Permit: TC-COM-0223-00641
Permit Details
Apply Date:
02/14/2023
Applicant:
Brett Daugherty
Description:
New Office building with attached shade canopy
Permit Reviews
Permit Number - TC-COM-0223-00641
Permit Status: Complete
Permit Description: New Office building with attached shade canopy
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/02/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 07/02/2024 | REQUIRES RESUBMIT |
| 07/08/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 07/10/2024 | APPROVED |
| 06/07/2023 | COMMERCIAL REVIEW - FULL v.4 | 06/22/2023 | REQUIRES RESUBMIT |
| 07/26/2023 | COMMERCIAL REVIEW - FULL v.6 | 07/27/2023 | APPROVED |
| 03/01/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/17/2023 | REQUIRES RESUBMIT |
| 04/20/2023 | COMMERCIAL REVIEW - FULL v.3 | 05/23/2023 | REQUIRES RESUBMIT |
| 05/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/17/2024 | REQUIRES RESUBMIT |
| 05/22/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 05/23/2024 | REQUIRES RESUBMIT |
| 07/12/2023 | COMMERCIAL REVIEW - FULL v.5 | 07/20/2023 | REQUIRES RESUBMIT |
| 07/27/2023 | RESTAMP - COMMERCIAL v.1 | 07/31/2023 | APPROVED |
| 07/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/01/2024 | REQUIRES RESUBMIT |
| 05/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/28/2024 | APPROVED |
| 05/28/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 05/28/2024 | APPROVED |
| 04/13/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/13/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0223-00641
Permit Status: Complete
Permit Description: New Office building with attached shade canopy
| Date | Description | Comments |
|---|---|---|
| 05/28/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 04/10/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 04/10/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0223-00641
Permite Description: New Office building with attached shade canopy
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2023 | COT - HCBU - Framing | N/A | Not Ready | 12/12/23: not ready |
| 12/12/2023 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 12/12/23: 30' of 4" PVC underground conduit per plan form building to property fence pending 15' run to transformer. Ok to backfill progress area. 120' of 4" PVC underground conduit from property fence on southwest end to proposed new building on neighboring lot (pending revised plans to add new structure) ok to back fill progress area. |
| 12/27/2023 | COT - HCPL - Plumbing Progress | N/A | Re-inspection required | This is an underground plumbing inspection: Main building underground sewer is complete and under water test. Repair garage underground sewer for restroom and vehicle wash drain is completed and under water test. Both underground's are holding water with no leaks. Okay to shade pipes and backfill trenches. 12/12/23: yard water line per plan ok to back fill, sewer connection under test ok to back fill. 12/27/23: tracer wire for oil separator missing, sample box missing per plan at oil separator. |
| 08/30/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 8/30/23: all footers are to schedule ok to be poured |
| 12/12/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 12/12/23: 30' of 4" PVC underground conduit per plan form building to property fence pending 15' run to transformer. Ok to backfill progress area. 120' of 4" PVC underground conduit from property fence on southwest end to proposed new building on neighboring lot (pending revised plans to add new structure) ok to back fill progress area. |
| 05/10/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 04/09/2024 | COT - HCBU - Building Progress | N/A | Partial Pass | 2/7/24 Partial for drywall nailing, ok for tape & texture 4/9/24:framing passed in tire/parts storage ok to drywall and texture, |
| 05/13/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Ok for Level 4 TCO. Will need to add Knox Box near entrance gate. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0223-00641
Permit Description: New Office building with attached shade canopy
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/04/2023 | COT - HCEL - Electrical Progress | Passed | ufer | |
| 10/04/2023 | COT - HCBU - Preslab | Passed | ||
| 12/12/2023 | COT - HCPL - Sewer | Passed | 12/12/23: sewer connection per plan ok to backfill. | |
| 12/12/2023 | COT - HCPL - Yard Water Line | Passed | 12/12/23: water line per plan and under pressure ok to backfill. | |
| 01/22/2024 | COT - HCBU - Framing | Passed | ||
| 01/22/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 01/22/2024 | COT - HCPL - Plumbing Progress | Passed | ||
| 04/01/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
| 04/09/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 8/30/23: all footers are to schedule ok to be poured 9/5/23: all AB1-AB2 have anchor bolts embedded per Schedule. Ok to proceed 4/9/24: trash enclosure reinforcement per plan ok to grout. |
|
| 04/18/2024 | COT - HCEL - Electrical Underground | Passed | ||
| 04/25/2024 | BULD - Electrical Clearance | Passed | Please supply letter of torque for cables in CT and disconnect 4/25/24: ECO TEP CLEARANCE for 3381 E WESTCO PL |
|
| 05/10/2024 | COT - HCBU - Building Progress | Passed | ||
| 05/10/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 05/10/2024 | COT - HCBU - Roof Nailing | Passed | ||
| 05/10/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 05/10/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 05/10/2024 | COT - HCME - Mechanical Progress | Passed | ||
| 05/10/2024 | COT - LCBU - Building Progress | Passed | ||
| 05/10/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 05/10/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 05/10/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 05/16/2024 | COT - HCEL - Electrical Final | Passed | ||
| 05/16/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 05/16/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 05/16/2024 | COT - HCME - Mechanical Final | Passed | ||
| 05/16/2024 | COT - HCBU - CofO | Passed | ||
| 05/16/2024 | COT - HCBU - Building Final | Passed | 5/10/24: ADA requirements not met at restrooms, Insulation required on exterior hose bib, copper piping in contact with dissimilar material must be protected. conditions must be satisfied prior to building final, (Engineering final, Fire final, ROW final) all must be passed prior to building final. 5/15/24: per -previous notes 5/16/24: Ok for CofO |
|
| 05/16/2024 | ENGR Engineering Final | Passed | ||
| 05/21/2024 | COT - FCON - Fire - Final | Passed |