Permit: TC-COM-0423-01074
Permit Details
Apply Date:
04/18/2023
Applicant:
Alexis Alvarez
Description:
NSTALL (2) SOLAR CARPORTS INSTALL (1) TRANSFORMER INSTALL WALL-MOUNTED PV EQUIPMENT INSTALL (10) CARPORT MOUNTED LIGHTS
Permit Reviews
Permit Number - TC-COM-0423-01074
Permit Status: Issued
Permit Description: NSTALL (2) SOLAR CARPORTS
INSTALL (1) TRANSFORMER
INSTALL WALL-MOUNTED PV EQUIPMENT
INSTALL (10) CARPORT MOUNTED LIGHTS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/22/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/22/2023 | REQUIRES RESUBMIT |
| 02/16/2024 | COMMERCIAL REVIEW - FULL v.6 | 03/19/2024 | REQUIRES RESUBMIT |
| 06/13/2024 | COMMERCIAL REVIEW - FULL v.8 | 07/16/2024 | APPROVED |
| 09/30/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/30/2025 | REQUIRES RESUBMIT |
| 04/09/2024 | COMMERCIAL REVIEW - FULL v.7 | 05/08/2024 | REQUIRES RESUBMIT |
| 11/24/2023 | COMMERCIAL REVIEW - FULL v.5 | 12/20/2023 | REQUIRES RESUBMIT |
| 05/11/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/12/2023 | REQUIRES RESUBMIT |
| 09/19/2024 | COMMERCIAL REVIEW - FULL v.1 | 10/14/2024 | APPROVED |
| 07/16/2024 | RESTAMP - COMMERCIAL v.1 | 07/22/2024 | APPROVED |
| 07/18/2023 | COMMERCIAL REVIEW - FULL v.3 | 07/18/2023 | REQUIRES RESUBMIT |
| 07/20/2023 | COMMERCIAL REVIEW - FULL v.4 | 08/15/2023 | REQUIRES RESUBMIT |
| 10/15/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 10/15/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0423-01074
Permit Status: Issued
Permit Description: NSTALL (2) SOLAR CARPORTS
INSTALL (1) TRANSFORMER
INSTALL WALL-MOUNTED PV EQUIPMENT
INSTALL (10) CARPORT MOUNTED LIGHTS
| Date | Description | Comments |
|---|---|---|
| 07/25/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
| 09/30/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 07/22/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 07/25/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 07/25/2024 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
| 07/25/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
| 07/25/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0423-01074
Permite Description: NSTALL (2) SOLAR CARPORTS
INSTALL (1) TRANSFORMER
INSTALL WALL-MOUNTED PV EQUIPMENT
INSTALL (10) CARPORT MOUNTED LIGHTS
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/09/2025 | COT - CSOL - Electrical Underground Solar Project | N/A | Partial Pass | |
| 04/16/2025 | COT - CSOL - Grounding/Bonding Solar Project | N/A | Not Applicable | duplicate |
| 04/22/2025 | BULD - Electrical Clearance | N/A | Partial Pass | Partial pass. Verbal clearance to TEP RECN. Scope of work is not completed. Had to re energize building. 4/22/2025 |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0423-01074
Permit Description: NSTALL (2) SOLAR CARPORTS
INSTALL (1) TRANSFORMER
INSTALL WALL-MOUNTED PV EQUIPMENT
INSTALL (10) CARPORT MOUNTED LIGHTS
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/16/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Approved last of the structure column foundations with ufer, okay for concrete placement | |
| 04/16/2025 | COT - CSOL - Electrical Underground Solar Project | Passed | Approved electrical conduits from transformer and equipment location to structure 1 and structure 2, okay to shade fill progress areas | |
| 06/12/2025 | COT - LCBU - Building Final | Passed | Contact: JT (928)965-6296 inspection at 8:00pm | |
| 06/12/2025 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 06/12/2025 | COT - LCBU - Framing | Passed | Contact: JT (928)965-6296 inspection at 8:00pm Framing will be submitted and approved per third party reports. 6/12/2025 |
|
| 06/12/2025 | COT - LCEL - Electrical Final | Passed | Contact: JT (928)965-6296 inspection at 8:00pm | |
| 06/12/2025 | COT - CSOL - Outdoor Lighting Solar Project | Passed | ||
| 06/12/2025 | COT - CSOL - Electrical Intermediate Solar Project | Passed | Contact: JT (928)965-6296 inspection at 8:00pm | |
| 06/12/2025 | BULD - Electrical Clearance | Passed | Clearance for TEP DGC. 6/12/2025 |