Inspection Status: Partial Pass

Inspection History: COT - LCME - Mechanical Intermediate

Date Description Inspector Results Comments
01/09/2026 COT - LCME - Mechanical Intermediate Partial Pass 1-9-26: mechanical & electrical above ceiling at coating room 1 & breezeway in Area C approved. Okay to install tiles & hard grid.
01/21/2026 COT - LCME - Mechanical Intermediate Canceled 1-21-26: canceled by contractor.
01/26/2026 COT - LCME - Mechanical Intermediate Partial Pass 1-26-26: partial pass-worker on site working on supports.
02/05/2026 COT - LCME - Mechanical Intermediate Partial Pass 2-5-26: okay to cover progress areas at ceiling. Install registers and will verify above ceiling at finals.
02/25/2026 COT - LCME - Mechanical Intermediate Passed 2-25-26: approved.
12/17/2025 COT - LCME - Mechanical Intermediate Re-inspection required 12-17-25: copper air line, fire sprinkler, together with condensation copper line above ceiling cannot be in contact with other metals-add 10 mil tape or install copper hangers, add insulation around pookie joints, replace/add duct hanger on south end of shipping/receiving/control area.
12/22/2025 COT - LCME - Mechanical Intermediate Partial Pass 12-22-25: partial pass-okay to continue with construction at quality control & shipping/receiving areas.