Inspection Status: Canceled

Inspection History: COT - LCPL - Plumbing Intermediate 

Permit Number - TC-COM-0424-00685

Inspection Description - COT - LCPL - Plumbing Intermediate 

Inspection Status - Canceled

Date Description Inspector Results Comments
01/21/2026 COT - LCPL - Plumbing Intermediate  Canceled 1-21-26: canceled by contractor.
01/26/2026 COT - LCPL - Plumbing Intermediate  Re-inspection required 1-26-26: label all junction boxes above ceiling, hot copper water lines 3/4" or larger must be insulation with minimum of R3, add 10 mil tape to all locations where copper lines are in contact with seismic wires, provide supports to copper lines that are resting directly on top of ceiling grid (supports attached directly to the ceiling grid is not allowed). Reschedule inspection when corrections are made.
02/05/2026 COT - LCPL - Plumbing Intermediate  Partial Pass 2-5-26: corrections made-okay to cover progress areas at ceiling.
02/25/2026 COT - LCPL - Plumbing Intermediate  Passed 2-25-26: approved.
05/29/2025 COT - LCPL - Plumbing Intermediate  Not Ready
09/17/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 9-17-25: new underground plumbing for a new shower & water station located at Area B approved-Okay to backfill progress areas.