | APPROVED |
| 04/22/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 05/07/2024 | REQUIRES RESUBMIT |
| 03/14/2025 | COMMERCIAL REVIEW - FULL v.2 | 03/17/2025 | APPROVED |
| 07/31/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 08/25/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0424-00685
Permit Status: Issued
Permit Description: Open Office area's height for multi-purpose option. Includes ceiling & associated mech, elec REV1: expanding area of work and installing equipment, self-contained chemical storage in the private yard
REV2: The additional scope that includes expanding the area of work to house new equipment and adding a new unisex shower, janitor’s closet with a mop sink, and a new storage closet. This revision includes the architectural, mechanical, and electrical improvements required for the updated scope.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/29/2024 | AIR BALANCING REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-0424-00685
Permit Status: Issued
Permit Description: Open Office area's height for multi-purpose option. Includes ceiling & associated mech, elec REV1: expanding area of work and installing equipment, self-contained chemical storage in the private yard
REV2: The additional scope that includes expanding the area of work to house new equipment and adding a new unisex shower, janitor’s closet with a mop sink, and a new storage closet. This revision includes the architectural, mechanical, and electrical improvements required for the updated scope.
| Date | Description | Comments |
|---|---|---|
| 05/06/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0424-00685
Permite Description: Open Office area's height for multi-purpose option. Includes ceiling & associated mech, elec REV1: expanding area of work and installing equipment, self-contained chemical storage in the private yard
REV2: The additional scope that includes expanding the area of work to house new equipment and adding a new unisex shower, janitor’s closet with a mop sink, and a new storage closet. This revision includes the architectural, mechanical, and electrical improvements required for the updated scope.
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/24/2025 | COT - LCEL - Electrical Underground | N/A | Partial Pass | 11-24-25: verified electrical underground conduit, ground rods & 3/0 copper at 30" below grade for HazMat container located at exterior northwest corner of building. Okay to backfill progress areas with the use of shading materials and continue with cons at progress areas. |
| 02/25/2026 | COT - LCEL - Electrical Final | N/A | Re-inspection required | 2-25-26: install permanent label on panel CP1. |
| 02/25/2026 | COT - LCME - Mechanical Final | N/A | Re-inspection required | 2-25-26: pookie exhaust and wrap at warehouse, seal penetration at east wall into next door suite at warehouse, complete air compressor copper tie at warehouse and add vertical & horizontal supports on copper line, warehouse missing hose at mop sink. |
| 12/22/2025 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | 12-22-25: partial pass-okay to continue with construction at quality control & shipping/receiving areas. |
| 12/22/2025 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | 12-22-25: partial pass-okay to continue with construction at quality control & shipping/receiving areas. |
| 01/21/2026 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | 1-21-26: canceled by contractor. |
| 01/26/2026 | COT - LCEL - Electrical Intermediate | N/A | Re-inspection required | 1-26-26: label all junction boxes above ceiling, hot copper water lines 3/4" or larger must be insulation with minimum of R3, add 10 mil tape to all locations where copper lines are in contact with seismic wires, provide supports to copper lines that are resting directly on top of ceiling grid (supports attached directly to the ceiling grid is not allowed). Reschedule inspection when corrections are made. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0424-00685
Permit Description: Open Office area's height for multi-purpose option. Includes ceiling & associated mech, elec REV1: expanding area of work and installing equipment, self-contained chemical storage in the private yard
REV2: The additional scope that includes expanding the area of work to house new equipment and adding a new unisex shower, janitor’s closet with a mop sink, and a new storage closet. This revision includes the architectural, mechanical, and electrical improvements required for the updated scope.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/25/2025 | BULD - Electrical Clearance | Passed | 2705 E. Medina STE 111-2. (meter #2) | |
| 09/17/2025 | PDSD Building Division - Demo - Final | Passed | 9-17-25: demo final approved. | |
| 09/19/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 9-19-25: reinforcement at pour back sections in Area B verified per plans-okay for concrete placement at progress areas. | |
| 12/22/2025 | COT - LCBU - Framing | Passed | 12-22-25: framing approved. | |
| 01/21/2026 | COT - LCEL - Electrical Underground | Passed | 1-21-26: approved. | |
| 02/25/2026 | COT - FCON - Sprinkler - Final | Passed | passed on 7/10/2024 | |
| 02/25/2026 | COT - LCEL - Electrical Above Ceiling | Passed | 2-25-26: approved. | |
| 02/25/2026 | COT - LCME - Mechanical Intermediate | Passed | 2-25-26: approved. | |
| 02/25/2026 | COT - LCPL - Plumbing Intermediate | Passed | 2-25-26: approved. | |
| 02/25/2026 | COT - LCEL - Electrical Intermediate | Passed | 2-25-26: approved. |