Inspection Status: Partial Pass
Inspection History: COT - LCME - Mechanical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 01/09/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
1-9-26: mechanical & electrical above ceiling at coating room 1 & breezeway in Area C approved. Okay to install tiles & hard grid. |
| 01/21/2026 |
COT - LCME - Mechanical Intermediate |
|
Canceled |
1-21-26: canceled by contractor. |
| 01/26/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
1-26-26: partial pass-worker on site working on supports. |
| 02/05/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
2-5-26: okay to cover progress areas at ceiling. Install registers and will verify above ceiling at finals. |
| 02/25/2026 |
COT - LCME - Mechanical Intermediate |
|
Passed |
2-25-26: approved. |
| 12/17/2025 |
COT - LCME - Mechanical Intermediate |
|
Re-inspection required |
12-17-25: copper air line, fire sprinkler, together with condensation copper line above ceiling cannot be in contact with other metals-add 10 mil tape or install copper hangers, add insulation around pookie joints, replace/add duct hanger on south end of shipping/receiving/control area. |
| 12/22/2025 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
12-22-25: partial pass-okay to continue with construction at quality control & shipping/receiving areas. |